13180 W TERRA BELLA ST 91331

Certificate Information: 13180 W TERRA BELLA ST 91331

Application / Permit
19010-20000-05271
Plan Check / Job No.
B19VN20534
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40' X 29' IRREGULAR SHAPE ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 2/25/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/11/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 ROSENDO MEDINA
Corrections Issued 12/10/2019 ROSENDO MEDINA
Quality Review Completed 12/10/2019 GUANG MIN TUNG
Building Plans Picked Up 12/11/2019 APPLICANT
Green Plans Picked Up 12/11/2019 APPLICANT
Applicant returned to address corrections 1/22/2020 ROSENDO MEDINA
Plan Check Approved 1/29/2020 ROSENDO MEDINA
Issued 2/25/2020 LADBS
CofO in Progress 7/2/2020 MICHEL ABAJAN
CofO Issued 7/11/2020 MICHAEL SMITH
Permit Finaled 7/11/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/17/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/17/2019 CELINA MORENO
Hydrant and Access approval Cleared 12/17/2019 ROBERT DUFF
Sewer availability Cleared 12/17/2019 CELINA MORENO
Green Code Cleared 1/13/2020 AARON COSTA
ZI Cleared 1/14/2020 RICHARD REASER
Low Impact Development Cleared 1/16/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/16/2020 ERIK BEASLEY

Contact Information

Architect Kivotos,, Juan M; Lic. No.: C26491 1323 N NIAGARA STREET      BURBANK, CA 91505
Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/4/2020 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 3/10/2020 Partial Approval MICHEL ABAJAN
METHANE-Subgrade 3/18/2020 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/23/2020 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 3/23/2020 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Barrier 3/23/2020 Not Ready for Inspection JENNIFER RABUCHIN
METHANE-Subgrade 3/23/2020 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 4/7/2020 Approved MICHEL ABAJAN
METHANE-Barrier 4/7/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 4/7/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/9/2020 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/20/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 4/20/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Rough 4/20/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/20/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/24/2020 Approved MICHEL ABAJAN
HVAC-Rough 4/24/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 4/24/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/29/2020 Approved MICHEL ABAJAN
Green Building Rough 4/29/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 4/29/2020 Approved MICHEL ABAJAN
Insulation 5/4/2020 Approved MICHEL ABAJAN
Drywall Nailing 5/6/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 6/10/2020 Approved MICHEL ABAJAN
Final 6/10/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 6/10/2020 Approved MICHEL ABAJAN
HVAC-Final 6/10/2020 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Final 6/10/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/10/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 6/10/2020 Approved MICHEL ABAJAN
Smoke Detectors 6/10/2020 Not Ready for Inspection MICHEL ABAJAN
Final 6/22/2020 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 6/22/2020 Approved MICHEL ABAJAN
PLUMBING-Final 6/22/2020 Conditional Approval MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 6/22/2020 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 6/22/2020 Approved MICHEL ABAJAN
Final 7/2/2020 OK to Issue CofO MICHEL ABAJAN
PLUMBING-Final 7/2/2020 Approved MICHEL ABAJAN