5513 N MURIETTA AVE 91401

Certificate Information: 5513 N MURIETTA AVE 91401

Application / Permit
19010-20000-04838
Plan Check / Job No.
B19VN18840
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
NEW FULL BATH ACCESS TO SW. POOL/SPA & LIV. ROOM FOR OUTDOOR POOL/SPA + 346 SF PATIO TRELLIS (EXEMPTED FROM BMO CALCS).
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 ABDUL CHEGENI
Corrections Issued 11/12/2019 ABDUL CHEGENI
Quality Review Completed 11/13/2019 STEVEN KIM
Building Plans Picked Up 11/14/2019 APPLICANT
Green Plans Picked Up 11/14/2019 APPLICANT
Applicant returned to address corrections 2/4/2020 ABDUL CHEGENI
Applicant returned to address corrections 2/10/2020 ABDUL CHEGENI
Plan Check Approved 2/12/2020 ABDUL CHEGENI
Issued 2/12/2020 LADBS
CofO in Progress 3/4/2021 BEAU COLLINS
No Progress 3/13/2021 MICHAEL TEMPLE
CofO in Progress 4/14/2021 MICHAEL TEMPLE
CofO Issued 4/17/2021 MICHAEL SMITH
Permit Finaled 4/17/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/19/2019 MICHAEL AYERS
CPC Cleared 12/30/2019 HERMINIGILDO AGUSTIN
Eng Process Fee Ord 176,300 Cleared 12/30/2019 ADRIAN CASTRO
Sewer availability Cleared 12/30/2019 ADRIAN CASTRO
Low Impact Development Cleared 1/10/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 1/10/2020 JOHN LIN
Hydrant and Access approval Cleared 1/16/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/19/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/26/2020 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/3/2020 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/23/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 6/23/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/23/2020 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 6/23/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 6/25/2020 Approved MISAEL ESPARZA
HVAC-Rough 6/25/2020 Approved MISAEL ESPARZA
Insulation 7/6/2020 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 7/6/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 7/9/2020 Corrections Issued MISAEL ESPARZA
Insulation 7/9/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/9/2020 Approved MISAEL ESPARZA
Shower Pan 7/9/2020 Approved MISAEL ESPARZA
Drywall Nailing 7/15/2020 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 7/15/2020 Conditional Approval MISAEL ESPARZA
Pre-Inspection 9/2/2020 Corrections Issued DAVID MATSON
Service/Power Release 12/1/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 12/14/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 12/14/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/8/2021 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 1/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
Final 1/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/8/2021 Partial Approval JENNIFER RABUCHIN
Green Building Rough 1/8/2021 Approved JENNIFER RABUCHIN
HVAC-Final 1/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Final 1/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/8/2021 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 1/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 1/8/2021 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 1/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 1/15/2021 Not Ready for Inspection JOHN HAYES
Final 1/15/2021 Corrections Issued JOHN HAYES
Green Building Final 1/15/2021 Not Ready for Inspection JOHN HAYES
Service/Power Release 1/15/2021 Not Ready for Inspection JOHN HAYES
Verify Sprinkler Sign Off 1/15/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/27/2021 Corrections Issued BEAU COLLINS
Green Building Final 1/27/2021 Approved BEAU COLLINS
Service/Power Release 1/27/2021 Not Ready for Inspection BEAU COLLINS
Verify Sprinkler Sign Off 1/27/2021 Approved BEAU COLLINS
BUILDING-Rough-Frame 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
Final 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
Service/Power Release 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 2/17/2021 Not Ready for Inspection JOHN HAYES
Final 2/17/2021 Not Ready for Inspection JOHN HAYES
Service/Power Release 2/17/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/25/2021 Not Ready for Inspection JENNIFER RABUCHIN
Final 2/25/2021 Not Ready for Inspection JENNIFER RABUCHIN
Service/Power Release 2/25/2021 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 3/3/2021 Approved BEAU COLLINS
Final 3/3/2021 OK to Issue CofO BEAU COLLINS
Service/Power Release 3/3/2021 Approved BEAU COLLINS