13814 W HUBBARD ST 91342
Certificate Information: 13814 W HUBBARD ST 91342
- Application / Permit
- 19010-20000-04807
- Plan Check / Job No.
- B19VN18692
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40' X 30' IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER AB 494 & SB 229, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/4/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/29/2019 | APPLICANT |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | RARES BODEA |
| Corrections Issued | 11/11/2019 | RARES BODEA |
| Quality Review Completed | 11/13/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/14/2019 | APPLICANT |
| Plan Check Approved | 3/11/2020 | RARES BODEA |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 3/15/2022 | JOHN HAYES |
| CofO Issued | 6/4/2022 | MICHAEL SMITH |
| Permit Finaled | 6/4/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/2/2020 | MITESH PATEL |
| Address approval | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 3/9/2020 | MARKOS PEREZ-BRAN |
| Green Code | Cleared | 3/11/2020 | AARON COSTA |
| Hydrant and Access approval | Cleared | 3/11/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 4/17/2020 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 4/20/2020 | Partial Approval | TROY SANDERS |
| Footing/Foundation/Slab | 4/21/2020 | Approved | TROY SANDERS |
| PLUMBING-Rough | 4/21/2020 | Partial Approval | TROY SANDERS |
| BUILDING-Rough-Frame | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 6/11/2020 | Approved | PIERRE VEGA |
| Verify Sprinkler Sign Off | 6/11/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/12/2020 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2020 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 6/12/2020 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 6/12/2020 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/19/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/19/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 6/19/2020 | Partial Inspection | PIERRE VEGA |
| Verify Sprinkler Sign Off | 6/19/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/23/2020 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/23/2020 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/23/2020 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/23/2020 | Partial Approval | GREGG CUMMINGS |
| Special/Order Compliance | 6/23/2020 | Partial Inspection | PIERRE VEGA |
| Verify Sprinkler Sign Off | 6/23/2020 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 7/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 7/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| HVAC-Rough | 7/10/2020 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/18/2020 | Approved | MISAEL ESPARZA |
| HVAC-Rough | 8/18/2020 | Approved | MISAEL ESPARZA |
| Insulation | 8/18/2020 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 9/9/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 9/9/2020 | Partial Approval | MISAEL ESPARZA |
| PLUMBING-Rough | 9/18/2020 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 10/2/2020 | Partial Inspection | MISAEL ESPARZA |
| Shower Pan | 10/22/2020 | Approved | MISAEL ESPARZA |
| Sewer | 11/13/2020 | Corrections Issued | MISAEL ESPARZA |
| Sewer | 1/15/2021 | Conditional Approval | MISAEL ESPARZA |
| Gas Test | 3/19/2021 | Approved | MISAEL ESPARZA |
| Service/Power Release | 3/19/2021 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| Final | 2/9/2022 | Corrections Issued | JOHN HAYES |
| Green Building Final | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 2/9/2022 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| Verify Rec and Parks Fee Memo | 2/9/2022 | Not Ready for Inspection | JOHN HAYES |
| ELECTRICAL-Final | 3/9/2022 | Approved | MICHEL ABAJAN |
| Final | 3/9/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Green Building Final | 3/9/2022 | Approved | MICHEL ABAJAN |
| HVAC-Final | 3/9/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 3/9/2022 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 3/9/2022 | SGSOV Approved | MICHEL ABAJAN |
| Service/Power Release | 3/9/2022 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 3/9/2022 | Approved | MICHEL ABAJAN |
| Verify Rec and Parks Fee Memo | 3/9/2022 | Approved | MICHEL ABAJAN |
| Final | 3/14/2022 | OK to Issue CofO | JOHN HAYES |
| HVAC-Final | 3/14/2022 | Approved | JOHN HAYES |
| Service/Power Release | 3/14/2022 | Approved | JOHN HAYES |