4548 N STERN AVE 91423
Certificate Information: 4548 N STERN AVE 91423
- Application / Permit
- 19010-20000-04827
- Plan Check / Job No.
- B19VN18783
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 45'-5" X 85'-3" 2-STORY SFD W/ ATTACHED 2-CAR GARAGE. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/18/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | JENNIFER LEE |
| Corrections Issued | 11/14/2019 | JENNIFER LEE |
| Quality Review Completed | 11/14/2019 | STEVEN KIM |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Green Plans Picked Up | 11/18/2019 | APPLICANT |
| Plan Check Approved | 1/16/2020 | JENNIFER LEE |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 11/4/2020 | ARAM AVEDISIAN |
| CofO Issued | 12/18/2020 | DANIEL ORRANTE |
| Permit Finaled | 12/18/2020 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/17/2019 | ANDRES COVARRUBIAS |
| Address approval | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Permit | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 12/27/2019 | OSCAR CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2020 | JOHN LIN |
| Frnt yard landscape/Water mgmt | Cleared | 1/6/2020 | STEVEN WECHSLER |
| Hydrant and Access approval | Cleared | 1/6/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 1/6/2020 | JOHN LIN |
| ZA Case | Cleared | 1/6/2020 | STEVEN WECHSLER |
| Green Code | Cleared | 1/7/2020 | AARON COSTA |
| Trees in Parkway | Cleared | 1/10/2020 | JOHN KIM |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/29/2020 | Corrections Issued | JOHN HAYES |
| PLUMBING-Rough | 1/31/2020 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 1/31/2020 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 2/5/2020 | Approved | CHARLES POWELL |
| Footing/Foundation/Slab | 2/19/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2020 | Approved | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2020 | Not Ready for Inspection | CHARLES POWELL |
| Deputy Wood Construction | 5/20/2020 | Partial Approval | CHARLES POWELL |
| Floor/Roof Diaphrgm/Shear Wall | 5/20/2020 | Approved | CHARLES POWELL |
| Shower Pan | 5/20/2020 | Approved | CHARLES POWELL |
| ELECTRICAL-Rough | 5/28/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 5/28/2020 | Corrections Issued | CHARLES POWELL |
| Interior/Exterior Lathing | 6/2/2020 | Approved | CHARLES POWELL |
| PLUMBING-Rough | 6/2/2020 | Partial Approval | CHARLES POWELL |
| BUILDING-Rough-Frame | 6/11/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 6/11/2020 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 6/11/2020 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 6/11/2020 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 6/11/2020 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 6/19/2020 | Approved | CHARLES POWELL |
| Insulation | 6/19/2020 | Approved | CHARLES POWELL |
| Special/Order Compliance | 8/5/2020 | Partial Approval | CHARLES POWELL |
| ELECTRICAL-Final | 10/15/2020 | Approved | CHARLES POWELL |
| Gas Test | 10/15/2020 | Approved | CHARLES POWELL |
| HVAC-Final | 10/15/2020 | Approved | CHARLES POWELL |
| PLUMBING-Final | 10/15/2020 | Partial Approval | CHARLES POWELL |
| Final | 10/26/2020 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 10/26/2020 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 10/26/2020 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 10/26/2020 | SGSOV Not Ready | ARAM AVEDISIAN |
| Service/Power Release | 10/26/2020 | Not Ready for Inspection | ARAM AVEDISIAN |
| Smoke Detectors | 10/26/2020 | Approved | ARAM AVEDISIAN |
| Final | 11/2/2020 | OK to Issue CofO | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/2/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 11/2/2020 | Approved | ARAM AVEDISIAN |