1955 S THURMAN AVE 90016

Certificate Information: 1955 S THURMAN AVE 90016

Application / Permit
19010-20000-04982
Plan Check / Job No.
B19VN19405
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED NEW (25' X 40') ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/7/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 RAPHAEL ROSAS
Corrections Issued 11/18/2019 RAPHAEL ROSAS
Green Plans Picked Up 11/18/2019 APPLICANT
Quality Review Completed 11/20/2019 CHON CHIO KUO
Building Plans Picked Up 11/20/2019 APPLICANT
Plan Check Approved 1/17/2020 ABDUL CHEGENI
Issued 1/21/2020 LADBS
CofO in Progress 11/12/2020 DAVID CHAN
Permit Finaled 4/8/2021 DEROLD HAUFF
CofO Issued 4/8/2021 DEROLD HAUFF
Permit Finaled 4/8/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/21/2019 MARKOS PEREZ-BRAN
Frnt yard landscape/Water mgmt Cleared 11/21/2019 HERMINIGILDO AGUSTIN
Hydrant and Access approval Cleared 11/21/2019 GEORGE SUCHAND
Green Code Cleared 12/10/2019 AARON COSTA
Low Impact Development Cleared 12/10/2019 SARAH YOUSSEF
Flood clearance Cleared 12/19/2019 BRYAN GATHUKA
Construction near power lines Cleared 1/15/2020 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/17/2020 JOHN LIN
Roof/Waste drainage to street Cleared 1/17/2020 JOHN LIN
Sewer availability Cleared 1/17/2020 JOHN LIN

Contact Information

Architect Yasharel,, Harry H; Lic. No.: C14933 4524 WHITE OAK PLACE      ENCINO, CA 91316
Contractor Owner-Builder       ,
Engineer Golabtounkar,, Tony Hamid; Lic. No.: C49104 1434 WESTWOOD BLVD ST 17      LOS ANGELES, CA 90024

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/24/2020 Partial Inspection DAVID CHAN
PLUMBING-Rough 3/31/2020 Partial Approval DAVID CHAN
FLOOD-Elevation Certificate 4/3/2020 Approved DAVID CHAN
Footing/Foundation/Slab 4/3/2020 Approved DAVID CHAN
Wood Frame 4/16/2020 Partial Approval DAVID CHAN
HVAC-Rough 4/28/2020 Corrections Issued DAVID CHAN
PLUMBING-Rough 4/28/2020 Corrections Issued DAVID CHAN
HVAC-Rough 5/1/2020 Approved DAVID CHAN
PLUMBING-Rough 5/1/2020 Approved DAVID CHAN
ELECTRICAL-Rough 5/13/2020 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 5/13/2020 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 5/19/2020 Approved DAVID CHAN
Insulation 5/19/2020 Approved DAVID CHAN
Interior/Exterior Lathing 5/19/2020 Approved DAVID CHAN
Insulation 5/20/2020 Corrections Issued SABAS ALONSO
Drywall Nailing 6/3/2020 Approved THOMAS LOGRASSO
Green Building Rough 6/3/2020 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 6/12/2020 Approved SABAS ALONSO
Special/Order Compliance 6/22/2020 No Access for Inspection DAVID CHAN
PLUMBING-Rough 7/20/2020 Approved DAVID CHAN
Special/Order Compliance 7/20/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 8/19/2020 Approved DAVID CHAN
ELECTRICAL-Final 8/19/2020 Approved DAVID CHAN
FLOOD-Proofing Certificate 8/19/2020 Approved DAVID CHAN
Final 8/19/2020 Corrections Issued DAVID CHAN
Green Building Final 8/19/2020 Approved DAVID CHAN
HVAC-Final 8/19/2020 Approved DAVID CHAN
PLUMBING-Final 8/19/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Not Ready DAVID CHAN
Smoke Detectors 8/19/2020 Approved DAVID CHAN
Verify Sprinkler Sign Off 8/19/2020 Approved DAVID CHAN
ELECTRICAL-Final 9/23/2020 Approved DAVID CHAN
Final 9/23/2020 Not Ready for Inspection DAVID CHAN
HVAC-Final 9/23/2020 Approved DAVID CHAN
PLUMBING-Final 9/23/2020 Approved DAVID CHAN
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Approved DAVID CHAN
ELECTRICAL-Final 9/30/2020 Approved JOSEPH MCGARRY
Final 9/30/2020 Not Ready for Inspection JOSEPH MCGARRY
Service/Power Release 9/30/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 10/5/2020 Corrections Issued JOSEPH MCGARRY
Service/Power Release 10/5/2020 Not Ready for Inspection JOSEPH MCGARRY
Final 11/10/2020 OK to Issue CofO DAVID CHAN
Service/Power Release 11/10/2020 Partial Approval DAVID CHAN