7722 S HOSFORD AVE 90045
Certificate Information: 7722 S HOSFORD AVE 90045
- Application / Permit
- 19010-20000-05094
- Plan Check / Job No.
- B19VN19776
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 68'1"X43'0" IRREGULAR SHAPED 2-STORY SFD WITH ATTACHED 2-CAR GARAGE & 12'0"X27'2" ATTACHED TRELLIS. NFPA 13D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | MARVEL DELACRUZ |
| Green Plans Picked Up | 11/22/2019 | APPLICANT |
| Corrections Issued | 11/23/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 11/25/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/25/2019 | APPLICANT |
| Applicant returned to address corrections | 1/16/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 1/29/2020 | MARVEL DELACRUZ |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 2/24/2021 | DAVID HEINE |
| CofO Issued | 7/1/2021 | VINCENT COTTON |
| Permit Finaled | 7/1/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/10/2019 | GEORGE SUCHAND |
| Permit | Cleared | 12/10/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/10/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 12/20/2019 | ADRIAN SANCHEZ |
| Green Code | Cleared | 12/24/2019 | MICHAEL AYERS |
| Specific Plan | Cleared | 1/2/2020 | PEDRO AYALA |
| Low Impact Development | Cleared | 1/23/2020 | SARAH YOUSSEF |
Contact Information
| Contractor | Lev Construction; Lic. No.: 1027463-B | 340 S CLOVERDALE AVE #404 LOS ANGELES, CA 90036 |
| Engineer | Nester,, Melvin Russell; Lic. No.: C26324 | 2902 TYLER CT SIMI VALLEY, CA 93063 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/20/2020 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Rough | 2/26/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 2/27/2020 | Partial Approval | DAVID FEILER |
| Sewer | 2/27/2020 | Approved | DAVID FEILER |
| PLUMBING-Rough | 3/2/2020 | Partial Approval | DAVID FEILER |
| METHANE-Barrier | 3/6/2020 | Approved | JOHNNY MIRANDA |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Approved | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 4/2/2020 | Approved | JOHNNY MIRANDA |
| METHANE-Subgrade | 4/2/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 4/20/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2020 | Partial Approval | JOHNNY MIRANDA |
| Green Building Rough | 4/20/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 5/14/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Approved | JOHNNY MIRANDA |
| Deputy Wood Construction | 5/20/2020 | Conditional Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/22/2020 | Corrections Issued | JOHNNY MIRANDA |
| HVAC-Rough | 5/22/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 5/22/2020 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/22/2020 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 5/26/2020 | Approved | JOHNNY MIRANDA |
| PLUMBING-Rough | 5/26/2020 | Approved | JOHNNY MIRANDA |
| Insulation | 6/5/2020 | Approved | JOHNNY MIRANDA |
| Shower Pan | 6/5/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/12/2020 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 6/12/2020 | Approved | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 6/12/2020 | Partial Approval | JOHNNY MIRANDA |
| Gas Test | 11/9/2020 | Corrections Issued | JOHNNY MIRANDA |
| Gas Test | 11/13/2020 | Approved | JOHNNY MIRANDA |
| Gas Test | 11/17/2020 | Approved | JOHNNY MIRANDA |
| ELECTRICAL-Final | 2/2/2021 | Approved | DAVID HEINE |
| HVAC-Final | 2/2/2021 | Corrections Issued | DAVID HEINE |
| PLUMBING-Final | 2/2/2021 | Approved | DAVID HEINE |
| BUILDING-Rough-Frame | 2/10/2021 | Approved | DAVID HEINE |
| Final | 2/10/2021 | Not Ready for Inspection | DAVID HEINE |
| Green Building Final | 2/10/2021 | Not Ready for Inspection | DAVID HEINE |
| HVAC-Final | 2/10/2021 | Approved | DAVID HEINE |
| METHANE-Final | 2/10/2021 | Approved | DAVID HEINE |
| METHANE-Rough | 2/10/2021 | Approved | DAVID HEINE |
| SGSOV-Seismic Gas S/O Valve | 2/10/2021 | SGSOV Approved | DAVID HEINE |
| Service/Power Release | 2/10/2021 | Not Ready for Inspection | DAVID HEINE |
| Smoke Detectors | 2/10/2021 | Approved | DAVID HEINE |
| Verify Sprinkler Sign Off | 2/10/2021 | Approved | DAVID HEINE |
| Final | 2/23/2021 | Not Ready for Inspection | DAVID HEINE |
| Green Building Final | 2/23/2021 | Corrections Issued | DAVID HEINE |
| Service/Power Release | 2/23/2021 | Not Ready for Inspection | DAVID HEINE |
| Final | 2/24/2021 | OK to Issue CofO | DAVID HEINE |
| Green Building Final | 2/24/2021 | Approved | DAVID HEINE |
| Service/Power Release | 2/24/2021 | Approved | DAVID HEINE |
| Special/Order Compliance | 3/9/2021 | Approved | DAVID HEINE |