8255 W OAKWOOD AVE 90048
Certificate Information: 8255 W OAKWOOD AVE 90048
- Application / Permit
- 19010-20000-05277
- Plan Check / Job No.
- B19VN20549
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (83'-8"x 41'-0") IRR SHAPE THREE STORY SINGLE FAMILY DWELLING WITH ATTACHED 2- CAR GARAGE. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/8/2020
- Issuing Office
- Current Status
- CofO Issued on 12/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 12/5/2019 | TROY DEGUZMAN |
| Green Plans Picked Up | 12/5/2019 | APPLICANT |
| Corrections Issued | 12/13/2019 | TROY DEGUZMAN |
| Quality Review Completed | 12/13/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/16/2019 | APPLICANT |
| Applicant returned to address corrections | 2/12/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/6/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 3/17/2020 | TROY DEGUZMAN |
| Plan Check Approved | 3/27/2020 | TROY DEGUZMAN |
| Issued | 4/8/2020 | APPLICANT |
| CofO in Progress | 12/14/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 12/21/2021 | RONALD MYRICK |
| CofO Issued | 12/21/2021 | RONALD MYRICK |
| Permit Finaled | 12/21/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 1/3/2020 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2020 | ELAINE LEI |
| Permit | Cleared | 1/3/2020 | ELAINE LEI |
| Sewer availability | Cleared | 1/3/2020 | ELAINE LEI |
| Low Impact Development | Cleared | 2/10/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/10/2020 | JEANIE LAM |
| Green Code | Cleared | 2/11/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 2/11/2020 | GEORGE SUCHAND |
| GPI Written Notices | Cleared | 3/6/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 3/6/2020 | TROY DEGUZMAN |
| Trees in Parkway | Cleared | 3/18/2020 | JOHN KIM |
Contact Information
| Architect | Brumer,, Aaron Jason; Lic. No.: C30005 | 10999 RIVERSIDE DRIVE SUITE 300 STUDIO CITY, CA 91602 |
| Contractor | Noesis Builders Inc; Lic. No.: 1046562-B | 8383 WILSHIRE BOULEVARD SUITE 740 BEVERLY HILLS, CA 90211 |
| Engineer | Choi,, David; Lic. No.: S4784 | 1327 LOMA AVENUE LONG BEACH, CA 90804 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/27/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 5/28/2020 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 5/28/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 5/28/2020 | Approved | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 6/15/2020 | Partial Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 6/15/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Steel/Welding | 7/9/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 7/14/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 8/25/2020 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/5/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2020 | Partial Approval | MICHAEL PELHAM |
| Insulation | 10/19/2020 | Partial Approval | MICHAEL PELHAM |
| HVAC-Rough | 11/5/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 11/6/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 11/30/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 12/24/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/31/2020 | No Access for Inspection | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/5/2021 | Partial Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 1/26/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 1/26/2021 | Approved | CHRIS CHRISTENSEN |
| Insulation | 1/26/2021 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 1/26/2021 | Partial Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/5/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Test | 7/29/2021 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 8/13/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 8/17/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 8/18/2021 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 9/1/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Final | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| METHANE-Rough | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 9/1/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 9/1/2021 | Approved | CHRIS CHRISTENSEN |
| Verify Rec and Parks Fee Memo | 12/2/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 12/3/2021 | Conditional Approval | CHRIS CHRISTENSEN |
| Final | 12/13/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |