4644 N WHITSETT AVE 91604

Certificate Information: 4644 N WHITSETT AVE 91604

Application / Permit
19010-20000-04762
Plan Check / Job No.
B19VN18454
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 3/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 5/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2019 APPLICANT
Assigned to Plan Check Engineer 11/21/2019 ABDUL CHEGENI
Green Plans Picked Up 11/22/2019 APPLICANT
Corrections Issued 12/3/2019 ABDUL CHEGENI
Quality Review Completed 12/5/2019 STEVEN KIM
Building Plans Picked Up 12/6/2019 APPLICANT
Plan Check Approved 3/12/2020 ABDUL CHEGENI
Issued 3/17/2020 LADBS
CofO in Progress 2/22/2022 ARAM AVEDISIAN
Permit Finaled 5/11/2022 MICHAEL SMITH
CofO Issued 5/11/2022 MICHAEL SMITH
Permit Finaled 5/11/2022 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/12/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/18/2019 APEKSHYA BAJRACHARYA
Highway dedication Cleared 12/18/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/18/2019 APEKSHYA BAJRACHARYA
ZI Cleared 12/27/2019 STEVEN WECHSLER
Green Code Cleared 2/13/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 2/13/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/20/2020 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 3/6/2020 RIDWAN HARDY
Construction within easement Cleared 3/6/2020 RIDWAN HARDY
Roof/Waste drainage to street Cleared 3/12/2020 JOHN LIN

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2020 Partial Approval ARAM AVEDISIAN
Sewer 11/18/2020 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 11/20/2020 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 11/20/2020 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 11/25/2020 Corrections Issued ARAM AVEDISIAN
Underground Mechanical 11/25/2020 Partial Approval ARAM AVEDISIAN
Footing/Foundation/Slab 12/7/2020 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 12/8/2020 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/16/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Approval ARAM AVEDISIAN
Green Building Rough 1/11/2021 Not Ready for Inspection ARAM AVEDISIAN
MERV13>=Rough 1/11/2021 Not Ready for Inspection ARAM AVEDISIAN
Verify Sprinkler Sign Off 1/11/2021 Not Ready for Inspection ARAM AVEDISIAN
ELECTRICAL-Rough 2/24/2021 Approved ARAM AVEDISIAN
PLUMBING-Rough 2/24/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 3/4/2021 Partial Approval ARAM AVEDISIAN
Green Building Rough 3/4/2021 Conditional Approval ARAM AVEDISIAN
HVAC-Rough 3/4/2021 Approved ARAM AVEDISIAN
MERV13>=Rough 3/4/2021 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 3/4/2021 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 3/12/2021 Approved MATTHEW NELSON
Masonry Wall/Backfill 3/12/2021 Not Ready for Inspection MATTHEW NELSON
Insulation 4/8/2021 Approved LILIANA PORTILLO
Drywall Nailing 4/29/2021 Approved DANIEL ORRANTE
Green Building Rough 4/29/2021 Approved DANIEL ORRANTE
Underground Mechanical 9/21/2021 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Final 11/10/2021 Not Ready for Inspection ARAM AVEDISIAN
Service/Power Release 1/25/2022 Partial Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 2/1/2022 Approved ARAM AVEDISIAN
Final 2/1/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 2/1/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/1/2022 SGSOV Not Ready ARAM AVEDISIAN
Smoke Detectors 2/1/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Final 2/18/2022 Approved ARAM AVEDISIAN
Final 2/18/2022 Corrections Issued ARAM AVEDISIAN
HVAC-Final 2/18/2022 Approved ARAM AVEDISIAN
MERV13>=Final 2/18/2022 Approved ARAM AVEDISIAN
PLUMBING-Final 2/18/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved ARAM AVEDISIAN
Final 2/22/2022 OK to Issue CofO ARAM AVEDISIAN
Service/Power Release 2/22/2022 Approved ARAM AVEDISIAN