7544 N RIVERTON AVE 91352

Certificate Information: 7544 N RIVERTON AVE 91352

Application / Permit
19010-20000-04940
Plan Check / Job No.
B19VN19269
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 40'-0" X 34'-6" DETACHED ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER WFPP.
Permit Issued
Issued on 2/17/2021
Issuing Office
Current Status
CofO Issued on 6/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2019 APPLICANT
Green Plans Picked Up 11/13/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ARTIN ZARUKIAN
Corrections Issued 11/17/2019 ARTIN ZARUKIAN
Quality Review Completed 11/20/2019 GUANG MIN TUNG
Building Plans Picked Up 11/21/2019 APPLICANT
Applicant returned to address corrections 12/14/2020 ARTIN ZARUKIAN
Plan Check Approved 2/17/2021 ARTIN ZARUKIAN
Issued 2/17/2021 APPLICANT
CofO in Progress 12/22/2021 ARAM AVEDISIAN
CofO Issued 6/23/2022 MICHAEL SMITH
Permit Finaled 6/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/30/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/30/2020 GUILLERMO PETRA
Miscellaneous Cleared 1/30/2020 GUILLERMO PETRA
Sewer availability Cleared 1/30/2020 GUILLERMO PETRA
Green Code Cleared 2/5/2020 DAVID MATSON
Hydrant and Access approval Cleared 10/26/2020 KURT CORRAL
Low Impact Development Cleared 11/19/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/14/2021 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/19/2021 Partial Approval DANIEL DREW
Sewer 3/19/2021 Not Ready for Inspection DANIEL DREW
Footing/Foundation/Slab 3/24/2021 Approved DANIEL DREW
PLUMBING-Rough 4/15/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/10/2021 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 5/10/2021 Not Ready for Inspection JOHN HAYES
Gas Test 5/10/2021 Partial Approval JOHN HAYES
Green Building Rough 5/10/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 5/10/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 5/10/2021 Partial Approval JOHN HAYES
Underground Mechanical 5/10/2021 Partial Approval JOHN HAYES
Verify Sprinkler Sign Off 5/10/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 5/18/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 5/18/2021 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 5/18/2021 Partial Approval JOHN HAYES
Green Building Rough 5/18/2021 Partial Approval JOHN HAYES
HVAC-Rough 5/18/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 5/18/2021 Approved JOHN HAYES
Wood Frame 5/18/2021 Partial Approval JOHN HAYES
ELECTRICAL-Rough 5/27/2021 Approved THOMAS FINNILA
HVAC-Rough 5/27/2021 Approved THOMAS FINNILA
Interior/Exterior Lathing 5/27/2021 Not Ready for Inspection THOMAS FINNILA
Wood Frame 5/27/2021 Conditional Approval THOMAS FINNILA
BUILDING-Rough-Frame 6/9/2021 Approved JOHN HAYES
Green Building Rough 6/9/2021 Approved JOHN HAYES
Insulation 6/9/2021 Approved JOHN HAYES
Interior/Exterior Lathing 6/9/2021 Partial Approval JOHN HAYES
Wood Frame 6/9/2021 Approved JOHN HAYES
Drywall Nailing 6/16/2021 Approved DANIEL ORRANTE
Interior/Exterior Lathing 6/25/2021 Approved DANIEL DREW
Floor/Roof Diaphrgm/Shear Wall 6/29/2021 Approved DANIEL DREW
Final 11/1/2021 Corrections Issued DANIEL DREW
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Approved DANIEL DREW
Smoke Detectors 11/1/2021 Approved DANIEL DREW
PLUMBING-Final 11/4/2021 Approved DANIEL DREW
HVAC-Rough 11/15/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 12/13/2021 Corrections Issued ARAM AVEDISIAN
Final 12/20/2021 Corrections Issued ARAM AVEDISIAN
Green Building Final 12/20/2021 Approved ARAM AVEDISIAN
HVAC-Final 12/20/2021 Approved ARAM AVEDISIAN
Final 12/22/2021 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 12/22/2021 Approved ARAM AVEDISIAN