9945 N VENA AVE 91331
Certificate Information: 9945 N VENA AVE 91331
- Application / Permit
- 19010-20000-05113
- Plan Check / Job No.
- B19VN19809
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ( 29'-0"x 40'-0") IRR. SHAPE DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | TROY DEGUZMAN |
| Corrections Issued | 11/26/2019 | TROY DEGUZMAN |
| Quality Review Completed | 11/26/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/26/2019 | APPLICANT |
| Green Plans Picked Up | 11/26/2019 | APPLICANT |
| Plan Check Approved | 12/26/2019 | TROY DEGUZMAN |
| Issued | 1/8/2020 | LADBS |
| CofO in Progress | 5/22/2020 | MICHEL ABAJAN |
| CofO Issued | 8/13/2020 | MICHAEL SMITH |
| Permit Finaled | 8/13/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2019 | JEANIE LAM |
| Sewer availability | Cleared | 12/4/2019 | JEANIE LAM |
| Green Code | Cleared | 12/11/2019 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 12/12/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 12/12/2019 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 12/23/2019 | JEREMY CARTER |
Contact Information
| Architect | Kivotos,, Juan M; Lic. No.: C26491 | 1323 N NIAGARA STREET BURBANK, CA 91505 |
| Contractor | Owner-Builder | , |
| Engineer | Yogurtian,, Arpinee; Lic. No.: C49916 | 2529 FOOTHILL BLVD, STE 208 LA CRESCENTA, CA 91214 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/17/2020 | Corrections Issued | MICHEL ABAJAN |
| METHANE-Barrier | 1/17/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Subgrade | 1/17/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 1/17/2020 | Partial Approval | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 1/24/2020 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 1/24/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 1/24/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 1/24/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/12/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 2/12/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| MERV13>=Rough | 2/12/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 2/12/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 2/12/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 2/25/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 2/25/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 2/25/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 2/25/2020 | Approved | MICHEL ABAJAN |
| METHANE-Rough | 2/25/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 2/25/2020 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 3/2/2020 | Approved | MICHEL ABAJAN |
| Insulation | 3/4/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 3/9/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 3/18/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/13/2020 | Corrections Issued | MICHEL ABAJAN |
| Final | 4/13/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/13/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 4/13/2020 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 4/13/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/13/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/13/2020 | SGSOV Not Ready | MICHEL ABAJAN |
| Service/Power Release | 4/13/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 4/13/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/20/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 5/20/2020 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 5/20/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 5/20/2020 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 5/20/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| ELECTRICAL-Final | 5/22/2020 | Approved | MICHEL ABAJAN |
| Final | 5/22/2020 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 5/22/2020 | Approved | MICHEL ABAJAN |