4548 N STERN AVE 91423

Certificate Information: 4548 N STERN AVE 91423

Application / Permit
19010-20000-04827
Plan Check / Job No.
B19VN18783
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 45'-5" X 85'-3" 2-STORY SFD W/ ATTACHED 2-CAR GARAGE. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 JENNIFER LEE
Corrections Issued 11/14/2019 JENNIFER LEE
Quality Review Completed 11/14/2019 STEVEN KIM
Building Plans Picked Up 11/14/2019 APPLICANT
Green Plans Picked Up 11/18/2019 APPLICANT
Plan Check Approved 1/16/2020 JENNIFER LEE
Issued 1/17/2020 LADBS
CofO in Progress 11/4/2020 ARAM AVEDISIAN
CofO Issued 12/18/2020 DANIEL ORRANTE
Permit Finaled 12/18/2020 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 12/17/2019 ANDRES COVARRUBIAS
Address approval Cleared 12/19/2019 GUILLERMO PETRA
Permit Cleared 12/19/2019 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 12/19/2019 GUILLERMO PETRA
Construction near power lines Cleared 12/27/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 1/6/2020 JOHN LIN
Frnt yard landscape/Water mgmt Cleared 1/6/2020 STEVEN WECHSLER
Hydrant and Access approval Cleared 1/6/2020 GEORGE SUCHAND
Sewer availability Cleared 1/6/2020 JOHN LIN
ZA Case Cleared 1/6/2020 STEVEN WECHSLER
Green Code Cleared 1/7/2020 AARON COSTA
Trees in Parkway Cleared 1/10/2020 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/29/2020 Corrections Issued JOHN HAYES
PLUMBING-Rough 1/31/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 1/31/2020 Not Ready for Inspection JOHN HAYES
Underground Mechanical 2/5/2020 Approved CHARLES POWELL
Footing/Foundation/Slab 2/19/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 3/10/2020 Approved CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/14/2020 Not Ready for Inspection CHARLES POWELL
Deputy Wood Construction 5/20/2020 Partial Approval CHARLES POWELL
Floor/Roof Diaphrgm/Shear Wall 5/20/2020 Approved CHARLES POWELL
Shower Pan 5/20/2020 Approved CHARLES POWELL
ELECTRICAL-Rough 5/28/2020 Approved CHARLES POWELL
PLUMBING-Rough 5/28/2020 Corrections Issued CHARLES POWELL
Interior/Exterior Lathing 6/2/2020 Approved CHARLES POWELL
PLUMBING-Rough 6/2/2020 Partial Approval CHARLES POWELL
BUILDING-Rough-Frame 6/11/2020 Approved ARAM AVEDISIAN
Green Building Rough 6/11/2020 Approved ARAM AVEDISIAN
HVAC-Rough 6/11/2020 Approved ARAM AVEDISIAN
MERV13>=Rough 6/11/2020 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 6/11/2020 Approved ARAM AVEDISIAN
Drywall Nailing 6/19/2020 Approved CHARLES POWELL
Insulation 6/19/2020 Approved CHARLES POWELL
Special/Order Compliance 8/5/2020 Partial Approval CHARLES POWELL
ELECTRICAL-Final 10/15/2020 Approved CHARLES POWELL
Gas Test 10/15/2020 Approved CHARLES POWELL
HVAC-Final 10/15/2020 Approved CHARLES POWELL
PLUMBING-Final 10/15/2020 Partial Approval CHARLES POWELL
Final 10/26/2020 Corrections Issued ARAM AVEDISIAN
Green Building Final 10/26/2020 Approved ARAM AVEDISIAN
MERV13>=Final 10/26/2020 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/26/2020 SGSOV Not Ready ARAM AVEDISIAN
Service/Power Release 10/26/2020 Not Ready for Inspection ARAM AVEDISIAN
Smoke Detectors 10/26/2020 Approved ARAM AVEDISIAN
Final 11/2/2020 OK to Issue CofO ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/2/2020 SGSOV Approved ARAM AVEDISIAN
Service/Power Release 11/2/2020 Approved ARAM AVEDISIAN