10575 W ART ST 91040

Certificate Information: 10575 W ART ST 91040

Application / Permit
19010-20000-04964
Plan Check / Job No.
B19VN19341
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED ONE STORY 15' X 56' ACCESSORY DWELLING UNIT - MODULAR HOME / STATE APPROVED PLAN. NFPA 13D THRU OUT (1200 SF MAXIMUM PER ORDINANCE, 12.22 A.33 (c)-(d))
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 10/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/6/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 PARISA ZAHABI
Corrections Issued 12/9/2019 PARISA ZAHABI
Quality Review Completed 12/9/2019 OMID HEDAYAT
Green Plans Picked Up 12/9/2019 APPLICANT
Building Plans Picked Up 12/13/2019 APPLICANT
Applicant returned to address corrections 2/5/2021 AUNG SOE
Plan Check Approved 2/10/2021 AUNG SOE
Issued 2/19/2021 APPLICANT
CofO in Progress 8/28/2023 JUAN VALENZUELA
CofO Issued 10/23/2023 RUBEN SALAS
Permit Finaled 10/23/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 12/30/2019 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 12/30/2019 LEE GUILBEAUX
Miscellaneous Cleared 12/30/2019 JASON CHAN
Miscellaneous Cleared 12/30/2019 JASON CHAN
Miscellaneous Cleared 12/30/2019 JASON CHAN
Sewer availability Cleared 12/30/2019 LEE GUILBEAUX
ZI Cleared 12/30/2019 JASON CHAN
GPI Written Notices Cleared 7/23/2020 PARISA ZAHABI
Grading Pre-Inspection Cleared 7/23/2020 PARISA ZAHABI
Hydrant and Access approval Cleared 9/22/2020 MATTHEW CRAIG
Specific Plan Cleared 9/22/2020 PEGGY MALONE-BROWN
Low Impact Development Cleared 10/18/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 11/20/2020 ADRIAN CASTRO
Green Code Cleared 2/10/2021 DAVID MATSON

Contact Information

Contractor Owner-Builder       ,

Inspector Information

DANIEL ORRANTE, (818) 374-1157 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/10/2021 Partial Inspection JENNIFER RABUCHIN
ELECTRICAL-Final 6/9/2021 Conditional Approval THOMAS FINNILA
PLUMBING-Final 6/9/2021 Approved THOMAS FINNILA
Verify Sprinkler Sign Off 6/9/2021 Corrections Issued THOMAS FINNILA
ELECTRICAL-Final 4/4/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/4/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 4/4/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Pre-Inspection 4/7/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Rough 4/12/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/12/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
PLUMBING-Rough 4/12/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Special/Order Compliance 4/12/2022 Corrections Issued DAVID MATSON
ELECTRICAL-Rough 10/19/2022 Not Ready for Inspection DAVID ANDERSON
Pre-Inspection 10/19/2022 Not Ready for Inspection DAVID ANDERSON
Footing/Foundation/Slab 4/11/2023 Approved JUAN VALENZUELA
BUILDING-Rough-Frame 8/25/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 8/25/2023 Approved JUAN VALENZUELA
Final 8/25/2023 OK to Issue CofO JUAN VALENZUELA
Green Building Final 8/25/2023 Approved JUAN VALENZUELA
Green Building Rough 8/25/2023 Approved JUAN VALENZUELA
HVAC-Final 8/25/2023 Approved JUAN VALENZUELA
SGSOV-Seismic Gas S/O Valve 8/25/2023 SGSOV Approved JUAN VALENZUELA
Service/Power Release 8/25/2023 Approved JUAN VALENZUELA
Smoke Detectors 8/25/2023 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 8/25/2023 Approved JUAN VALENZUELA