7722 S HOSFORD AVE 90045

Certificate Information: 7722 S HOSFORD AVE 90045

Application / Permit
19010-20000-05094
Plan Check / Job No.
B19VN19776
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 68'1"X43'0" IRREGULAR SHAPED 2-STORY SFD WITH ATTACHED 2-CAR GARAGE & 12'0"X27'2" ATTACHED TRELLIS. NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
Permit Issued
Issued on 2/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 MARVEL DELACRUZ
Green Plans Picked Up 11/22/2019 APPLICANT
Corrections Issued 11/23/2019 MARVEL DELACRUZ
Quality Review Completed 11/25/2019 GUANG MIN TUNG
Building Plans Picked Up 11/25/2019 APPLICANT
Applicant returned to address corrections 1/16/2020 MARVEL DELACRUZ
Plan Check Approved 1/29/2020 MARVEL DELACRUZ
Issued 2/4/2020 LADBS
CofO in Progress 2/24/2021 DAVID HEINE
CofO Issued 7/1/2021 VINCENT COTTON
Permit Finaled 7/1/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 12/10/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 12/10/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/10/2019 GEORGE SUCHAND
Permit Cleared 12/10/2019 ADRIAN CASTRO
Sewer availability Cleared 12/10/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 12/19/2019 GUILLERMO PETRA
Trees in Parkway Cleared 12/20/2019 ADRIAN SANCHEZ
Green Code Cleared 12/24/2019 MICHAEL AYERS
Specific Plan Cleared 1/2/2020 PEDRO AYALA
Low Impact Development Cleared 1/23/2020 SARAH YOUSSEF

Contact Information

Contractor Lev Construction; Lic. No.: 1027463-B 340 S CLOVERDALE AVE #404      LOS ANGELES, CA 90036
Engineer Nester,, Melvin Russell; Lic. No.: C26324 2902 TYLER CT      SIMI VALLEY, CA 93063
Engineer Wang,, Hongyu; Lic. No.: C72679 6270 MCLEOD DR STE 140      LAS VEGAS, NV 89120

Inspector Information

MORRIS JACKSON, (310) 914-3885 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 2/20/2020 Not Ready for Inspection CRAIG DAVIS
PLUMBING-Rough 2/26/2020 Corrections Issued DAVID FEILER
PLUMBING-Rough 2/27/2020 Partial Approval DAVID FEILER
Sewer 2/27/2020 Approved DAVID FEILER
PLUMBING-Rough 3/2/2020 Partial Approval DAVID FEILER
METHANE-Barrier 3/6/2020 Approved JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/2/2020 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 4/2/2020 Approved JOHNNY MIRANDA
METHANE-Subgrade 4/2/2020 Approved JOHNNY MIRANDA
Drywall Nailing 4/20/2020 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/20/2020 Partial Approval JOHNNY MIRANDA
Green Building Rough 4/20/2020 Not Ready for Inspection JOHNNY MIRANDA
BUILDING-Rough-Frame 5/14/2020 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Approved JOHNNY MIRANDA
Deputy Wood Construction 5/20/2020 Conditional Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/22/2020 Corrections Issued JOHNNY MIRANDA
HVAC-Rough 5/22/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 5/22/2020 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 5/22/2020 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 5/26/2020 Approved JOHNNY MIRANDA
PLUMBING-Rough 5/26/2020 Approved JOHNNY MIRANDA
Insulation 6/5/2020 Approved JOHNNY MIRANDA
Shower Pan 6/5/2020 Approved JOHNNY MIRANDA
Drywall Nailing 6/12/2020 Approved JOHNNY MIRANDA
Green Building Rough 6/12/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 6/12/2020 Partial Approval JOHNNY MIRANDA
Gas Test 11/9/2020 Corrections Issued JOHNNY MIRANDA
Gas Test 11/13/2020 Approved JOHNNY MIRANDA
Gas Test 11/17/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/2/2021 Approved DAVID HEINE
HVAC-Final 2/2/2021 Corrections Issued DAVID HEINE
PLUMBING-Final 2/2/2021 Approved DAVID HEINE
BUILDING-Rough-Frame 2/10/2021 Approved DAVID HEINE
Final 2/10/2021 Not Ready for Inspection DAVID HEINE
Green Building Final 2/10/2021 Not Ready for Inspection DAVID HEINE
HVAC-Final 2/10/2021 Approved DAVID HEINE
METHANE-Final 2/10/2021 Approved DAVID HEINE
METHANE-Rough 2/10/2021 Approved DAVID HEINE
SGSOV-Seismic Gas S/O Valve 2/10/2021 SGSOV Approved DAVID HEINE
Service/Power Release 2/10/2021 Not Ready for Inspection DAVID HEINE
Smoke Detectors 2/10/2021 Approved DAVID HEINE
Verify Sprinkler Sign Off 2/10/2021 Approved DAVID HEINE
Final 2/23/2021 Not Ready for Inspection DAVID HEINE
Green Building Final 2/23/2021 Corrections Issued DAVID HEINE
Service/Power Release 2/23/2021 Not Ready for Inspection DAVID HEINE
Final 2/24/2021 OK to Issue CofO DAVID HEINE
Green Building Final 2/24/2021 Approved DAVID HEINE
Service/Power Release 2/24/2021 Approved DAVID HEINE
Special/Order Compliance 3/9/2021 Approved DAVID HEINE