7618 W BECKETT ST 91042

Certificate Information: 7618 W BECKETT ST 91042

Application / Permit
19010-20000-04892
Plan Check / Job No.
B19VN19130
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 82'-1" X 32'-0" ONE STORY SFD W/ATTACHED TWO CAR GARAGE. [FIRE SPRINKLERS REQ'D THROUGH-OUT].
Permit Issued
Issued on 1/13/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/15/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2019 APPLICANT
Assigned to Plan Check Engineer 11/14/2019 ARTIN ZARUKIAN
Corrections Issued 11/16/2019 ARTIN ZARUKIAN
Green Plans Picked Up 11/19/2019 APPLICANT
Quality Review Completed 11/20/2019 GUANG MIN TUNG
Building Plans Picked Up 11/21/2019 APPLICANT
Plan Check Approved 1/13/2020 ARTIN ZARUKIAN
Issued 1/13/2020 LADBS
CofO in Progress 9/29/2020 BEAU COLLINS
CofO Issued 10/15/2020 MICHAEL SMITH
Permit Finaled 10/15/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/18/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 11/19/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 11/19/2019 GEORGE SUCHAND
Permit Cleared 11/19/2019 ADRIAN CASTRO
Sewer availability Cleared 11/19/2019 ADRIAN CASTRO
Trees in Parkway Cleared 11/20/2019 JOHN KIM
Low Impact Development Cleared 12/18/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/23/2019 LEE GUILBEAUX
Green Code Cleared 12/26/2019 DAVID MATSON
GPI Written Notices Cleared 1/6/2020 ARTIN ZARUKIAN
Grading Pre-Inspection Cleared 1/6/2020 ARTIN ZARUKIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

DAVID ANDERSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/10/2020 Approved BEAU COLLINS
Excavation/Setback/Form/Re-Bar 2/21/2020 Approved BEAU COLLINS
Underground Mechanical 2/21/2020 Partial Approval BEAU COLLINS
Footing/Foundation/Slab 2/24/2020 Not Ready for Inspection PIERRE VEGA
Excavation/Setback/Form/Re-Bar 2/25/2020 Approved BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 3/23/2020 Corrections Issued BEAU COLLINS
ELECTRICAL-Rough 4/8/2020 Not Ready for Inspection BEAU COLLINS
Floor/Roof Diaphrgm/Shear Wall 4/8/2020 Approved BEAU COLLINS
HVAC-Rough 4/8/2020 Approved BEAU COLLINS
PLUMBING-Rough 4/8/2020 Partial Approval BEAU COLLINS
BUILDING-Rough-Frame 4/23/2020 Approved BEAU COLLINS
Green Building Rough 4/23/2020 Approved BEAU COLLINS
Insulation 4/23/2020 Approved BEAU COLLINS
Verify Sprinkler Sign Off 4/23/2020 Approved BEAU COLLINS
Drywall Nailing 4/28/2020 Approved BEAU COLLINS
Interior/Exterior Lathing 4/28/2020 Partial Approval BEAU COLLINS
Sewer 6/16/2020 Not Ready for Inspection BEAU COLLINS
ELECTRICAL-Final 7/17/2020 Approved BEAU COLLINS
HVAC-Final 7/17/2020 Not Ready for Inspection BEAU COLLINS
Service/Power Release 7/17/2020 Approved BEAU COLLINS
Final 9/16/2020 Corrections Issued BEAU COLLINS
Footing/Foundation/Slab 9/16/2020 Approved BEAU COLLINS
Green Building Final 9/16/2020 Approved BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 9/16/2020 SGSOV Not Ready BEAU COLLINS
Smoke Detectors 9/16/2020 Approved BEAU COLLINS
Final 9/29/2020 OK to Issue CofO BEAU COLLINS
SGSOV-Seismic Gas S/O Valve 9/29/2020 SGSOV Approved BEAU COLLINS