5137 N NAGLE AVE 91423

Certificate Information: 5137 N NAGLE AVE 91423

Application / Permit
19010-20000-04930
Plan Check / Job No.
B19VN19207
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD/ GAR
Permit Issued
Issued on 1/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 CHON CHIO KUO
Corrections Issued 11/18/2019 CHON CHIO KUO
Quality Review Completed 11/21/2019 GUANG MIN TUNG
Building Plans Picked Up 11/25/2019 APPLICANT
Green Plans Picked Up 11/25/2019 APPLICANT
Applicant returned to address corrections 1/16/2020 CHON CHIO KUO
Plan Check Approved 1/29/2020 CHON CHIO KUO
Issued 1/30/2020 LADBS
CofO in Progress 7/1/2020 CHARLES POWELL
Permit Finaled 7/9/2020 MICHAEL SMITH
CofO Issued 7/9/2020 MICHAEL SMITH
Permit Finaled 7/9/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/5/2019 ADRIAN CASTRO
Permit Cleared 12/5/2019 ADRIAN CASTRO
Sewer availability Cleared 12/5/2019 ADRIAN CASTRO
Low Impact Development Cleared 12/12/2019 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 1/9/2020 AARON COSTA
Hydrant and Access approval Cleared 1/10/2020 GEORGE SUCHAND
ZI Cleared 1/29/2020 DAISY BENICIA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 2/6/2020 Approved CHARLES POWELL
Footing/Foundation/Slab 2/14/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 2/26/2020 Approved CHARLES POWELL
Green Building Rough 2/26/2020 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 2/26/2020 Not Ready for Inspection CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/6/2020 Approved CHARLES POWELL
HVAC-Rough 3/16/2020 Approved CHARLES POWELL
PLUMBING-Rough 3/16/2020 Approved CHARLES POWELL
Shower Pan 3/23/2020 Approved CHARLES POWELL
BUILDING-Rough-Frame 3/25/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 3/25/2020 Approved CHARLES POWELL
Green Building Rough 3/25/2020 Not Ready for Inspection CHARLES POWELL
Verify Sprinkler Sign Off 3/25/2020 Approved CHARLES POWELL
Deputy Wood Construction 4/8/2020 Partial Approval MARK JOHNSON
Green Building Rough 4/14/2020 Approved TROY SANDERS
Insulation 4/14/2020 Not Ready for Inspection TROY SANDERS
Interior/Exterior Lathing 4/14/2020 Approved TROY SANDERS
Insulation 4/16/2020 Conditional Approval BRENDAN LOONEY
Drywall Nailing 4/20/2020 Not Ready for Inspection GREGG CUMMINGS
Insulation 4/22/2020 Approved GREGG CUMMINGS
Pre-Inspection 4/22/2020 Approved GREGG CUMMINGS
Gas Test 5/21/2020 Approved CHARLES POWELL
ELECTRICAL-Final 6/24/2020 Approved CHARLES POWELL
HVAC-Final 6/24/2020 Approved CHARLES POWELL
PLUMBING-Final 6/25/2020 Approved CHARLES POWELL
Drywall Nailing 6/29/2020 Approved CHARLES POWELL
Final 6/29/2020 Partial Approval CHARLES POWELL
Green Building Final 6/29/2020 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 6/29/2020 SGSOV Approved CHARLES POWELL
Service/Power Release 6/29/2020 Approved CHARLES POWELL
Smoke Detectors 6/29/2020 Approved CHARLES POWELL