Work Description
NEW 66'-10" X 45'-4" (2)-STORY SINGLE FAMILY DWELLING WITH BASEMENT; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/23/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/27/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 SELLA BENYAMIN
Green Plans Picked Up 11/19/2019 APPLICANT
Corrections Issued 12/3/2019 SELLA BENYAMIN
Quality Review Completed 12/5/2019 STEVEN KIM
Building Plans Picked Up 12/9/2019 APPLICANT
Plan Check Approved 1/23/2020 SELLA BENYAMIN
Issued 1/23/2020 LADBS
CofO in Progress 10/26/2021 ARTHUR SARGSYAN
CofO in Progress 10/26/2021 ARTHUR SARGSYAN
Permit Finaled 10/27/2021 DEROLD HAUFF
CofO Issued 10/27/2021 DEROLD HAUFF
Permit Finaled 10/27/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/9/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 12/9/2019 GEORGE SUCHAND
Permit Cleared 12/9/2019 GUILLERMO PETRA
Sewer availability Cleared 12/9/2019 GUILLERMO PETRA
ZA Case Cleared 12/9/2019 HERMINIGILDO AGUSTIN
Abandoned oil well Cleared 12/16/2019 GEORGE SUCHAND
Low Impact Development Cleared 12/19/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/19/2019 ADRIAN CASTRO
Green Code Cleared 12/20/2019 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/29/2020 Partial Approval ARTHUR SARGSYAN
Pre-Inspection 2/10/2020 Approved ARTHUR SARGSYAN
Underground Mechanical 4/27/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 5/7/2020 Partial Approval ARTHUR SARGSYAN
METHANE-Barrier 5/7/2020 Approved ARTHUR SARGSYAN
METHANE-Subgrade 5/7/2020 Approved ARTHUR SARGSYAN
Deputy Methane Barrier 5/8/2020 Approved ARTHUR SARGSYAN
Footing/Foundation/Slab 5/22/2020 Approved ARTHUR SARGSYAN
Deputy Methane Barrier 6/11/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/25/2020 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 9/29/2020 Not Ready for Inspection ARTHUR SARGSYAN
HVAC-Rough 9/29/2020 Not Ready for Inspection ARTHUR SARGSYAN
PLUMBING-Rough 9/29/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 10/7/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 10/21/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 10/23/2020 Approved ARTHUR SARGSYAN
Green Building Rough 10/23/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 10/23/2020 Approved ARTHUR SARGSYAN
Verify Sprinkler Sign Off 10/23/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 11/2/2020 Approved ARTHUR SARGSYAN
Shower Pan 11/2/2020 Approved ARTHUR SARGSYAN
Insulation 11/6/2020 Approved DONALD CRICHLOW
Drywall Nailing 11/13/2020 Approved DONALD CRICHLOW
Underground Mechanical 12/15/2020 Approved JOSEPH MCGARRY
Service/Power Release 6/24/2021 Approved JOSEPH MCGARRY
ELECTRICAL-Final 7/29/2021 Approved ARTHUR SARGSYAN
PLUMBING-Final 7/29/2021 Approved ARTHUR SARGSYAN
Green Building Final 8/3/2021 Approved ARTHUR SARGSYAN
HVAC-Final 8/3/2021 Approved ARTHUR SARGSYAN
Service/Power Release 8/3/2021 Not Ready for Inspection ARTHUR SARGSYAN
Gas Test 8/12/2021 Approved ARTHUR SARGSYAN
Final 10/6/2021 OK to Issue CofO ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 10/6/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 10/6/2021 Approved ARTHUR SARGSYAN