8000 S DUNBARTON AVE 90045

Certificate Information: 8000 S DUNBARTON AVE 90045

Application / Permit
19010-20000-05063
Plan Check / Job No.
B19VN19658
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Patio Cover
Work Description
NEW (16'-5"x 12'-0") DETACHED PATIO COVER/ CABANA. WORK PER ENGINEER.
Permit Issued
Issued on 1/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 1/5/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 TROY DEGUZMAN
Corrections Issued 11/23/2019 TROY DEGUZMAN
Quality Review Completed 11/25/2019 GUANG MIN TUNG
Building Plans Picked Up 12/5/2019 APPLICANT
Green Plans Picked Up 12/5/2019 APPLICANT
Plan Check Approved 1/10/2020 TROY DEGUZMAN
Issued 1/14/2020 LADBS
CofO in Progress 1/4/2022 RICHARD STEINBACH
Permit Finaled 1/5/2022 DANIEL ORRANTE
CofO Issued 1/5/2022 DANIEL ORRANTE
Permit Finaled 1/5/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 12/16/2019 OSCAR CASTRO
Construction within easement Cleared 12/16/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 12/19/2019 ADRIAN CASTRO
Sewer availability Cleared 12/19/2019 ADRIAN CASTRO
Green Code Cleared 1/7/2020 MICHAEL AYERS
Low Impact Development Cleared 1/7/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/9/2020 GUILLERMO PETRA
ZI Cleared 1/9/2020 HERMINIGILDO AGUSTIN

Contact Information

Contractor Tega Builders Inc; Lic. No.: 1041646-B 5656 WISH AV      ENCINO, CA 91316
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/4/2020 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 3/4/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Barrier 3/4/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Subgrade 3/4/2020 Not Ready for Inspection JUAN VALENZUELA
Footing/Foundation/Slab 3/27/2020 Partial Approval JUAN VALENZUELA
METHANE-Barrier 3/27/2020 Partial Approval JUAN VALENZUELA
METHANE-Subgrade 3/27/2020 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/2/2020 Approved JUAN VALENZUELA
Footing/Foundation/Slab 4/2/2020 Approved JUAN VALENZUELA
METHANE-Barrier 4/2/2020 Approved JUAN VALENZUELA
METHANE-Subgrade 4/2/2020 Approved JUAN VALENZUELA
Special/Order Compliance 4/15/2020 No Access for Inspection JUAN VALENZUELA
Special/Order Compliance 4/17/2020 No Access for Inspection JUAN VALENZUELA
Special/Order Compliance 4/28/2020 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 6/19/2020 Approved CRAIG DAVIS
Special/Order Compliance 6/19/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/11/2020 Partial Inspection JUAN VALENZUELA
Special/Order Compliance 10/26/2020 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 10/28/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Approved JUAN VALENZUELA
Green Building Rough 12/3/2020 Not Ready for Inspection JUAN VALENZUELA
METHANE-Rough 12/3/2020 Approved JUAN VALENZUELA
Special/Order Compliance 12/3/2020 Partial Inspection PIERRE VEGA
Verify Sprinkler Sign Off 12/3/2020 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 12/30/2021 Approved DAVID FEILER
ELECTRICAL-Final 12/30/2021 No Access for Inspection DAVID FEILER
Final 12/30/2021 No Access for Inspection DAVID FEILER
Green Building Final 12/30/2021 No Access for Inspection DAVID FEILER
Green Building Rough 12/30/2021 Approved DAVID FEILER
HVAC-Final 12/30/2021 No Access for Inspection DAVID FEILER
PLUMBING-Final 12/30/2021 No Access for Inspection DAVID FEILER
SGSOV-Seismic Gas S/O Valve 12/30/2021 SGSOV Approved DAVID FEILER
Smoke Detectors 12/30/2021 Approved DAVID FEILER
Final 1/4/2022 OK to Issue CofO RICHARD STEINBACH
Green Building Final 1/4/2022 Approved RICHARD STEINBACH