13958 W DAVENTRY ST 91331

Certificate Information: 13958 W DAVENTRY ST 91331

Application / Permit
19010-20000-05240
Plan Check / Job No.
B19VN20380
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 32'-0" X 40'-0" DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229 W/ 8'-0" X 10'-2" FRONT PORCH. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 JENNIFER LEE
Corrections Issued 12/10/2019 JENNIFER LEE
Quality Review Completed 12/11/2019 STEVEN KIM
Building Plans Picked Up 12/11/2019 APPLICANT
Green Plans Picked Up 12/11/2019 APPLICANT
Applicant returned to address corrections 1/29/2020 JENNIFER LEE
Plan Check Approved 3/3/2020 JENNIFER LEE
Issued 3/4/2020 LADBS
CofO in Progress 8/10/2020 MICHEL ABAJAN
CofO Issued 8/29/2020 MICHAEL SMITH
Permit Finaled 8/29/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/17/2019 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/17/2019 CELINA MORENO
Hydrant and Access approval Cleared 12/17/2019 ROBERT DUFF
Sewer availability Cleared 12/17/2019 CELINA MORENO
Green Code Cleared 1/16/2020 DAVID MATSON
Low Impact Development Cleared 1/16/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 1/16/2020 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,
Engineer Yogurtian,, Arpinee; Lic. No.: C49916 2529 FOOTHILL BLVD, STE 208      LA CRESCENTA, CA 91214

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/20/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/6/2020 Partial Approval MICHEL ABAJAN
METHANE-Rough 4/6/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 4/6/2020 Partial Approval MICHEL ABAJAN
Sewer 4/6/2020 Approved MICHEL ABAJAN
Underground Mechanical 4/6/2020 Partial Approval MICHEL ABAJAN
Verify Sprinkler Sign Off 4/6/2020 Approved MICHEL ABAJAN
Wood Frame 5/14/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/26/2020 Approved MICHEL ABAJAN
HVAC-Rough 5/26/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 5/26/2020 Approved MICHEL ABAJAN
Underground Mechanical 5/26/2020 Partial Approval MICHEL ABAJAN
Insulation 5/29/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/29/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/2/2020 Approved MICHEL ABAJAN
Green Building Rough 6/2/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 7/21/2020 Approved MICHEL ABAJAN
Final 7/21/2020 Not Ready for Inspection MICHEL ABAJAN
Footing/Foundation/Slab 7/21/2020 Approved MICHEL ABAJAN
Green Building Final 7/21/2020 Not Ready for Inspection MICHEL ABAJAN
METHANE-Barrier 7/21/2020 Approved MICHEL ABAJAN
METHANE-Subgrade 7/21/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/21/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 7/21/2020 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 7/21/2020 Not Ready for Inspection MICHEL ABAJAN
Pre-Inspection 7/24/2020 Partial Inspection MICHEL ABAJAN
ELECTRICAL-Final 8/10/2020 Approved MICHEL ABAJAN
Final 8/10/2020 OK to Issue CofO MICHEL ABAJAN
Green Building Final 8/10/2020 Approved MICHEL ABAJAN
HVAC-Final 8/10/2020 Approved MICHEL ABAJAN
PLUMBING-Final 8/10/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/10/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 8/10/2020 Approved MICHEL ABAJAN
Smoke Detectors 8/10/2020 Approved MICHEL ABAJAN