10440 W WHIPPLE ST 91602
Certificate Information: 10440 W WHIPPLE ST 91602
- Application / Permit
- 19010-20000-04935
- Plan Check / Job No.
- B19VN19239
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (78'- 4 3/4"x 42'-0") 2 STORY SINGLE FAMILY DWELLING W/ ATTCHED 2-CAR GARAGE AND BASEMENT. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/20/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/27/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/5/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/14/2019 | TROY DEGUZMAN |
| Green Plans Picked Up | 11/14/2019 | APPLICANT |
| Corrections Issued | 11/19/2019 | TROY DEGUZMAN |
| Quality Review Completed | 11/20/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 11/22/2019 | APPLICANT |
| Applicant returned to address corrections | 12/18/2019 | TROY DEGUZMAN |
| Plan Check Approved | 1/8/2020 | TROY DEGUZMAN |
| Issued | 4/20/2020 | LADBS |
| CofO in Progress | 10/21/2021 | THOMAS FINNILA |
| Permit Finaled | 10/27/2021 | MICHAEL SMITH |
| CofO Issued | 10/27/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/10/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2019 | MARKOS PEREZ-BRAN |
| Hydrant and Access approval | Cleared | 12/10/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 12/10/2019 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 12/18/2019 | AARON COSTA |
| Low Impact Development | Cleared | 12/19/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | MARKOS PEREZ-BRAN |
| Hold | Cleared | 6/16/2020 | JASON SHEETS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vidal,, Juan Alonso; Lic. No.: GE861 | 7438 SHIRLEY AVE RESEDA, CA 91335 |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/17/2020 | Approved | THOMAS FINNILA |
| Deputy Shotcrete | 6/25/2020 | Conditional Approval | THOMAS FINNILA |
| Reinforced Concrete Frame | 6/29/2020 | Corrections Issued | THOMAS FINNILA |
| Reinforced Concrete Frame | 7/2/2020 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2020 | Partial Approval | THOMAS FINNILA |
| Underground Mechanical | 8/28/2020 | Partial Approval | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/3/2020 | Corrections Issued | THOMAS FINNILA |
| Deputy Drilled-In Anchors | 9/4/2020 | Conditional Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2020 | Not Ready for Inspection | THOMAS FINNILA |
| Excavation/Setback/Form/Re-Bar | 9/11/2020 | Partial Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 9/17/2020 | Partial Approval | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2020 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 10/22/2020 | Corrections Issued | THOMAS FINNILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/28/2020 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Rough | 10/28/2020 | Partial Approval | THOMAS FINNILA |
| HVAC-Rough | 1/7/2021 | Conditional Approval | THOMAS FINNILA |
| Shower Pan | 1/7/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 1/22/2021 | Corrections Issued | THOMAS FINNILA |
| Shower Pan | 1/22/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 1/27/2021 | Partial Approval | THOMAS FINNILA |
| Deputy Steel/Welding | 1/27/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 1/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 1/27/2021 | Not Ready for Inspection | THOMAS FINNILA |
| BUILDING-Rough-Frame | 2/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Rough | 2/2/2021 | Conditional Approval | THOMAS FINNILA |
| Green Building Rough | 2/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 2/2/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/17/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 2/17/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/22/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 2/22/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Interior/Exterior Lathing | 2/25/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Wood Frame | 2/25/2021 | Corrections Issued | THOMAS FINNILA |
| Interior/Exterior Lathing | 3/1/2021 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 3/5/2021 | Approved | THOMAS FINNILA |
| Green Building Rough | 3/5/2021 | Approved | THOMAS FINNILA |
| Insulation | 3/5/2021 | Approved | THOMAS FINNILA |
| Verify Sprinkler Sign Off | 3/5/2021 | Approved | THOMAS FINNILA |
| Drywall Nailing | 3/18/2021 | Approved | THOMAS FINNILA |
| Deputy Reinf. Concrete | 6/15/2021 | Conditional Approval | THOMAS FINNILA |
| PLUMBING-Final | 8/9/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 8/10/2021 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Final | 8/10/2021 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 8/16/2021 | Approved | MICHEL ABAJAN |
| Green Building Final | 8/16/2021 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 8/16/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 8/16/2021 | Approved | MICHEL ABAJAN |
| Final | 8/23/2021 | Corrections Issued | THOMAS FINNILA |
| Final | 9/7/2021 | Not Ready for Inspection | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/7/2021 | SGSOV Not Ready | THOMAS FINNILA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Approved | LILIANA PORTILLO |
| Underground Mechanical | 10/1/2021 | Corrections Issued | THOMAS FINNILA |
| Underground Mechanical | 10/7/2021 | Approved | JENNIFER RABUCHIN |
| Final | 10/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Green Building Final | 10/13/2021 | Corrections Issued | THOMAS FINNILA |
| Service/Power Release | 10/13/2021 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 10/13/2021 | Approved | THOMAS FINNILA |
| Final | 10/20/2021 | OK to Issue CofO | THOMAS FINNILA |
| Green Building Final | 10/20/2021 | Approved | THOMAS FINNILA |
| Service/Power Release | 10/20/2021 | Approved | THOMAS FINNILA |