9443 N DORRINGTON AVE 91331

Certificate Information: 9443 N DORRINGTON AVE 91331

Application / Permit
19010-20000-05223
Plan Check / Job No.
B19VN20331
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 29'-0" X 41'-3" ONE STORY DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 ARTIN ZARUKIAN
Corrections Issued 11/30/2019 ARTIN ZARUKIAN
Quality Review Completed 12/3/2019 GUANG MIN TUNG
Building Plans Picked Up 12/19/2019 APPLICANT
Green Plans Picked Up 12/19/2019 APPLICANT
Plan Check Approved 2/4/2020 ARTIN ZARUKIAN
Issued 2/11/2020 LADBS
CofO in Progress 9/14/2020 MICHEL ABAJAN
CofO Issued 9/23/2020 MICHAEL SMITH
Permit Finaled 9/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/22/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/22/2020 GABRIEL ROBLES
Low Impact Development Cleared 1/22/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/22/2020 GABRIEL ROBLES
Sewer availability Cleared 1/22/2020 GABRIEL ROBLES
Green Code Cleared 1/24/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 1/30/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/14/2020 Partial Inspection MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 3/18/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/2/2020 Partial Approval MICHEL ABAJAN
PLUMBING-Rough 4/2/2020 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 4/29/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 4/29/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 4/29/2020 Partial Approval MICHEL ABAJAN
Green Building Rough 4/29/2020 Approved MICHEL ABAJAN
HVAC-Rough 4/29/2020 Approved MICHEL ABAJAN
PLUMBING-Rough 4/29/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 4/29/2020 Approved MICHEL ABAJAN
Insulation 5/12/2020 Approved MICHEL ABAJAN
Shower Pan 5/12/2020 Approved MICHEL ABAJAN
Drywall Nailing 5/27/2020 Approved MICHEL ABAJAN
Final 8/17/2020 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 8/17/2020 Approved MICHEL ABAJAN
Green Building Final 8/17/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 8/17/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 8/17/2020 Approved MICHEL ABAJAN
Smoke Detectors 8/17/2020 Approved MICHEL ABAJAN
Final 9/1/2020 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/1/2020 SGSOV Not Ready MICHEL ABAJAN
ELECTRICAL-Final 9/14/2020 Approved MICHEL ABAJAN
Final 9/14/2020 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 9/14/2020 Approved MICHEL ABAJAN
PLUMBING-Final 9/14/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Approved MICHEL ABAJAN