10619 N VANORA DR 91040

Certificate Information: 10619 N VANORA DR 91040

Application / Permit
19010-20000-04876
Plan Check / Job No.
B19VN19058
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 40'-0"" X 32'-7' IRREGULAR SHAPE DET. ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 11/13/2020
Issuing Office
Current Status
CofO Corrected on 2/28/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 PARISA ZAHABI
Corrections Issued 12/9/2019 PARISA ZAHABI
Quality Review Completed 12/11/2019 OMID HEDAYAT
Building Plans Picked Up 12/12/2019 APPLICANT
Green Plans Picked Up 12/12/2019 APPLICANT
Applicant returned to address corrections 10/20/2020 PARISA ZAHABI
Plan Check Approved 10/21/2020 PARISA ZAHABI
Issued 11/13/2020 APPLICANT
CofO in Progress 7/27/2021 MATTHEW NELSON
CofO Issued-Status Void 9/8/2021 MICHAEL SMITH
Permit Finaled-Status Void 9/8/2021 MICHAEL SMITH
Re-Activate Permit 2/28/2022 DAVID MATSON
Permit Finaled 2/28/2022 JOHN JANSON
CofO Corrected 2/28/2022 JOHN JANSON
Permit Finaled 2/28/2022 JOHN JANSON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 2/14/2020 BARTON HOLMES
Construction near power lines Cleared 2/19/2020 ERNEST FRESQUEZ
ZI Cleared 2/27/2020 PEGGY MALONE-BROWN
Green Code Cleared 3/5/2020 AARON COSTA
Low Impact Development Cleared 8/24/2020 MARTIN FRAGOSO
Address approval Cleared 8/26/2020 JOHN TRIANTAFYLLOS
Eng Process Fee Ord 176,300 Cleared 8/27/2020 JOHN TRIANTAFYLLOS
Roof/Waste drainage to street Cleared 8/27/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 8/27/2020 JOHN TRIANTAFYLLOS
Hydrant and Access approval Cleared 9/23/2020 MATTHEW CRAIG
GPI Written Notices Cleared 10/21/2020 PARISA ZAHABI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/9/2020 Corrections Issued MATTHEW NELSON
Footing/Foundation/Slab 12/9/2020 Corrections Issued MATTHEW NELSON
Pre-Inspection 12/9/2020 Partial Inspection MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 12/14/2020 Approved MATTHEW NELSON
Footing/Foundation/Slab 12/14/2020 Approved MATTHEW NELSON
Pre-Inspection 12/14/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 12/18/2020 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 12/21/2020 Partial Inspection MATTHEW NELSON
BUILDING-Rough-Frame 1/12/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 1/12/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 1/12/2021 Not Ready for Inspection MATTHEW NELSON
MERV13>=Rough 1/12/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 1/12/2021 Not Ready for Inspection MATTHEW NELSON
Verify Sprinkler Sign Off 1/12/2021 Approved MATTHEW NELSON
Wood Frame 1/12/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 1/22/2021 Partial Inspection MATTHEW NELSON
Green Building Rough 1/22/2021 Approved MATTHEW NELSON
MERV13>=Rough 1/22/2021 Not Ready for Inspection MATTHEW NELSON
Underground Mechanical 1/22/2021 Partial Approval MATTHEW NELSON
Interior/Exterior Lathing 1/27/2021 Approved MATTHEW NELSON
Rough-Elec/Plmb/HVAC 2/3/2021 Approved MATTHEW NELSON
Insulation 2/5/2021 Approved MATTHEW NELSON
Drywall Nailing 2/16/2021 Approved MATTHEW NELSON
Gas Test 2/16/2021 Approved MATTHEW NELSON
Interior/Exterior Lathing 2/23/2021 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/15/2021 Not Ready for Inspection JOHN HAYES
Final 6/15/2021 Corrections Issued JOHN HAYES
Green Building Final 6/15/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 6/15/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 6/15/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 6/15/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 6/15/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 7/6/2021 Approved MATTHEW NELSON
Gas Test 7/6/2021 Approved MATTHEW NELSON
Green Building Final 7/6/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 7/6/2021 Approved MATTHEW NELSON
MERV13>=Final 7/6/2021 Approved MATTHEW NELSON
PLUMBING-Final 7/6/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 7/6/2021 SGSOV Approved MATTHEW NELSON
Service/Power Release 7/6/2021 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 7/6/2021 Approved MATTHEW NELSON
Verify Rec and Parks Fee Memo 7/6/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 7/12/2021 Approved MATTHEW NELSON
Final 7/12/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Final 7/12/2021 Approved MATTHEW NELSON
MERV13>=Rough 7/12/2021 Approved MATTHEW NELSON
Service/Power Release 7/12/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 7/19/2021 Approved MATTHEW NELSON
Final 7/19/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 7/19/2021 Approved MATTHEW NELSON
PLUMBING-Final 7/19/2021 Approved MATTHEW NELSON
Service/Power Release 7/19/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 7/26/2021 Approved MATTHEW NELSON
Final 7/26/2021 OK to Issue CofO MATTHEW NELSON
Gas Test 7/26/2021 Approved MATTHEW NELSON
HVAC-Final 7/26/2021 Approved MATTHEW NELSON
PLUMBING-Final 7/26/2021 Approved MATTHEW NELSON
Service/Power Release 7/26/2021 Approved MATTHEW NELSON