13115 N DE GARMO AVE 91342

Certificate Information: 13115 N DE GARMO AVE 91342

Application / Permit
19010-20000-04806
Plan Check / Job No.
B19VN18691
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 30' X 40' IRREGULAR SHAPED ACCESSORY DWELLING UNIT PER AB 494 & SB 229, ALL WORK PER ENGINEERING
Permit Issued
Issued on 3/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2019 APPLICANT
Green Plans Picked Up 11/4/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 RARES BODEA
Corrections Issued 11/11/2019 RARES BODEA
Quality Review Completed 11/13/2019 GUANG MIN TUNG
Building Plans Picked Up 11/14/2019 APPLICANT
Plan Check Approved 3/11/2020 RARES BODEA
Issued 3/16/2020 LADBS
CofO in Progress 8/12/2021 MISAEL ESPARZA
CofO Issued 9/9/2021 MICHAEL SMITH
Permit Finaled 9/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 3/2/2020 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 3/2/2020 GUILLERMO PETRA
Low Impact Development Cleared 3/2/2020 MITESH PATEL
Sewer availability Cleared 3/2/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 3/9/2020 MARKOS PEREZ-BRAN
Green Code Cleared 3/11/2020 AARON COSTA
Hydrant and Access approval Cleared 3/11/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Wassef,, Mena Maher Salama; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/8/2020 Partial Approval TROY SANDERS
ELECTRICAL-Rough 4/17/2020 Partial Approval TROY SANDERS
Footing/Foundation/Slab 4/17/2020 Approved TROY SANDERS
ELECTRICAL-Rough 6/22/2020 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval GREGG CUMMINGS
Green Building Rough 6/22/2020 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 6/22/2020 Not Ready for Inspection GREGG CUMMINGS
Verify Sprinkler Sign Off 6/22/2020 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 6/23/2020 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 6/23/2020 Approved GREGG CUMMINGS
Special/Order Compliance 6/23/2020 Partial Inspection PIERRE VEGA
BUILDING-Rough-Frame 7/13/2020 Partial Approval GREGG CUMMINGS
Green Building Rough 7/13/2020 Not Ready for Inspection GREGG CUMMINGS
HVAC-Rough 7/13/2020 Corrections Issued GREGG CUMMINGS
Verify Sprinkler Sign Off 7/13/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 8/5/2020 Corrections Issued MISAEL ESPARZA
Green Building Rough 8/5/2020 Not Ready for Inspection MISAEL ESPARZA
HVAC-Rough 8/5/2020 Approved MISAEL ESPARZA
Wood Frame 8/5/2020 Not Ready for Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 8/17/2020 Partial Approval MISAEL ESPARZA
Green Building Rough 8/17/2020 Approved MISAEL ESPARZA
Insulation 8/25/2020 Corrections Issued MISAEL ESPARZA
Insulation 9/3/2020 Conditional Approval MISAEL ESPARZA
Drywall Nailing 9/18/2020 Approved MISAEL ESPARZA
PLUMBING-Rough 9/18/2020 Corrections Issued MISAEL ESPARZA
Interior/Exterior Lathing 9/24/2020 Partial Approval MISAEL ESPARZA
Shower Pan 10/2/2020 No Access for Inspection MISAEL ESPARZA
Shower Pan 10/23/2020 Approved MISAEL ESPARZA
Gas Test 3/25/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 4/27/2021 Not Ready for Inspection STEVEN BACK
HVAC-Final 4/27/2021 Corrections Issued STEVEN BACK
PLUMBING-Final 4/27/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 5/4/2021 Approved MISAEL ESPARZA
Final 5/4/2021 Not Ready for Inspection MISAEL ESPARZA
Green Building Final 5/4/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 5/4/2021 SGSOV Not Ready MISAEL ESPARZA
Service/Power Release 5/4/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 5/4/2021 Corrections Issued MISAEL ESPARZA
ELECTRICAL-Final 8/9/2021 Approved MISAEL ESPARZA
Final 8/9/2021 Not Ready for Inspection MISAEL ESPARZA
HVAC-Final 8/9/2021 Corrections Issued MISAEL ESPARZA
PLUMBING-Final 8/9/2021 Approved MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 8/9/2021 SGSOV Approved MISAEL ESPARZA
Service/Power Release 8/9/2021 Not Ready for Inspection MISAEL ESPARZA
Smoke Detectors 8/9/2021 Approved MISAEL ESPARZA
ELECTRICAL-Final 8/12/2021 Approved MISAEL ESPARZA
Final 8/12/2021 OK to Issue CofO MISAEL ESPARZA
HVAC-Final 8/12/2021 Approved MISAEL ESPARZA
PLUMBING-Final 8/12/2021 Approved MISAEL ESPARZA
Service/Power Release 8/12/2021 Approved MISAEL ESPARZA