13488 N GLENOAKS BLVD 91342

Certificate Information: 13488 N GLENOAKS BLVD 91342

Application / Permit
19010-20000-05152
Plan Check / Job No.
B19VN19987
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 59.25' X 23.5' ONE STORY ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) ALL WORK PER ENGINEERING
Permit Issued
Issued on 4/8/2021
Issuing Office
Valley
Current Status
CofO Issued on 12/17/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2019 APPLICANT
Assigned to Plan Check Engineer 12/12/2019 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/18/2019 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/24/2019 OMID HEDAYAT
Green Plans Picked Up 12/27/2019 APPLICANT
Building Plans Picked Up 12/30/2019 APPLICANT
Plan Check Approved 11/19/2020 SEWADA ZADOORAN MILAGARDI
Issued 4/8/2021 APPLICANT
CofO in Progress 12/5/2022 JOHN COLEMAN
CofO Issued 12/17/2022 MICHAEL SMITH
Permit Finaled 12/17/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 2/10/2020 JOHN TRIANTAFYLLOS
Green Code Cleared 2/13/2020 AARON COSTA
Low Impact Development Cleared 6/29/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 7/7/2020 GABRIEL ROBLES
Zoning Information File Cleared 10/15/2020 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,
Engineer Lopez,, Mauricio Jose; Lic. No.: C36801 1391 N THIRD AVE      UPLAND, CA 91786

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/10/2022 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/15/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 3/24/2022 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 3/29/2022 Approved JOHN HAYES
BUILDING-Rough-Frame 4/15/2022 Not Ready for Inspection JOHN HAYES
Underground Mechanical 4/15/2022 Not Ready for Inspection JOHN HAYES
Sewer 4/19/2022 Corrections Issued JOHN HAYES
Gas Test 4/22/2022 Partial Approval JOHN HAYES
PLUMBING-Rough 4/22/2022 Partial Approval JOHN HAYES
Sewer 4/22/2022 Partial Approval JOHN HAYES
ELECTRICAL-Rough 5/2/2022 Partial Approval JOHN HAYES
Underground Mechanical 5/2/2022 Partial Approval JOHN HAYES
BUILDING-Rough-Frame 5/18/2022 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/18/2022 Not Ready for Inspection JOHN HAYES
Green Building Rough 5/18/2022 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/18/2022 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/18/2022 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 5/18/2022 Not Ready for Inspection JOHN HAYES
Deputy Wood Construction 7/8/2022 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 7/13/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/13/2022 Approved ARAM AVEDISIAN
Green Building Rough 7/13/2022 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 7/13/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/13/2022 Partial Approval ARAM AVEDISIAN
Insulation 7/25/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 7/25/2022 Conditional Approval CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 7/29/2022 Approved ARAM AVEDISIAN
Green Building Rough 7/29/2022 Approved ARAM AVEDISIAN
Insulation 7/29/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/29/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/29/2022 Approved ARAM AVEDISIAN
Drywall Nailing 8/8/2022 Approved CALEB MEISTER
Excavation/Setback/Form/Re-Bar 8/16/2022 Partial Approval ARAM AVEDISIAN
Shower Pan 8/16/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 9/30/2022 Not Ready for Inspection ARAM AVEDISIAN
Final 10/18/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 10/18/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/18/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 10/18/2022 Approved ARAM AVEDISIAN
Final 11/8/2022 Not Ready for Inspection ARAM AVEDISIAN
Final 11/28/2022 OK to Issue CofO JOHN COLEMAN
HVAC-Final 11/28/2022 Approved JOHN COLEMAN
PLUMBING-Rough 11/28/2022 Approved JOHN COLEMAN
Service/Power Release 11/28/2022 Approved JOHN COLEMAN
Service/Power Release 12/15/2022 Approved ARAM AVEDISIAN