15801 W COBALT ST 91342

Certificate Information: 15801 W COBALT ST 91342

Application / Permit
19010-20000-05201
Plan Check / Job No.
B19VN20143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 15'-9" X 12'-6" DETACHED REC ROOM WITH HALF BATHROOM
Permit Issued
Issued on 3/4/2021
Issuing Office
Current Status
CofO Issued on 11/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 SELLA BENYAMIN
Corrections Issued 12/19/2019 SELLA BENYAMIN
Quality Review Completed 12/27/2019 STEVEN KIM
Building Plans Picked Up 12/30/2019 APPLICANT
Green Plans Picked Up 12/30/2019 APPLICANT
Applicant returned to address corrections 1/22/2021 SELLA BENYAMIN
Plan Check Approved 3/3/2021 SELLA BENYAMIN
Issued 3/4/2021 APPLICANT
CofO in Progress 9/23/2021 JOHN HAYES
Permit Finaled 11/30/2021 MICHAEL SMITH
CofO Issued 11/30/2021 MICHAEL SMITH
Permit Finaled 11/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Sewer availability Cleared 8/11/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 8/12/2020 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 8/12/2020 LEE GUILBEAUX
Tract Map conditions Cleared 9/11/2020 KENTON TRINH
Roof/Waste drainage to street Cleared 10/23/2020 ADRIAN CASTRO
Construction near power lines Cleared 11/10/2020 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2021 Corrections Issued MISAEL ESPARZA
Sewer 4/7/2021 Approved MISAEL ESPARZA
Underground Mechanical 4/7/2021 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 4/14/2021 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 5/7/2021 Partial Approval MICHAEL TEMPLE
Green Building Rough 5/7/2021 Not Ready for Inspection MICHAEL TEMPLE
MERV13>=Rough 5/7/2021 Not Ready for Inspection MICHAEL TEMPLE
Rough-Elec/Plmb/HVAC 5/7/2021 Approved MICHAEL TEMPLE
Verify Sprinkler Sign Off 5/7/2021 Approved MICHAEL TEMPLE
BUILDING-Rough-Frame 5/17/2021 Corrections Issued MISAEL ESPARZA
Drywall Nailing 5/17/2021 Not Ready for Inspection MISAEL ESPARZA
Insulation 5/17/2021 Approved MISAEL ESPARZA
Masonry Wall/Backfill 5/17/2021 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/24/2021 Approved ARTHUR SARGSYAN
Insulation 5/24/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 6/8/2021 Approved MISAEL ESPARZA
Excavation/Setback/Form/Re-Bar 6/16/2021 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/6/2021 Approved MISAEL ESPARZA
Final 7/6/2021 Corrections Issued MISAEL ESPARZA
Green Building Final 7/6/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 7/6/2021 Approved MISAEL ESPARZA
MERV13>=Final 7/6/2021 Approved MISAEL ESPARZA
MERV13>=Rough 7/6/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 7/6/2021 Not Required MISAEL ESPARZA
Smoke Detectors 7/6/2021 Approved MISAEL ESPARZA
Final 7/19/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 7/19/2021 Not Ready for Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 7/19/2021 SGSOV Approved MISAEL ESPARZA
Final 7/26/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 7/26/2021 Not Ready for Inspection MICHEL ABAJAN
Final 8/13/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 8/13/2021 Approved MISAEL ESPARZA
Final 9/22/2021 OK to Issue CofO JOHN HAYES