8427 N ENCINO AVE 91325

Certificate Information: 8427 N ENCINO AVE 91325

Application / Permit
19010-20000-05285
Plan Check / Job No.
B19VN20578
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32' X 53' IRREGULAR SHAPE DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 1/25/2023
Issuing Office
Valley
Current Status
CofO Issued on 1/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2019 APPLICANT
Assigned to Plan Check Engineer 12/19/2019 PARISA ZAHABI
Corrections Issued 12/27/2019 PARISA ZAHABI
Green Plans Picked Up 12/31/2019 APPLICANT
Quality Review Completed 1/6/2020 OMID HEDAYAT
Building Plans Picked Up 1/8/2020 APPLICANT
Applicant returned to address corrections 4/22/2022 SELLA BENYAMIN
Plan Check Approved 5/17/2022 SELLA BENYAMIN
Issued 1/25/2023 APPLICANT
CofO in Progress 12/23/2024 JAVIER RAMOS JR
Permit Finaled 1/24/2025 RUBEN SALAS
CofO Issued 1/24/2025 RUBEN SALAS
Permit Finaled 1/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/27/2020 GABRIEL ROBLES
Trees in Parkway Cleared 3/4/2020 JOHN KIM
Construction near power lines Cleared 5/2/2020 RIDWAN HARDY
Low Impact Development Cleared 9/16/2021 JORGE MEJIA LEMUS
Permit Cleared 9/21/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 9/27/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 9/28/2021 CARLOS AGUILERA
Sewer availability Cleared 9/28/2021 CARLOS AGUILERA
Hydrant and Access approval Cleared 1/11/2022 MATTHEW CRAIG

Contact Information

Contractor Owner-Builder       ,
Engineer Motavvef,, Nasser; Lic. No.: C40977 15335 MORRISON ST 370      SHERMAN OAKS, CA 91403

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/23/2023 Corrections Issued JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 11/27/2023 Approved JAVIER RAMOS JR
PLUMBING-Rough 11/27/2023 Partial Approval JAVIER RAMOS JR
Pre-Inspection 11/27/2023 Approved JAVIER RAMOS JR
Sewer 11/27/2023 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 3/5/2024 Corrections Issued JAVIER RAMOS JR
Deputy Wood Construction 3/14/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 4/2/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 4/2/2024 Approved JAVIER RAMOS JR
Green Building Rough 4/2/2024 Approved JAVIER RAMOS JR
HVAC-Rough 4/2/2024 Approved JAVIER RAMOS JR
PLUMBING-Rough 4/2/2024 Approved JAVIER RAMOS JR
Shower Pan 4/2/2024 Approved JAVIER RAMOS JR
Underground Mechanical 4/2/2024 Approved JAVIER RAMOS JR
Drywall Nailing 9/30/2024 Approved JAVIER RAMOS JR
Final 9/30/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 9/30/2024 Approved JAVIER RAMOS JR
Green Building Final 9/30/2024 Approved JAVIER RAMOS JR
HVAC-Final 9/30/2024 Approved JAVIER RAMOS JR
PLUMBING-Final 9/30/2024 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 9/30/2024 SGSOV Not Required JAVIER RAMOS JR
Service/Power Release 9/30/2024 Not Ready for Inspection JAVIER RAMOS JR
Smoke Detectors 9/30/2024 Approved JAVIER RAMOS JR
Final 12/2/2024 Not Ready for Inspection MICHAEL CORTEZ
Service/Power Release 12/2/2024 Not Ready for Inspection MICHAEL CORTEZ
ELECTRICAL-Final 12/23/2024 Approved JAVIER RAMOS JR
Final 12/23/2024 OK to Issue CofO JAVIER RAMOS JR
Service/Power Release 12/23/2024 Approved JAVIER RAMOS JR