330-330 1/2 N SERRANO AVE 90004
Certificate Information: 330-330 1/2 N SERRANO AVE 90004
- Application / Permit
- 19010-20000-05334
- Plan Check / Job No.
- B19VN20732
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 2-STORY DUPLEX WITH BASEMENT AND ATTACHED GARAGE (FRONT BUILDING); EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 8/27/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/26/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/26/2019 | SELLA BENYAMIN |
| Green Plans Picked Up | 12/31/2019 | APPLICANT |
| Corrections Issued | 1/3/2020 | SELLA BENYAMIN |
| Quality Review Completed | 1/10/2020 | STEVEN KIM |
| Building Plans Picked Up | 1/14/2020 | APPLICANT |
| Applicant returned to address corrections | 2/20/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/3/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/12/2020 | SELLA BENYAMIN |
| Plan Check Approved | 4/7/2020 | SELLA BENYAMIN |
| Plan Check Approved | 8/12/2020 | JASON JANGADA |
| Plan Check Approved | 8/12/2020 | SELLA BENYAMIN |
| Issued | 8/27/2020 | APPLICANT |
| CofO in Progress | 11/17/2021 | MASHEL JONGERT |
| Permit Finaled | 11/29/2021 | DEROLD HAUFF |
| CofO Issued | 11/29/2021 | DEROLD HAUFF |
| Permit Finaled | 11/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/3/2020 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 2/3/2020 | JOHN TRIANTAFYLLOS |
| Permit | Cleared | 2/3/2020 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 2/3/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/7/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 2/14/2020 | AARON COSTA |
| Trees in Parkway | Cleared | 2/14/2020 | JOHN KIM |
| Low Impact Development | Cleared | 2/20/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 2/21/2020 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2020 | Conditional Approval | JOSEPH MCGARRY |
| Underground Mechanical | 10/21/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 10/26/2020 | Approved | ARTHUR SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Steel/Welding | 11/24/2020 | No Access for Inspection | ELMER BLAND |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/5/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 1/19/2021 | Partial Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 3/9/2021 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 3/10/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 3/15/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Wood Frame | 3/15/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/19/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Deck | 3/19/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 3/19/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 3/19/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Shower Pan | 3/19/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 3/30/2021 | Conditional Approval | JOSEPH MCGARRY |
| Insulation | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/30/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 3/30/2021 | Approved | JOSEPH MCGARRY |
| Insulation | 4/1/2021 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 4/6/2021 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 8/10/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| HVAC-Final | 8/10/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/10/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 8/23/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 8/23/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 11/9/2021 | Corrections Issued | MASHEL JONGERT |
| Final | 11/16/2021 | Corrections Issued | MASHEL JONGERT |
| Final | 11/17/2021 | OK to Issue CofO | MASHEL JONGERT |