17527 W BURBANK BLVD 91316

Certificate Information: 17527 W BURBANK BLVD 91316

Application / Permit
19010-20000-05214
Plan Check / Job No.
B19VN20268
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 39' 6" X 40' IRR.-SHAPE ACCESSORY DWELLING UNIT W/ ATTACHED 18' X 18' 2-CAR GARAGE PER AB 494 AND SB 229. ALL WORK DONE PER WOOD FRAME PRESCRIPTIVE PROVISIONS.
Permit Issued
Issued on 1/2/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 GURUNATH NESARAJAH
Corrections Issued 11/28/2019 GURUNATH NESARAJAH
Quality Review Completed 12/3/2019 GUANG MIN TUNG
Building Plans Picked Up 12/5/2019 APPLICANT
Green Plans Picked Up 12/12/2019 APPLICANT
Plan Check Approved 1/2/2020 GURUNATH NESARAJAH
Plan Check Approved 1/2/2020 GURUNATH NESARAJAH
Issued 1/2/2020 LADBS
CofO in Progress 7/7/2020 MICHAEL SMITH
Permit Finaled 7/9/2020 DONALD SUNSERI
CofO Issued 7/9/2020 DONALD SUNSERI
Permit Finaled 7/9/2020 DONALD SUNSERI

Permit Application Clearance Information

ZI Cleared 12/17/2019 HERMINIGILDO AGUSTIN
Green Code Cleared 12/19/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 12/20/2019 GEORGE SUCHAND
Low Impact Development Cleared 12/24/2019 ANDRES COVARRUBIAS
Address approval Cleared 12/30/2019 LEE GUILBEAUX
Construction near power lines Cleared 12/30/2019 WALTER RAMIREZ
Eng Process Fee Ord 176,300 Cleared 12/30/2019 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 12/30/2019 LEE GUILBEAUX
Sewer availability Cleared 12/30/2019 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/13/2020 Approved STEVEN BACK
PLUMBING-Rough 2/13/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/17/2020 Not Ready for Inspection STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Approved STEVEN BACK
ELECTRICAL-Rough 4/9/2020 Approved STEVEN BACK
PLUMBING-Rough 4/9/2020 Approved STEVEN BACK
Special/Order Compliance 4/9/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 4/15/2020 Partial Approval STEVEN BACK
Green Building Rough 4/15/2020 Approved STEVEN BACK
HVAC-Rough 4/15/2020 Approved STEVEN BACK
MERV13>=Rough 4/15/2020 Approved STEVEN BACK
Verify Sprinkler Sign Off 4/15/2020 Not Ready for Inspection STEVEN BACK
Insulation 4/20/2020 Corrections Issued STEVEN BACK
BUILDING-Rough-Frame 4/23/2020 Approved STEVEN BACK
Insulation 4/23/2020 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 4/24/2020 Approved STEVEN BACK
Insulation 4/24/2020 Approved STEVEN BACK
Special/Order Compliance 4/28/2020 Approved STEVEN BACK
Special/Order Compliance 4/29/2020 Approved STEVEN BACK
Drywall Nailing 5/5/2020 Approved STEVEN BACK
Final 6/18/2020 Corrections Issued STEVEN BACK
Green Building Final 6/18/2020 Not Ready for Inspection STEVEN BACK
MERV13>=Final 6/18/2020 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/18/2020 SGSOV Not Ready STEVEN BACK
Service/Power Release 6/18/2020 Corrections Issued STEVEN BACK
Smoke Detectors 6/18/2020 Approved STEVEN BACK
Final 6/24/2020 Not Ready for Inspection STEVEN BACK
Green Building Final 6/24/2020 Not Ready for Inspection STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/24/2020 SGSOV Approved STEVEN BACK
Service/Power Release 6/24/2020 Not Ready for Inspection STEVEN BACK
Final 7/1/2020 Corrections Issued STEVEN BACK
Green Building Final 7/1/2020 Approved STEVEN BACK
Service/Power Release 7/1/2020 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Final 7/7/2020 Approved STEVEN BACK
Final 7/7/2020 OK to Issue CofO STEVEN BACK
Service/Power Release 7/7/2020 Approved STEVEN BACK