7648 N SANCOLA AVE 91352

Certificate Information: 7648 N SANCOLA AVE 91352

Application / Permit
19010-20000-05064
Plan Check / Job No.
B19VN19670
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 26' X 48'6"ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEER.
Permit Issued
Issued on 3/6/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Green Plans Picked Up 11/19/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 PINANK PATEL
Corrections Issued 11/25/2019 PINANK PATEL
Quality Review Completed 11/26/2019 GUANG MIN TUNG
Building Plans Picked Up 12/3/2019 APPLICANT
Applicant returned to address corrections 2/11/2020 PINANK PATEL
Plan Check Approved 3/6/2020 PINANK PATEL
Issued 3/6/2020 LADBS
CofO in Progress 2/10/2025 DAVID ANDERSON
Permit Finaled 2/18/2025 RUBEN SALAS
CofO Issued 2/18/2025 RUBEN SALAS
Permit Finaled 2/18/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/6/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/6/2019 GUILLERMO PETRA
Sewer availability Cleared 12/6/2019 GUILLERMO PETRA
Green Code Cleared 12/10/2019 MICHAEL AYERS
Low Impact Development Cleared 2/26/2020 SARAH YOUSSEF
Hydrant and Access approval Cleared 3/2/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 3/2/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/31/2020 Corrections Issued BEAU COLLINS
PLUMBING-Rough 7/31/2020 Conditional Approval BEAU COLLINS
Excavation/Setback/Form/Re-Bar 8/18/2020 Approved BEAU COLLINS
ELECTRICAL-Rough 10/5/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 10/5/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 10/5/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 10/15/2020 No Access for Inspection BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 10/15/2020 No Access for Inspection BEAU COLLINS
HVAC-Rough 10/15/2020 No Access for Inspection BEAU COLLINS
PLUMBING-Rough 10/15/2020 No Access for Inspection BEAU COLLINS
BUILDING-Rough-Frame 10/20/2020 Conditional Approval BEAU COLLINS
Green Building Rough 10/20/2020 Conditional Approval BEAU COLLINS
Verify Sprinkler Sign Off 10/20/2020 Approved BEAU COLLINS
Insulation 10/27/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 10/27/2020 Partial Approval BEAU COLLINS
Drywall Nailing 12/1/2020 Approved BEAU COLLINS
Shower Pan 12/1/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 12/10/2020 Approved BEAU COLLINS
BUILDING-Rough-Frame 2/16/2021 Approved BEAU COLLINS
Footing/Foundation/Slab 2/16/2021 Approved BEAU COLLINS
Green Building Rough 2/16/2021 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 2/16/2021 SGSOV Not Ready BEAU COLLINS
ELECTRICAL-Final 3/2/2021 Not Ready for Inspection BEAU COLLINS
HVAC-Final 3/2/2021 Not Ready for Inspection BEAU COLLINS
PLUMBING-Final 3/2/2021 Corrections Issued BEAU COLLINS
Smoke Detectors 3/2/2021 Approved BEAU COLLINS
Final 6/17/2021 Corrections Issued JOHN HAYES
HVAC-Final 6/17/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 6/17/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Not Ready JOHN HAYES
ELECTRICAL-Final 8/25/2021 Approved MATTHEW NELSON
Final 8/25/2021 Corrections Issued MATTHEW NELSON
Green Building Final 8/25/2021 Approved MATTHEW NELSON
HVAC-Final 8/25/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Final 8/25/2021 Partial Approval MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 8/25/2021 SGSOV Approved MATTHEW NELSON
Service/Power Release 8/25/2021 Not Ready for Inspection MATTHEW NELSON
Final 9/7/2021 No Access for Inspection JOHN HAYES
Service/Power Release 9/7/2021 No Access for Inspection JOHN HAYES
Final 9/9/2021 Corrections Issued WILLIAM KUEHN
Service/Power Release 9/9/2021 Not Ready for Inspection WILLIAM KUEHN
Final 2/7/2025 OK to Issue CofO DAVID ANDERSON
Service/Power Release 2/7/2025 Approved DAVID ANDERSON