19446 W VICTORY BLVD 91335

Certificate Information: 19446 W VICTORY BLVD 91335

Application / Permit
19010-20000-04870
Plan Check / Job No.
B19VN19035
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
MAJOR REMODEL OF (E) GARAGE (WALLS TO REMAIN: 20'LINEAR LENGTH WALL ON EAST SIDE, 5'5" WALL ON NORTH SIDE, AND 1'6" WALL ON SOUTH SIDE) TO MAKE A NEW 28'6"X24'4" IRREGULAR SHAPED 2-STORY ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 2/11/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/1/2019 APPLICANT
Assigned to Plan Check Engineer 11/26/2019 MARVEL DELACRUZ
Corrections Issued 12/4/2019 MARVEL DELACRUZ
Green Plans Picked Up 12/5/2019 APPLICANT
Quality Review Completed 12/6/2019 GUANG MIN TUNG
Building Plans Picked Up 12/6/2019 APPLICANT
Plan Check Approved 2/11/2020 MARVEL DELACRUZ
Issued 2/11/2020 LADBS
CofO in Progress 6/11/2021 HENRY KIM
Permit Finaled 6/15/2021 JOHN JANSON
CofO Issued 6/15/2021 JOHN JANSON
Permit Finaled 6/15/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/17/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/17/2019 GUILLERMO PETRA
Permit Cleared 12/17/2019 GUILLERMO PETRA
Sewer availability Cleared 12/17/2019 GUILLERMO PETRA
ZI Cleared 12/17/2019 DAISY BENICIA
Green Code Cleared 1/23/2020 AARON COSTA
Low Impact Development Cleared 1/28/2020 ORVAL HERNANDEZ-MARCIAL
Trees in Parkway Cleared 1/28/2020 JOHN KIM
Hydrant and Access approval Cleared 1/30/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 1/30/2020 APEKSHYA BAJRACHARYA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/5/2020 Partial Approval HENRY KIM
Pre-Inspection 5/5/2020 Corrections Issued HENRY KIM
Deputy Drilled-In Anchors 5/6/2020 Conditional Approval HENRY KIM
Footing/Foundation/Slab 5/12/2020 Approved HENRY KIM
BUILDING-Rough-Frame 7/7/2020 Not Ready for Inspection HENRY KIM
ELECTRICAL-Rough 7/7/2020 Not Ready for Inspection HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Corrections Issued HENRY KIM
Green Building Rough 7/7/2020 Not Ready for Inspection HENRY KIM
HVAC-Rough 7/7/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/7/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/9/2020 Corrections Issued HENRY KIM
ELECTRICAL-Rough 7/10/2020 Approved HENRY KIM
HVAC-Rough 7/14/2020 Approved HENRY KIM
Underground Mechanical 7/23/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 7/28/2020 Corrections Issued HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/28/2020 Corrections Issued HENRY KIM
Green Building Rough 7/28/2020 Not Ready for Inspection HENRY KIM
PLUMBING-Rough 7/28/2020 Approved HENRY KIM
Sewer 7/28/2020 Approved HENRY KIM
Underground Mechanical 7/28/2020 Corrections Issued HENRY KIM
Underground Mechanical 7/29/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Partial Approval HENRY KIM
Insulation 7/31/2020 Partial Approval HENRY KIM
BUILDING-Rough-Frame 8/4/2020 Approved HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 8/4/2020 Approved HENRY KIM
Insulation 8/4/2020 Partial Approval HENRY KIM
Interior/Exterior Lathing 8/5/2020 Approved HENRY KIM
Insulation 8/14/2020 Corrections Issued HENRY KIM
Drywall Nailing 8/20/2020 Approved HENRY KIM
Green Building Rough 8/20/2020 Approved HENRY KIM
Insulation 8/20/2020 Approved HENRY KIM
Interior/Exterior Lathing 10/21/2020 Partial Approval HENRY KIM
Shower Pan 10/21/2020 Corrections Issued HENRY KIM
Shower Pan 10/29/2020 Corrections Issued HENRY KIM
Interior/Exterior Lathing 11/5/2020 Approved HENRY KIM
Shower Pan 11/5/2020 Approved HENRY KIM
Underground Mechanical 11/10/2020 Approved HENRY KIM
ELECTRICAL-Final 1/12/2021 Corrections Issued HENRY KIM
Final 1/12/2021 Corrections Issued HENRY KIM
Gas Test 1/12/2021 Corrections Issued HENRY KIM
Green Building Final 1/12/2021 Approved HENRY KIM
HVAC-Final 1/12/2021 Corrections Issued HENRY KIM
PLUMBING-Final 1/12/2021 Corrections Issued HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/12/2021 SGSOV Not Ready HENRY KIM
Smoke Detectors 1/12/2021 Approved HENRY KIM
Gas Test 1/22/2021 Approved HENRY KIM
PLUMBING-Final 1/22/2021 Approved HENRY KIM
SGSOV-Seismic Gas S/O Valve 1/22/2021 SGSOV Approved HENRY KIM
HVAC-Final 1/27/2021 Corrections Issued HENRY KIM
HVAC-Final 2/8/2021 Approved HENRY KIM
Final 2/22/2021 Corrections Issued HENRY KIM
ELECTRICAL-Final 6/11/2021 Approved HENRY KIM
Final 6/11/2021 OK to Issue CofO HENRY KIM