10729 W ESTHER AVE 90064

Certificate Information: 10729 W ESTHER AVE 90064

Application / Permit
19010-20000-04822
Plan Check / Job No.
B19VN18769
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 41' X 82'-4" (1) STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT. CONTRACTOR M LIBRUSH CONSTRUCTION INC HOLDING B LICENSE # 933238 MUST PULL CONSTRUCTION PERMIT NO. 19010-20000-04822. THIS CONTRACTOR PULLED DEMO PERMIT # 20019-20000-00056.
Permit Issued
Issued on 7/14/2020
Issuing Office
Metro
Current Status
CofO Issued on 3/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 SELLA BENYAMIN
Corrections Issued 11/13/2019 SELLA BENYAMIN
Quality Review Completed 11/14/2019 STEVEN KIM
Building Plans Picked Up 11/18/2019 APPLICANT
Green Plans Picked Up 11/18/2019 APPLICANT
Applicant returned to address corrections 3/26/2020 SELLA BENYAMIN
Plan Check Approved 7/1/2020 SELLA BENYAMIN
Issued 7/14/2020 APPLICANT
CofO in Progress 3/10/2021 KENNETH NAGLE
CofO in Progress 3/11/2021 OGANES TARAKHCHYAN
Permit Finaled 3/12/2021 KENNETH NAGLE
CofO Issued 3/12/2021 KENNETH NAGLE
Permit Finaled 3/12/2021 KENNETH NAGLE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/5/2019 ADRIAN CASTRO
Permit Cleared 12/5/2019 ADRIAN CASTRO
Sewer availability Cleared 12/5/2019 ADRIAN CASTRO
Green Code Cleared 12/17/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 12/17/2019 GEORGE SUCHAND
Low Impact Development Cleared 12/17/2019 ANDRES COVARRUBIAS
Trees in Parkway Cleared 12/17/2019 JOHN KIM
Roof/Waste drainage to street Cleared 12/19/2019 APEKSHYA BAJRACHARYA
Flood clearance Cleared 3/11/2020 BRYAN GATHUKA

Contact Information

Contractor M D M Builders Group; Lic. No.: 933238-B 541 SOUTH SPRING ST STE 213      LOS ANGELES, CA 90013

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 7/16/2020 Not Ready for Inspection JUSTIN CURTIS
Footing/Foundation/Slab 7/16/2020 Partial Approval JUSTIN CURTIS
Floor/Roof Diaphrgm/Shear Wall 7/29/2020 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 7/29/2020 Corrections Issued KEVIN SARGSYAN
Wood Frame 7/29/2020 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 7/30/2020 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 7/30/2020 Partial Approval KEVIN SARGSYAN
Insulation 8/3/2020 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/5/2020 Partial Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2020 Partial Approval KEVIN SARGSYAN
HVAC-Rough 9/4/2020 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 9/4/2020 Corrections Issued KEVIN SARGSYAN
Wood Frame 9/4/2020 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 9/9/2020 Approved KEVIN SARGSYAN
ELECTRICAL-Rough 9/9/2020 Approved KEVIN SARGSYAN
Gas Test 9/9/2020 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 9/9/2020 Partial Approval KEVIN SARGSYAN
HVAC-Rough 9/10/2020 Approved KEVIN SARGSYAN
PLUMBING-Rough 9/23/2020 Approved KEVIN SARGSYAN
Sewer 9/25/2020 Approved KEVIN SARGSYAN
Shower Pan 9/25/2020 Approved KEVIN SARGSYAN
Green Building Rough 10/2/2020 Corrections Issued KEVIN SARGSYAN
Interior/Exterior Lathing 10/2/2020 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 10/7/2020 Corrections Issued KEVIN SARGSYAN
Green Building Rough 10/7/2020 Approved KEVIN SARGSYAN
Insulation 10/7/2020 Partial Approval KEVIN SARGSYAN
Interior/Exterior Lathing 10/7/2020 Partial Approval KEVIN SARGSYAN
Wood Frame 10/7/2020 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 10/28/2020 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 11/16/2020 Approved KEVIN SARGSYAN
Drywall Nailing 11/16/2020 Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 11/16/2020 Approved KEVIN SARGSYAN
Insulation 11/16/2020 Approved KEVIN SARGSYAN
Verify Sprinkler Sign Off 11/16/2020 Approved KEVIN SARGSYAN
Service/Power Release 1/7/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 1/8/2021 Approved KEVIN SARGSYAN
ELECTRICAL-Final 1/19/2021 Approved EVAN COOPER
HVAC-Final 1/19/2021 Approved EVAN COOPER
PLUMBING-Final 1/19/2021 Approved EVAN COOPER
Pre-Gunite 2/5/2021 Not Ready for Inspection RICHARD ROBLES
Service/Power Release 2/5/2021 Not Ready for Inspection RICHARD ROBLES
Verify Rec and Parks Fee Memo 2/5/2021 Not Ready for Inspection RICHARD ROBLES
Service/Power Release 2/17/2021 Not Ready for Inspection RICHARD ROBLES
Special/Order Compliance 2/17/2021 Approved RICHARD ROBLES
FLOOD-Elevation Certificate 3/2/2021 Approved RICHARD ROBLES
Final 3/2/2021 Corrections Issued RICHARD ROBLES
Footing/Foundation/Slab 3/2/2021 Approved RICHARD ROBLES
Green Building Final 3/2/2021 Approved RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 3/2/2021 SGSOV Approved RICHARD ROBLES
Service/Power Release 3/2/2021 Not Ready for Inspection RICHARD ROBLES
Smoke Detectors 3/2/2021 Approved RICHARD ROBLES
Special/Order Compliance 3/2/2021 Approved RICHARD ROBLES
Service/Power Release 3/3/2021 Approved KENNETH NAGLE
Final 3/4/2021 Conditional Approval KENNETH NAGLE
Final 3/10/2021 OK to Issue CofO OGANES TARAKHCHYAN