8000 S DUNBARTON AVE 90045
Certificate Information: 8000 S DUNBARTON AVE 90045
- Application / Permit
- 19010-20000-05062
- Plan Check / Job No.
- B19VN19658
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (53'-7"x 46'-0") IRR. SHAPE 2 STORY SINGLE FAMILY DWELLING WITH ATTCHED 2-CAR GARAGE. "COMPLY WITH DEPARTMENT ORDER effective date 07/30/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". NFPA-13D FIRE SPRINKLER THRUOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 1/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/5/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | TROY DEGUZMAN |
| Corrections Issued | 11/23/2019 | TROY DEGUZMAN |
| Quality Review Completed | 11/25/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/5/2019 | APPLICANT |
| Green Plans Picked Up | 12/5/2019 | APPLICANT |
| Plan Check Approved | 1/10/2020 | TROY DEGUZMAN |
| Issued | 1/14/2020 | LADBS |
| CofO in Progress | 1/4/2022 | RICHARD STEINBACH |
| Permit Finaled | 1/5/2022 | DANIEL ORRANTE |
| CofO Issued | 1/5/2022 | DANIEL ORRANTE |
| Permit Finaled | 1/5/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/19/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/19/2019 | ADRIAN CASTRO |
| Permit | Cleared | 12/19/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/19/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/7/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 1/7/2020 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 1/8/2020 | GEORGE SUCHAND |
| Roof/Waste drainage to street | Cleared | 1/9/2020 | GUILLERMO PETRA |
| ZI | Cleared | 1/9/2020 | HERMINIGILDO AGUSTIN |
| Trees in Parkway | Cleared | 1/11/2020 | ADRIAN SANCHEZ |
Contact Information
| Contractor | Tega Builders Inc; Lic. No.: 1041646-B | 5656 WISH AV ENCINO, CA 91316 |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/24/2020 | Corrections Issued | JUAN VALENZUELA |
| Underground Mechanical | 2/28/2020 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Barrier | 3/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Subgrade | 3/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/18/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/18/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Barrier | 3/18/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Subgrade | 3/18/2020 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 3/27/2020 | Partial Approval | JUAN VALENZUELA |
| METHANE-Barrier | 3/27/2020 | Partial Approval | JUAN VALENZUELA |
| METHANE-Subgrade | 3/27/2020 | Partial Approval | JUAN VALENZUELA |
| Deputy Methane Barrier | 4/1/2020 | Conditional Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/2/2020 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 4/2/2020 | Approved | JUAN VALENZUELA |
| METHANE-Barrier | 4/2/2020 | Approved | JUAN VALENZUELA |
| METHANE-Subgrade | 4/2/2020 | Approved | JUAN VALENZUELA |
| Special/Order Compliance | 5/7/2020 | Approved | CRAIG DAVIS |
| Floor/Roof Diaphrgm/Shear Wall | 9/11/2020 | Corrections Issued | JUAN VALENZUELA |
| Pre-Inspection | 10/30/2020 | Partial Inspection | JUAN VALENZUELA |
| Special/Order Compliance | 10/30/2020 | Partial Inspection | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2020 | Corrections Issued | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2020 | Corrections Issued | JUAN VALENZUELA |
| Deputy Wood Construction | 11/25/2020 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2020 | Approved | JUAN VALENZUELA |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | JUAN VALENZUELA |
| METHANE-Rough | 12/4/2020 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 12/4/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 12/22/2020 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 12/29/2020 | Corrections Issued | DAVID HEINE |
| PLUMBING-Rough | 12/31/2020 | Corrections Issued | JOHNNY MIRANDA |
| Gas Test | 1/5/2021 | Partial Approval | DAVID HEINE |
| PLUMBING-Rough | 1/5/2021 | Approved | DAVID HEINE |
| Special/Order Compliance | 1/6/2021 | Partial Inspection | PIERRE VEGA |
| ELECTRICAL-Rough | 2/1/2021 | Approved | EVAN COOPER |
| Insulation | 2/9/2021 | Approved | DAVID HEINE |
| Drywall Nailing | 2/22/2021 | Approved | DAVID HEINE |
| Green Building Rough | 2/22/2021 | Approved | DAVID HEINE |
| Special/Order Compliance | 3/16/2021 | Partial Approval | DAVID HEINE |
| Pre-Inspection | 3/19/2021 | No Access for Inspection | JOHNNY MIRANDA |
| Pre-Inspection | 4/6/2021 | Partial Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 4/15/2021 | Corrections Issued | BRENDAN LOONEY |
| Gas Test | 6/9/2021 | Partial Approval | BRENDAN LOONEY |
| Gas Test | 6/15/2021 | Approved | DONALD GALLAGHER |
| Special/Order Compliance | 7/16/2021 | Partial Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 7/27/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 9/1/2021 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 9/8/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 9/8/2021 | Corrections Issued | BRENDAN LOONEY |
| Service/Power Release | 9/8/2021 | Not Ready for Inspection | BRENDAN LOONEY |
| Smoke Detectors | 9/8/2021 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 11/2/2021 | Not Ready for Inspection | DAVID FEILER |
| HVAC-Final | 11/24/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Final | 11/24/2021 | Approved | DAVID FEILER |
| HVAC-Final | 12/6/2021 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 12/30/2021 | Approved | DAVID FEILER |
| Final | 12/30/2021 | No Access for Inspection | DAVID FEILER |
| Green Building Final | 12/30/2021 | No Access for Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 12/30/2021 | SGSOV Approved | DAVID FEILER |
| Service/Power Release | 12/30/2021 | No Access for Inspection | DAVID FEILER |
| Final | 1/4/2022 | Conditional Approval | RICHARD STEINBACH |
| Green Building Final | 1/4/2022 | Approved | RICHARD STEINBACH |
| Service/Power Release | 1/4/2022 | Approved | RICHARD STEINBACH |