12747 W HALKIRK ST 91604
Certificate Information: 12747 W HALKIRK ST 91604
- Application / Permit
- 19010-20000-04938
- Plan Check / Job No.
- B19VN19254
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) IRREGULAR SHAPE 36'-8" x 74'-9", 2 STORY, SNGLE FAMILY DWELLING W/ ATTACHED GARAGE PER ZA-2018-6766-ZAA THE BUILDING SHALL BE EQUIPPED W/ AN AUTOMATIC SPRINKLER SYSTEM IN ACCORDANCE W/ NFPA13D.
- Permit Issued
- Issued on 7/29/2020
- Issuing Office
- Current Status
- CofO Issued on 10/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/26/2019 | SEAN SHAHMIRI |
| Corrections Issued | 12/5/2019 | SEAN SHAHMIRI |
| Quality Review Completed | 12/11/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 12/11/2019 | APPLICANT |
| Green Plans Picked Up | 12/11/2019 | APPLICANT |
| Applicant returned to address corrections | 6/24/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 7/27/2020 | SEAN SHAHMIRI |
| Issued | 7/29/2020 | APPLICANT |
| CofO in Progress | 10/13/2021 | ARAM AVEDISIAN |
| CofO Issued | 10/13/2021 | MICHAEL SMITH |
| Permit Finaled | 10/13/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 3/6/2020 | ROBERT DUFF |
| Green Code | Cleared | 3/10/2020 | MICHAEL AYERS |
| ZA Case | Cleared | 6/25/2020 | PABLO ESTRADA |
| ZI | Cleared | 6/25/2020 | PABLO ESTRADA |
| Low Impact Development | Cleared | 6/29/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 7/7/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 7/7/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 7/14/2020 | GABRIEL ROBLES |
| Trees in Parkway | Cleared | 7/14/2020 | JOHN KIM |
| Grading Pre-Inspection | Cleared | 7/27/2020 | SEAN SHAHMIRI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vahdat,, Shahram; Lic. No.: C47934 | 4333 EMPRESS AVE ENCINO, CA 91436 |
| Engineer | Warling,, Jeffrey Paul; Lic. No.: C43743 | 2828 COCHRAN STREET 321 SIMI VALLEY, CA 93065 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/18/2020 | Approved | DANIEL ORRANTE |
| Footing/Foundation/Slab | 9/8/2020 | Conditional Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 9/10/2020 | Conditional Approval | ARAM AVEDISIAN |
| Wood Frame | 10/2/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2020 | Conditional Approval | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 12/15/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 12/15/2020 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 12/15/2020 | Approved | ARAM AVEDISIAN |
| Wood Frame | 12/15/2020 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 12/23/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 12/23/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 12/23/2020 | Partial Approval | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 12/23/2020 | Approved | ARAM AVEDISIAN |
| Insulation | 1/5/2021 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 1/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 1/13/2021 | Corrections Issued | THOMAS FINNILA |
| Drywall Nailing | 1/15/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 1/15/2021 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 1/15/2021 | Approved | ARAM AVEDISIAN |
| Sewer | 5/4/2021 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 7/22/2021 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 7/22/2021 | Partial Approval | ARAM AVEDISIAN |
| Green Building Final | 7/30/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Pre-Gunite | 7/30/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 7/30/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Final | 8/18/2021 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/18/2021 | Approved | ARAM AVEDISIAN |
| Green Building Final | 8/18/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 8/18/2021 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 8/18/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 8/18/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 8/18/2021 | Approved | ARAM AVEDISIAN |
| Final | 10/13/2021 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 10/13/2021 | Approved | ARAM AVEDISIAN |