3263 N CRAIG DR 90068
Certificate Information: 3263 N CRAIG DR 90068
- Application / Permit
- 19010-20000-05194
- Plan Check / Job No.
- B19VN20091
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 24'-6" X 56' (2)-STORY SFD WITH BASEMENT AND ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/8/2020
- Issuing Office
- Current Status
- Issued on 10/8/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | SELLA BENYAMIN |
| Green Plans Picked Up | 11/27/2019 | APPLICANT |
| Corrections Issued | 12/2/2019 | SELLA BENYAMIN |
| Quality Review Completed | 12/5/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/5/2019 | APPLICANT |
| Applicant returned to address corrections | 3/4/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 3/13/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 6/10/2020 | SELLA BENYAMIN |
| Applicant returned to address corrections | 7/10/2020 | SELLA BENYAMIN |
| Plan Check Approved | 8/24/2020 | SELLA BENYAMIN |
| Plan Check Approved | 10/7/2020 | SELLA BENYAMIN |
| Issued | 10/8/2020 | APPLICANT |
Permit Application Clearance Information
| Certificate of Compliance | Cleared | 12/24/2019 | HERMINIGILDO AGUSTIN |
| Miscellaneous | Cleared | 12/24/2019 | HERMINIGILDO AGUSTIN |
| Address approval | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| BHO/Hillside ordinance | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| Permit | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/10/2020 | EMIL KYUPELYAN |
| BHO/Hillside ordinance | Cleared | 1/23/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/14/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/14/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/18/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 3/4/2020 | DAVID MATSON |
| Disturb/Remove Protected Trees | Cleared | 3/5/2020 | ADRIAN SANCHEZ |
| Trees in Parkway | Cleared | 3/5/2020 | ADRIAN SANCHEZ |
| BHO/Hillside ordinance | Cleared | 3/20/2020 | MARY MARCUS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Babakhanian,, Oksen; Lic. No.: S3500 | 6854 FOOTHILL BLVD TUJUNGA, CA 91042 |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Special/Order Compliance | 2/25/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/3/2021 | Corrections Issued | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/14/2021 | Partial Approval | JOSEPH MCGARRY |
| Reinforced Concrete Frame | 8/26/2021 | Corrections Issued | BRIAN SULLIVAN |
| Reinforced Concrete Frame | 8/30/2021 | Partial Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 10/18/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 11/9/2021 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/13/2022 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/28/2022 | Partial Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Partial Approval | RUBEN SALAS |
| Footing/Foundation/Slab | 5/18/2022 | Partial Approval | RUBEN SALAS |
| Rough-Elec/Plmb/HVAC | 8/18/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 2/21/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 2/21/2023 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 2/21/2023 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Final | 2/21/2023 | Partial Inspection | RAUL BARAJAS |
| PLUMBING-Final | 2/21/2023 | Partial Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 2/21/2023 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/30/2023 | Corrections Issued | BRIAN SULLIVAN |
| ELECTRICAL-Final | 3/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Green Building Rough | 3/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| HVAC-Final | 3/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 3/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 3/30/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/10/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 4/10/2023 | Not Ready for Inspection | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 4/10/2023 | Corrections Issued | BRIAN SULLIVAN |
| Special/Order Compliance | 4/10/2023 | Partial Inspection | RUBEN SALAS |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/13/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 7/13/2023 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 7/13/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/31/2023 | Partial Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 8/3/2023 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 8/7/2023 | Corrections Issued | BRIAN SULLIVAN |
| Green Building Rough | 8/7/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/1/2023 | Conditional Approval | BRIAN SULLIVAN |
| Insulation | 9/11/2023 | Corrections Issued | BRIAN SULLIVAN |
| Drywall Nailing | 10/13/2023 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 10/19/2023 | Partial Approval | BRIAN SULLIVAN |