3558 S BUTLER AVE 90066

Certificate Information: 3558 S BUTLER AVE 90066

Application / Permit
19010-20000-04969
Plan Check / Job No.
B19VN19357
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 2 story ACCESSORY DWELLING UNIT ( 25'-8"x25'-2") with 5'x7' attached patio cover, PER AB 494 & SB 229 “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
Permit Issued
Issued on 11/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 11/5/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 12/5/2019 MOHAMMAD ESMAILI
Corrections Issued 12/10/2019 MOHAMMAD ESMAILI
Quality Review Completed 12/11/2019 OMID HEDAYAT
Building Plans Picked Up 12/16/2019 APPLICANT
Green Plans Picked Up 12/16/2019 APPLICANT
Applicant returned to address corrections 2/11/2022 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/7/2022 MOHAMMAD ESMAILI
Plan Check Approved 11/9/2022 MOHAMMAD ESMAILI
Issued 11/29/2022 APPLICANT
CofO in Progress 10/17/2024 DANIEL VERA
Permit Finaled 11/5/2024 RICHARD STEINBACH
CofO Issued 11/5/2024 RICHARD STEINBACH
Permit Finaled 11/5/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 12/16/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 3/2/2021 SAUL GARCIA
Sewer availability Cleared 3/2/2021 SAUL GARCIA
Hydrant and Access approval Cleared 1/10/2022 GILBERT URREA
Roof/Waste drainage to street Cleared 8/11/2022 DINAH GARIN
Grading Pre-Inspection Cleared 9/7/2022 MOHAMMAD ESMAILI
Green Code Cleared 9/7/2022 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Wassef,, Mena Maher Salama; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/7/2023 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 3/7/2023 Partial Approval JOHNNY MIRANDA
Sewer 3/7/2023 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 3/28/2023 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/19/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 6/14/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 6/14/2023 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 6/14/2023 Corrections Issued JOHNNY MIRANDA
ELECTRICAL-Rough 6/30/2023 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/30/2023 Approved JOHNNY MIRANDA
HVAC-Rough 6/30/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/30/2023 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 7/24/2023 Approved JESUS PINEDA
Green Building Rough 7/24/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 7/24/2023 Partial Approval JESUS PINEDA
Special/Order Compliance 7/24/2023 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 7/24/2023 Not Ready for Inspection JESUS PINEDA
Insulation 7/31/2023 Corrections Issued JESUS PINEDA
Insulation 8/14/2023 Approved JESUS PINEDA
Drywall Nailing 8/24/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 10/13/2023 Approved BEN MOLSTAD
Shower Pan 10/13/2023 Approved BEN MOLSTAD
ELECTRICAL-Final 2/15/2024 Corrections Issued JESUS PINEDA
Final 2/15/2024 Corrections Issued JESUS PINEDA
Gas Test 2/15/2024 Corrections Issued JESUS PINEDA
Green Building Final 2/15/2024 Corrections Issued JESUS PINEDA
HVAC-Final 2/15/2024 Approved JESUS PINEDA
PLUMBING-Final 2/15/2024 Approved JESUS PINEDA
ELECTRICAL-Final 3/29/2024 Not Ready for Inspection JESUS PINEDA
Final 3/29/2024 Not Ready for Inspection JESUS PINEDA
Gas Test 3/29/2024 Approved JESUS PINEDA
Green Building Final 3/29/2024 Not Ready for Inspection JESUS PINEDA
PLUMBING-Rough 3/29/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 3/29/2024 SGSOV Approved JESUS PINEDA
Service/Power Release 3/29/2024 Not Ready for Inspection JESUS PINEDA
Smoke Detectors 3/29/2024 Approved JESUS PINEDA
ELECTRICAL-Final 4/22/2024 Approved JESUS PINEDA
Final 4/22/2024 Not Ready for Inspection JESUS PINEDA
Green Building Final 4/22/2024 Approved JESUS PINEDA
Service/Power Release 4/22/2024 Not Ready for Inspection JESUS PINEDA
Final 10/16/2024 OK to Issue CofO DANIEL VERA
Service/Power Release 10/16/2024 Approved DANIEL VERA