8731 1/2 W YATES ST 91040

Certificate Information: 8731 1/2 W YATES ST 91040

Application / Permit
19010-20000-05042
Plan Check / Job No.
B19VN19593
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24'-4" X 24'-4" TWO STORY ACCESSORY DWELLING UNIT WITH ATTACHED COVER PATIO PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/19/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/12/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 PARISA ZAHABI
Corrections Issued 12/11/2019 PARISA ZAHABI
Green Plans Picked Up 12/12/2019 APPLICANT
Quality Review Completed 12/16/2019 OMID HEDAYAT
Building Plans Picked Up 12/16/2019 APPLICANT
Plan Check Approved 2/19/2020 PARISA ZAHABI
Issued 2/19/2020 LADBS
CofO in Progress 5/23/2024 DAVID ANDERSON
Permit Finaled 6/12/2024 RUBEN SALAS
CofO Issued 6/12/2024 RUBEN SALAS
Permit Finaled 6/12/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/6/2020 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 1/6/2020 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 1/6/2020 GABRIEL ROBLES
BHO/Hillside ordinance Cleared 1/6/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/6/2020 GABRIEL ROBLES
ZI Cleared 1/6/2020 DAISY BENICIA
ZI Cleared 1/7/2020 PEGGY MALONE-BROWN
Low Impact Development Cleared 1/13/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/23/2020 JOHN LIN
Distance to fire station Cleared 2/10/2020 GEORGE SUCHAND
Green Code Cleared 2/10/2020 AARON COSTA
Hydrant and Access approval Cleared 2/10/2020 GEORGE SUCHAND
GPI Written Notices Cleared 2/19/2020 PARISA ZAHABI
Grading Pre-Inspection Cleared 2/19/2020 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/15/2020 Not Ready for Inspection BEAU COLLINS
Excavation/Setback/Form/Re-Bar 3/25/2021 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 3/25/2021 Corrections Issued BEAU COLLINS
PLUMBING-Rough 3/25/2021 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 4/6/2021 Approved BEAU COLLINS
ELECTRICAL-Rough 4/22/2021 Partial Approval BEAU COLLINS
Excavation/Setback/Form/Re-Bar 4/22/2021 Approved BEAU COLLINS
Gas Test 4/22/2021 Partial Approval BEAU COLLINS
PLUMBING-Rough 4/22/2021 Partial Approval BEAU COLLINS
Sewer 4/29/2021 Approved BEAU COLLINS
Wood Frame 4/29/2021 Conditional Approval BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 5/6/2021 Approved MATTHEW NELSON
HVAC-Rough 5/12/2021 No Access for Inspection DAVID MATSON
PLUMBING-Rough 5/12/2021 No Access for Inspection DAVID MATSON
HVAC-Rough 5/17/2021 Approved MATTHEW NELSON
PLUMBING-Rough 5/17/2021 Approved MATTHEW NELSON
ELECTRICAL-Rough 6/8/2021 Approved MATTHEW NELSON
Wood Frame 6/14/2021 Approved MATTHEW NELSON
Insulation 7/22/2021 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 7/22/2021 Approved DEANDRE HOFFMAN
Drywall Nailing 7/27/2021 Approved WILLIAM KUEHN
Green Building Rough 7/27/2021 Approved WILLIAM KUEHN
Interior/Exterior Lathing 7/27/2021 Approved WILLIAM KUEHN
BUILDING-Rough-Frame 12/22/2021 No Access for Inspection WILLIAM KUEHN
Final 12/22/2021 Corrections Issued WILLIAM KUEHN
Green Building Final 12/22/2021 No Access for Inspection WILLIAM KUEHN
MERV13>=Final 12/22/2021 No Access for Inspection WILLIAM KUEHN
MERV13>=Rough 12/22/2021 No Access for Inspection WILLIAM KUEHN
SGSOV-Seismic Gas S/O Valve 12/22/2021 SGSOV Not Ready WILLIAM KUEHN
Service/Power Release 12/22/2021 No Access for Inspection WILLIAM KUEHN
Smoke Detectors 12/22/2021 No Access for Inspection WILLIAM KUEHN
Verify Sprinkler Sign Off 12/22/2021 No Access for Inspection WILLIAM KUEHN
BUILDING-Rough-Frame 12/28/2021 Partial Approval MATTHEW NELSON
Final 12/28/2021 Corrections Issued MATTHEW NELSON
Green Building Final 12/28/2021 Corrections Issued MATTHEW NELSON
MERV13>=Final 12/28/2021 Approved MATTHEW NELSON
MERV13>=Rough 12/28/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 12/28/2021 SGSOV Approved MATTHEW NELSON
Service/Power Release 12/28/2021 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 12/28/2021 Approved MATTHEW NELSON
Verify Sprinkler Sign Off 12/28/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 1/4/2022 Approved MATTHEW NELSON
PLUMBING-Final 1/4/2022 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/31/2022 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Final 10/31/2022 Approved DAVID ANDERSON
Final 10/31/2022 Not Ready for Inspection DAVID ANDERSON
Gas Test 10/31/2022 Approved DAVID ANDERSON
Green Building Final 10/31/2022 Approved DAVID ANDERSON
Service/Power Release 10/31/2022 Not Ready for Inspection DAVID ANDERSON
Verify Sprinkler Sign Off 10/31/2022 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 5/22/2024 Approved DAVID ANDERSON
Final 5/22/2024 OK to Issue CofO DAVID ANDERSON
Service/Power Release 5/22/2024 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 5/22/2024 Approved DAVID ANDERSON