514 N VIA DE LA PAZ 90272
Certificate Information: 514 N VIA DE LA PAZ 90272
- Application / Permit
- 19010-20000-05055
- Plan Check / Job No.
- B19VN19636
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 3-STORY 91'-4" X 38'-0" FULLY SPRINKLERED SFD WITH ATTACHED PATIO , TWO CAR GARAGE & ROOF DECK.
- Permit Issued
- Issued on 4/23/2020
- Issuing Office
- Current Status
- CofO Issued on 4/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/12/2019 | APPLICANT |
| Green Plans Picked Up | 11/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 11/24/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 11/26/2019 | GUANG MIN TUNG |
| Applicant returned to address corrections | 2/5/2020 | ARTIN ZARUKIAN |
| Plan Check Approved | 3/11/2020 | ARTIN ZARUKIAN |
| Issued | 4/23/2020 | APPLICANT |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| CofO in Progress | 4/21/2022 | ANDREW NAVE |
| Permit Finaled | 4/28/2022 | DANIEL ORRANTE |
| CofO Issued | 4/28/2022 | DANIEL ORRANTE |
| Permit Finaled | 4/28/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 12/4/2019 | GEORGE SUCHAND |
| Address approval | Cleared | 1/29/2020 | ADRIAN CASTRO |
| Coastal Zone | Cleared | 1/29/2020 | VINCENT QUITORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2020 | ADRIAN CASTRO |
| Frnt yard landscape/Water mgmt | Cleared | 1/29/2020 | VINCENT QUITORIANO |
| Grading Pre-Inspection | Cleared | 1/29/2020 | BARTON HOLMES |
| Miscellaneous | Cleared | 1/29/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 1/29/2020 | VINCENT QUITORIANO |
| Permit | Cleared | 1/29/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 1/29/2020 | ADRIAN CASTRO |
| Green Code | Cleared | 2/11/2020 | DAVID MATSON |
| GPI Written Notices | Cleared | 2/18/2020 | ARTIN ZARUKIAN |
| Disturb/Remove Protected Trees | Cleared | 2/28/2020 | STEPHEN DUPREY |
| Low Impact Development | Cleared | 3/9/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/10/2020 | GUILLERMO PETRA |
Contact Information
| Architect | Lippich,, Leslie Thomas; Lic. No.: C7480 | 14044 VENTURA BLVD. #301 SHERMAN OAKS, CA 91423 |
| Contractor | Lev Construction; Lic. No.: 1027463-B | 340 S CLOVERDALE AVE #404 LOS ANGELES, CA 90036 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Vinci,, James Richard; Lic. No.: S4411 | 175 E WILBUR ROAD STE 103 THOUSAND OAKS, CA 91360 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| STEPHANIE SWANSON, (213) 469-1255 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/19/2020 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 8/24/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/16/2020 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 10/21/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 10/22/2020 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 10/29/2020 | Partial Approval | DAVID HEINE |
| Footing/Foundation/Slab | 10/30/2020 | Partial Approval | ANDREW NAVE |
| Deputy Shotcrete | 11/5/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/19/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 12/3/2020 | Corrections Issued | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Partial Approval | ANDREW NAVE |
| Reinforced Masonry Frame | 12/9/2020 | Partial Approval | ANDREW NAVE |
| Masonry Wall/Backfill | 12/11/2020 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 12/23/2020 | Approved | ROBERT SHELLY |
| Underground Mechanical | 12/24/2020 | No Access for Inspection | KENNETH NAGLE |
| PLUMBING-Rough | 12/30/2020 | Corrections Issued | KENNETH NAGLE |
| Underground Mechanical | 1/4/2021 | Partial Inspection | ANDREW NAVE |
| Footing/Foundation/Slab | 1/6/2021 | Partial Approval | ANDREW NAVE |
| Underground Mechanical | 1/6/2021 | Partial Approval | ANDREW NAVE |
| Excavation/Setback/Form/Re-Bar | 1/8/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 1/26/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2021 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 3/31/2021 | Conditional Approval | ANDREW NAVE |
| Special/Order Compliance | 3/31/2021 | Approved | ANDREW NAVE |
| Special/Order Compliance | 4/6/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | ANDREW NAVE |
| Wood Frame | 4/12/2021 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2021 | Partial Inspection | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/26/2021 | Approved | ANDREW NAVE |
| HVAC-Rough | 5/14/2021 | Corrections Issued | JOHN KIDWELL |
| HVAC-Rough | 5/19/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 5/19/2021 | Conditional Approval | ANDREW NAVE |
| ELECTRICAL-Rough | 5/24/2021 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 5/24/2021 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 5/24/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 5/25/2021 | Conditional Approval | ANDREW NAVE |
| Green Building Rough | 5/25/2021 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 5/25/2021 | Approved | ANDREW NAVE |
| Shower Pan | 6/17/2021 | Approved | JUAN VALENZUELA |
| Insulation | 6/18/2021 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 6/25/2021 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 6/25/2021 | Partial Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 6/28/2021 | Partial Approval | ADAM ESCOTO |
| Masonry Wall/Backfill | 8/18/2021 | Corrections Issued | ANDREW NAVE |
| Reinforced Masonry Frame | 8/27/2021 | Partial Approval | ANDREW NAVE |
| Masonry Wall/Backfill | 8/31/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 2/1/2022 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 2/1/2022 | Approved | ANDREW NAVE |
| HVAC-Final | 2/1/2022 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Final | 2/1/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 2/3/2022 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 3/2/2022 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 3/9/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 3/9/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 3/9/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 3/17/2022 | Approved | ANDREW NAVE |
| Service/Power Release | 3/17/2022 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 4/5/2022 | Approved | ANDREW NAVE |
| Final | 4/5/2022 | Corrections Issued | ANDREW NAVE |
| Footing/Foundation/Slab | 4/5/2022 | Approved | ANDREW NAVE |
| Green Building Final | 4/5/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 4/5/2022 | SGSOV Approved | ANDREW NAVE |
| Smoke Detectors | 4/5/2022 | Corrections Issued | ANDREW NAVE |
| Final | 4/21/2022 | OK to Issue CofO | ANDREW NAVE |
| Green Building Final | 4/21/2022 | Approved | ANDREW NAVE |
| Smoke Detectors | 4/21/2022 | Approved | ANDREW NAVE |