10729 W ESTHER AVE 90064
Certificate Information: 10729 W ESTHER AVE 90064
- Application / Permit
- 19010-20000-04822
- Plan Check / Job No.
- B19VN18769
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 41' X 82'-4" (1) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT. CONTRACTOR M LIBRUSH CONSTRUCTION INC HOLDING B LICENSE # 933238 MUST PULL CONSTRUCTION PERMIT NO. 19010-20000-04822. THIS CONTRACTOR PULLED DEMO PERMIT # 20019-20000-00056.
- Permit Issued
- Issued on 7/14/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | SELLA BENYAMIN |
| Corrections Issued | 11/13/2019 | SELLA BENYAMIN |
| Quality Review Completed | 11/14/2019 | STEVEN KIM |
| Building Plans Picked Up | 11/18/2019 | APPLICANT |
| Green Plans Picked Up | 11/18/2019 | APPLICANT |
| Applicant returned to address corrections | 3/26/2020 | SELLA BENYAMIN |
| Plan Check Approved | 7/1/2020 | SELLA BENYAMIN |
| Issued | 7/14/2020 | APPLICANT |
| CofO in Progress | 3/10/2021 | KENNETH NAGLE |
| CofO in Progress | 3/11/2021 | OGANES TARAKHCHYAN |
| Permit Finaled | 3/12/2021 | KENNETH NAGLE |
| CofO Issued | 3/12/2021 | KENNETH NAGLE |
| Permit Finaled | 3/12/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Permit | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 12/5/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 12/17/2019 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 12/17/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 12/17/2019 | ANDRES COVARRUBIAS |
| Trees in Parkway | Cleared | 12/17/2019 | JOHN KIM |
| Roof/Waste drainage to street | Cleared | 12/19/2019 | APEKSHYA BAJRACHARYA |
| Flood clearance | Cleared | 3/11/2020 | BRYAN GATHUKA |
Contact Information
| Contractor | M D M Builders Group; Lic. No.: 933238-B | 541 SOUTH SPRING ST STE 213 LOS ANGELES, CA 90013 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 7/16/2020 | Not Ready for Inspection | JUSTIN CURTIS |
| Footing/Foundation/Slab | 7/16/2020 | Partial Approval | JUSTIN CURTIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/29/2020 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 7/29/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 7/30/2020 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/30/2020 | Partial Approval | KEVIN SARGSYAN |
| Insulation | 8/3/2020 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2020 | Partial Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 9/4/2020 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/4/2020 | Corrections Issued | KEVIN SARGSYAN |
| Wood Frame | 9/4/2020 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 9/9/2020 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 9/9/2020 | Approved | KEVIN SARGSYAN |
| Gas Test | 9/9/2020 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/9/2020 | Partial Approval | KEVIN SARGSYAN |
| HVAC-Rough | 9/10/2020 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 9/23/2020 | Approved | KEVIN SARGSYAN |
| Sewer | 9/25/2020 | Approved | KEVIN SARGSYAN |
| Shower Pan | 9/25/2020 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 10/2/2020 | Corrections Issued | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/2/2020 | Corrections Issued | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 10/7/2020 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 10/7/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 10/7/2020 | Partial Approval | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/7/2020 | Partial Approval | KEVIN SARGSYAN |
| Wood Frame | 10/7/2020 | Approved | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 10/28/2020 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 11/16/2020 | Approved | KEVIN SARGSYAN |
| Drywall Nailing | 11/16/2020 | Approved | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 11/16/2020 | Approved | KEVIN SARGSYAN |
| Insulation | 11/16/2020 | Approved | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 11/16/2020 | Approved | KEVIN SARGSYAN |
| Service/Power Release | 1/7/2021 | Not Ready for Inspection | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/8/2021 | Approved | KEVIN SARGSYAN |
| ELECTRICAL-Final | 1/19/2021 | Approved | EVAN COOPER |
| HVAC-Final | 1/19/2021 | Approved | EVAN COOPER |
| PLUMBING-Final | 1/19/2021 | Approved | EVAN COOPER |
| Pre-Gunite | 2/5/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Service/Power Release | 2/5/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Verify Rec and Parks Fee Memo | 2/5/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Service/Power Release | 2/17/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Special/Order Compliance | 2/17/2021 | Approved | RICHARD ROBLES |
| FLOOD-Elevation Certificate | 3/2/2021 | Approved | RICHARD ROBLES |
| Final | 3/2/2021 | Corrections Issued | RICHARD ROBLES |
| Footing/Foundation/Slab | 3/2/2021 | Approved | RICHARD ROBLES |
| Green Building Final | 3/2/2021 | Approved | RICHARD ROBLES |
| SGSOV-Seismic Gas S/O Valve | 3/2/2021 | SGSOV Approved | RICHARD ROBLES |
| Service/Power Release | 3/2/2021 | Not Ready for Inspection | RICHARD ROBLES |
| Smoke Detectors | 3/2/2021 | Approved | RICHARD ROBLES |
| Special/Order Compliance | 3/2/2021 | Approved | RICHARD ROBLES |
| Service/Power Release | 3/3/2021 | Approved | KENNETH NAGLE |
| Final | 3/4/2021 | Conditional Approval | KENNETH NAGLE |
| Final | 3/10/2021 | OK to Issue CofO | OGANES TARAKHCHYAN |