20313 W WINDSOR LANE 91326
Certificate Information: 20313 W WINDSOR LANE 91326
- Application / Permit
- 19010-20000-05166
- Plan Check / Job No.
- B19VN19837
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- THREE STORY SFD WITH ATTACHED 3 CAR GARAGE _STANDARD PLAN #648_ PLAN 3XA (BUILDING SHALL BE FULLY SPRINKLER THROUGH OUT WITH NFPA 13D).
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/11/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | DAWN MC NULTY |
| Corrections Issued | 12/16/2019 | DAWN MC NULTY |
| Quality Review Completed | 12/18/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 12/20/2019 | APPLICANT |
| Green Plans Picked Up | 12/20/2019 | APPLICANT |
| Plan Check Approved | 3/3/2020 | DAWN MC NULTY |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 6/7/2021 | SEAN WIRCH |
| Permit Finaled | 6/11/2021 | MICHAEL SMITH |
| CofO Issued | 6/11/2021 | MICHAEL SMITH |
| Permit Finaled | 6/11/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/19/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 2/20/2020 | ROBERT DUFF |
| "T" removal | Cleared | 2/24/2020 | SARAH GOLDMAN |
| CPC | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Specific Plan | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Tract Map conditions | Cleared | 2/24/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 2/24/2020 | SARAH GOLDMAN |
| ZA Case | Cleared | 2/24/2020 | SARAH GOLDMAN |
| Low Impact Development | Cleared | 2/26/2020 | AMMAR ELTAWIL |
| Sewer availability | Cleared | 2/27/2020 | GUILLERMO PETRA |
| Green Code | Cleared | 3/2/2020 | MICHAEL AYERS |
| Address approval | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Permit | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 3/3/2020 | GUILLERMO PETRA |
Contact Information
| Contractor | Shapell Homes Inc; Lic. No.: 1001034-B | 250 GIBRALTAR RD ATTN: GATES/LEGAL HORSHAM, PA 19044 |
| Engineer | Miller, Karen Lynn; Lic. No.: GE2257 | 5364 DORIS WY TORRANCE, CA 90505 |
| Engineer | Wong, Ramon Roman Ii; Lic. No.: S2345 | 1800 E. 16TH STREET SANTA ANA, CA 92701 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 10/6/2020 | Approved | SEAN WIRCH |
| Footing/Foundation/Slab | 10/20/2020 | Approved | SEAN WIRCH |
| Deputy Reinf. Concrete | 10/23/2020 | Approved | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Partial Approval | SEAN WIRCH |
| Sewer | 11/13/2020 | Approved | DONALD SUNSERI |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Not Ready for Inspection | SEAN WIRCH |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Partial Approval | SEAN WIRCH |
| ELECTRICAL-Rough | 2/3/2021 | Approved | SEAN WIRCH |
| HVAC-Rough | 2/3/2021 | Approved | SEAN WIRCH |
| PLUMBING-Rough | 2/3/2021 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 2/5/2021 | Approved | SEAN WIRCH |
| Green Building Rough | 2/5/2021 | Approved | SEAN WIRCH |
| Verify Sprinkler Sign Off | 2/5/2021 | Approved | SEAN WIRCH |
| Underground Mechanical | 2/17/2021 | Approved | SEAN WIRCH |
| Drywall Nailing | 2/22/2021 | Approved | SEAN WIRCH |
| Interior/Exterior Lathing | 2/22/2021 | Partial Approval | SEAN WIRCH |
| Interior/Exterior Lathing | 3/16/2021 | Approved | SEAN WIRCH |
| Gas Test | 4/14/2021 | Approved | SEAN WIRCH |
| Service/Power Release | 4/14/2021 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 4/27/2021 | SGSOV Approved | SEAN WIRCH |
| ELECTRICAL-Final | 5/13/2021 | Approved | SEAN WIRCH |
| HVAC-Final | 5/13/2021 | Approved | SEAN WIRCH |
| PLUMBING-Final | 5/13/2021 | Approved | SEAN WIRCH |
| Final | 6/4/2021 | OK to Issue CofO | SEAN WIRCH |
| Green Building Final | 6/4/2021 | Approved | SEAN WIRCH |
| Smoke Detectors | 6/4/2021 | Approved | SEAN WIRCH |