4644 N WHITSETT AVE 91604
Certificate Information: 4644 N WHITSETT AVE 91604
- Application / Permit
- 19010-20000-04762
- Plan Check / Job No.
- B19VN18454
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
- Permit Issued
- Issued on 3/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/11/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2019 | ABDUL CHEGENI |
| Green Plans Picked Up | 11/22/2019 | APPLICANT |
| Corrections Issued | 12/3/2019 | ABDUL CHEGENI |
| Quality Review Completed | 12/5/2019 | STEVEN KIM |
| Building Plans Picked Up | 12/6/2019 | APPLICANT |
| Plan Check Approved | 3/12/2020 | ABDUL CHEGENI |
| Issued | 3/17/2020 | LADBS |
| CofO in Progress | 2/22/2022 | ARAM AVEDISIAN |
| Permit Finaled | 5/11/2022 | MICHAEL SMITH |
| CofO Issued | 5/11/2022 | MICHAEL SMITH |
| Permit Finaled | 5/11/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/18/2019 | APEKSHYA BAJRACHARYA |
| Highway dedication | Cleared | 12/18/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 12/18/2019 | APEKSHYA BAJRACHARYA |
| ZI | Cleared | 12/27/2019 | STEVEN WECHSLER |
| Green Code | Cleared | 2/13/2020 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 2/13/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/20/2020 | ORVAL HERNANDEZ-MARCI |
| Construction near power lines | Cleared | 3/6/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/6/2020 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 3/12/2020 | JOHN LIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 14545 VICTORY BLVD 405 VAN NUYS, CA 91411 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/18/2020 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 11/18/2020 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 11/20/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/20/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/25/2020 | Corrections Issued | ARAM AVEDISIAN |
| Underground Mechanical | 11/25/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/7/2020 | Corrections Issued | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 12/8/2020 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/11/2021 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 1/11/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| MERV13>=Rough | 1/11/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 1/11/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 2/24/2021 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/24/2021 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 3/4/2021 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 3/4/2021 | Conditional Approval | ARAM AVEDISIAN |
| HVAC-Rough | 3/4/2021 | Approved | ARAM AVEDISIAN |
| MERV13>=Rough | 3/4/2021 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 3/4/2021 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 3/12/2021 | Approved | MATTHEW NELSON |
| Masonry Wall/Backfill | 3/12/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Insulation | 4/8/2021 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 4/29/2021 | Approved | DANIEL ORRANTE |
| Green Building Rough | 4/29/2021 | Approved | DANIEL ORRANTE |
| Underground Mechanical | 9/21/2021 | Partial Approval | ARAM AVEDISIAN |
| ELECTRICAL-Final | 11/10/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Service/Power Release | 1/25/2022 | Partial Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 2/1/2022 | Approved | ARAM AVEDISIAN |
| Final | 2/1/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 2/1/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2022 | SGSOV Not Ready | ARAM AVEDISIAN |
| Smoke Detectors | 2/1/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/18/2022 | Approved | ARAM AVEDISIAN |
| Final | 2/18/2022 | Corrections Issued | ARAM AVEDISIAN |
| HVAC-Final | 2/18/2022 | Approved | ARAM AVEDISIAN |
| MERV13>=Final | 2/18/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Final | 2/18/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 2/18/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Final | 2/22/2022 | OK to Issue CofO | ARAM AVEDISIAN |
| Service/Power Release | 2/22/2022 | Approved | ARAM AVEDISIAN |