8243 N BABCOCK AVE 91605
Certificate Information: 8243 N BABCOCK AVE 91605
- Application / Permit
- 19010-20000-04967
- Plan Check / Job No.
- B19VN19352
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 36'-0" x 18'-0" TWO-STORY ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/6/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | ROSENDO MEDINA |
| Corrections Issued | 12/3/2019 | ROSENDO MEDINA |
| Quality Review Completed | 12/6/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 12/9/2019 | APPLICANT |
| Green Plans Picked Up | 12/11/2019 | APPLICANT |
| Plan Check Approved | 1/21/2020 | ROSENDO MEDINA |
| Issued | 1/21/2020 | LADBS |
| CofO in Progress | 11/17/2021 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 1/15/2022 | MICHAEL SMITH |
| Permit Finaled | 1/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 1/7/2020 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | JOHN LIN |
| Hydrant and Access approval | Cleared | 1/16/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 1/16/2020 | JOHN LIN |
| Green Code | Cleared | 1/17/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 1/17/2020 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 1/17/2020 | ELENA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/20/2021 | Approved | JOHN HAYES |
| Footing/Foundation/Slab | 5/10/2021 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 5/13/2021 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 5/24/2021 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/2/2021 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2021 | Partial Approval | JOHN HAYES |
| Deputy Wood Construction | 6/16/2021 | No Access for Inspection | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Rough | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| Verify Sprinkler Sign Off | 6/28/2021 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 7/6/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 7/6/2021 | Approved | JOHN HAYES |
| Green Building Rough | 7/6/2021 | Approved | JOHN HAYES |
| HVAC-Rough | 7/6/2021 | Approved | JOHN HAYES |
| MERV13>=Rough | 7/6/2021 | Approved | JOHN HAYES |
| PLUMBING-Rough | 7/6/2021 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 7/6/2021 | Approved | JOHN HAYES |
| Insulation | 7/12/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 7/12/2021 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 7/19/2021 | Approved | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 7/19/2021 | Approved | DEANDRE HOFFMAN |
| Shower Pan | 7/19/2021 | Corrections Issued | DEANDRE HOFFMAN |
| Shower Pan | 7/21/2021 | Approved | ALAN MORELOS |
| Underground Mechanical | 8/23/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 11/9/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Final | 11/9/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Final | 11/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 11/9/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 11/9/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 11/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 11/9/2021 | SGSOV Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 11/9/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 11/9/2021 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 11/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 11/17/2021 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 11/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| MERV13>=Final | 11/17/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Service/Power Release | 11/17/2021 | Approved | CHRISTOPHER DELLEFIELD |