19125 W STRATHERN ST 91335

Certificate Information: 19125 W STRATHERN ST 91335

Application / Permit
19010-20000-04883
Plan Check / Job No.
B19VN19083
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 30'-4" X 40'-6" DETACHED ACCESSORY DWELLING UNIT WITH 5' X 6' PORCH ALL WORK PER WFPP PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 8/16/2021
Issuing Office
Current Status
CofO Issued on 12/30/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 12/4/2019 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 12/9/2019 OMID HEDAYAT
Building Plans Picked Up 12/11/2019 APPLICANT
Green Plans Picked Up 12/11/2019 APPLICANT
Applicant returned to address corrections 6/23/2021 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 7/7/2021 SEWADA ZADOORAN MILAGARDI
Issued 8/16/2021 APPLICANT
CofO in Progress 12/30/2021 VINCENT HANLEY
CofO in Progress 12/30/2021 VINCENT HANLEY
Permit Finaled 12/30/2021 MICHAEL SMITH
CofO Issued 12/30/2021 MICHAEL SMITH
Permit Finaled 12/30/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/12/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 1/13/2021 GABRIEL ROBLES
Sewer availability Cleared 1/13/2021 GABRIEL ROBLES
Low Impact Development Cleared 2/24/2021 ORVAL HERNANDEZ-MARCI
Hydrant and Access approval Cleared 4/13/2021 MATTHEW CRAIG
Green Code Cleared 6/18/2021 MICHAEL AYERS
Roof/Waste drainage to street Cleared 6/23/2021 DAGOVERTO GUERRERO
Zoning Information File Cleared 7/7/2021 SEWADA ZADOORAN MILAGARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/13/2021 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 9/13/2021 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/17/2021 Not Ready for Inspection VINCENT HANLEY
Footing/Foundation/Slab 9/17/2021 Not Ready for Inspection VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 9/22/2021 Approved VINCENT HANLEY
Footing/Foundation/Slab 9/22/2021 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 10/13/2021 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 10/14/2021 Approved VINCENT HANLEY
HVAC-Rough 10/14/2021 Approved VINCENT HANLEY
PLUMBING-Rough 10/14/2021 Approved VINCENT HANLEY
Underground Mechanical 10/14/2021 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 10/21/2021 Order to Comply Issued VINCENT HANLEY
Green Building Rough 10/21/2021 Approved VINCENT HANLEY
Interior/Exterior Lathing 10/21/2021 Partial Approval VINCENT HANLEY
Shower Pan 10/21/2021 Approved VINCENT HANLEY
Drywall Nailing 10/27/2021 Approved VINCENT HANLEY
BUILDING-Rough-Frame 11/29/2021 Approved VINCENT HANLEY
ELECTRICAL-Final 11/29/2021 Approved VINCENT HANLEY
Final 11/29/2021 Corrections Issued VINCENT HANLEY
Gas Test 11/29/2021 Approved VINCENT HANLEY
Green Building Final 11/29/2021 Approved VINCENT HANLEY
PLUMBING-Final 11/29/2021 Corrections Issued VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 11/29/2021 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 11/29/2021 Not Ready for Inspection VINCENT HANLEY
Smoke Detectors 11/29/2021 Approved VINCENT HANLEY
Verify Sprinkler Sign Off 11/29/2021 Not Ready for Inspection VINCENT HANLEY
ELECTRICAL-Final 12/21/2021 Approved VINCENT HANLEY
Final 12/21/2021 OK to Issue CofO VINCENT HANLEY
HVAC-Final 12/21/2021 Approved VINCENT HANLEY
PLUMBING-Final 12/21/2021 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 12/21/2021 SGSOV Approved VINCENT HANLEY
Service/Power Release 12/21/2021 Approved VINCENT HANLEY