5513 N MURIETTA AVE 91401

Certificate Information: 5513 N MURIETTA AVE 91401

Application / Permit
19010-20000-04837
Plan Check / Job No.
B19VN18840
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2-STORY SFD WITH ATTACHED GARAGE <SPRINKLERS REQ'D THROUGHOUT> - 1 OF 2
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/30/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 ABDUL CHEGENI
Corrections Issued 11/12/2019 ABDUL CHEGENI
Quality Review Completed 11/13/2019 STEVEN KIM
Building Plans Picked Up 11/14/2019 APPLICANT
Green Plans Picked Up 11/14/2019 APPLICANT
Applicant returned to address corrections 2/4/2020 ABDUL CHEGENI
Applicant returned to address corrections 2/10/2020 ABDUL CHEGENI
Plan Check Approved 2/12/2020 ABDUL CHEGENI
Issued 2/12/2020 LADBS
CofO in Progress 2/26/2021 JENNIFER RABUCHIN
Permit Finaled 4/10/2021 MICHAEL SMITH
CofO Issued 4/10/2021 MICHAEL SMITH
Permit Finaled 4/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Green Code Cleared 12/19/2019 MICHAEL AYERS
Address approval Cleared 12/30/2019 ADRIAN CASTRO
CPC Cleared 12/30/2019 DAISY BENICIA
Eng Process Fee Ord 176,300 Cleared 12/30/2019 ADRIAN CASTRO
Low Impact Development Cleared 1/10/2020 JORGE MEJIA LEMUS
Permit Cleared 1/10/2020 JOHN LIN
Roof/Waste drainage to street Cleared 1/10/2020 JOHN LIN
Sewer availability Cleared 1/10/2020 JOHN LIN
Hydrant and Access approval Cleared 1/16/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/19/2020 Corrections Issued MISAEL ESPARZA
PLUMBING-Rough 2/26/2020 Partial Approval MISAEL ESPARZA
Footing/Foundation/Slab 3/3/2020 Approved MISAEL ESPARZA
Deputy Steel/Welding 3/24/2020 Approved MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Partial Approval MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Corrections Issued MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 5/5/2020 Partial Approval MISAEL ESPARZA
BUILDING-Rough-Frame 6/23/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 6/23/2020 Not Ready for Inspection MISAEL ESPARZA
PLUMBING-Rough 6/23/2020 Approved MISAEL ESPARZA
Verify Sprinkler Sign Off 6/23/2020 Not Ready for Inspection MISAEL ESPARZA
ELECTRICAL-Rough 6/25/2020 Corrections Issued MISAEL ESPARZA
HVAC-Rough 6/25/2020 Approved MISAEL ESPARZA
BUILDING-Rough-Frame 6/29/2020 Approved MISAEL ESPARZA
ELECTRICAL-Rough 6/29/2020 Approved MISAEL ESPARZA
Green Building Rough 6/29/2020 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 6/29/2020 Approved MISAEL ESPARZA
Insulation 7/6/2020 Not Ready for Inspection MISAEL ESPARZA
Interior/Exterior Lathing 7/6/2020 Not Ready for Inspection MISAEL ESPARZA
Insulation 7/9/2020 Conditional Approval MISAEL ESPARZA
Interior/Exterior Lathing 7/9/2020 Partial Approval MISAEL ESPARZA
Shower Pan 7/9/2020 Approved MISAEL ESPARZA
Drywall Nailing 7/15/2020 Approved MISAEL ESPARZA
Green Building Rough 7/15/2020 Approved MISAEL ESPARZA
Interior/Exterior Lathing 7/15/2020 Approved MISAEL ESPARZA
Insulation 9/2/2020 Approved DAVID MATSON
Insulation 9/8/2020 Approved ARAM AVEDISIAN
Underground Mechanical 9/10/2020 Partial Approval WILLIAM KUEHN
Service/Power Release 12/1/2020 Corrections Issued JENNIFER RABUCHIN
Special/Order Compliance 12/1/2020 Corrections Issued JENNIFER RABUCHIN
Verify Rec and Parks Fee Memo 12/1/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Final 12/14/2020 Not Ready for Inspection JOHN HAYES
Final 12/14/2020 Corrections Issued JOHN HAYES
HVAC-Final 12/14/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 1/8/2021 Approved JENNIFER RABUCHIN
Final 1/8/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 1/8/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 1/8/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 1/8/2021 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 1/8/2021 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 1/8/2021 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 1/8/2021 Approved JENNIFER RABUCHIN
Final 1/15/2021 Corrections Issued JOHN HAYES
Green Building Final 1/15/2021 Not Ready for Inspection JOHN HAYES
Service/Power Release 1/15/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 1/27/2021 Corrections Issued BEAU COLLINS
Service/Power Release 1/27/2021 Not Ready for Inspection BEAU COLLINS
BUILDING-Rough-Frame 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
Final 2/5/2021 No Access for Inspection DAVID SANDOVAL
Green Building Final 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
Service/Power Release 2/5/2021 Not Ready for Inspection DAVID SANDOVAL
BUILDING-Rough-Frame 2/17/2021 Not Ready for Inspection JOHN HAYES
Final 2/17/2021 Not Ready for Inspection JOHN HAYES
Green Building Final 2/17/2021 Not Ready for Inspection JOHN HAYES
Service/Power Release 2/17/2021 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 2/25/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 2/25/2021 Approved JENNIFER RABUCHIN
Final 2/25/2021 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 2/25/2021 Approved JENNIFER RABUCHIN
Green Building Final 2/25/2021 Approved JENNIFER RABUCHIN
HVAC-Final 2/25/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 2/25/2021 Approved JENNIFER RABUCHIN
Service/Power Release 2/25/2021 Approved JENNIFER RABUCHIN