12881 W PAXTON ST 91331

Certificate Information: 12881 W PAXTON ST 91331

Application / Permit
19010-20000-04747
Plan Check / Job No.
B19VN18357
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
32' x 37' ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 3/31/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/16/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 CHON CHIO KUO
Corrections Issued 11/4/2019 CHON CHIO KUO
Quality Review Completed 11/5/2019 GUANG MIN TUNG
Building Plans Picked Up 11/5/2019 APPLICANT
Green Plans Picked Up 11/18/2019 APPLICANT
Applicant returned to address corrections 2/6/2020 CHON CHIO KUO
Applicant returned to address corrections 3/23/2020 CHON CHIO KUO
Plan Check Approved 3/24/2020 CHON CHIO KUO
Issued 3/31/2020 LADBS
CofO in Progress 8/31/2020 MICHEL ABAJAN
No Progress 9/2/2020 MICHEL ABAJAN
CofO in Progress 10/5/2020 MICHEL ABAJAN
CofO Issued 10/16/2020 MICHAEL SMITH
Permit Finaled 10/16/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/25/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 12/20/2019 LEE GUILBEAUX
Sewer availability Cleared 12/20/2019 LEE GUILBEAUX
Green Code Cleared 1/13/2020 MICHAEL AYERS
Hydrant and Access approval Cleared 1/13/2020 GEORGE SUCHAND
Clean Up Green Up Cleared 2/4/2020 VINCENT QUITORIANO
Low Impact Development Cleared 2/4/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/4/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/15/2020 Partial Approval MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 4/23/2020 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/23/2020 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/11/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/11/2020 Partial Approval MICHEL ABAJAN
Gas Test 5/11/2020 Partial Approval MICHEL ABAJAN
HVAC-Rough 5/11/2020 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 5/11/2020 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 5/15/2020 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 5/15/2020 Approved MICHEL ABAJAN
Green Building Rough 5/15/2020 Approved MICHEL ABAJAN
HVAC-Rough 5/15/2020 Approved MICHEL ABAJAN
Interior/Exterior Lathing 5/15/2020 Approved MICHEL ABAJAN
MERV13>=Rough 5/15/2020 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 5/15/2020 Approved MICHEL ABAJAN
Insulation 5/22/2020 Approved MICHEL ABAJAN
Drywall Nailing 6/2/2020 Approved MICHEL ABAJAN
ELECTRICAL-Final 7/2/2020 Approved MICHEL ABAJAN
Final 7/2/2020 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 7/2/2020 Approved MICHEL ABAJAN
HVAC-Final 7/2/2020 Approved MICHEL ABAJAN
MERV13>=Final 7/2/2020 Approved MICHEL ABAJAN
PLUMBING-Final 7/2/2020 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 7/2/2020 SGSOV Approved MICHEL ABAJAN
Service/Power Release 7/2/2020 Approved MICHEL ABAJAN
Smoke Detectors 7/2/2020 Approved MICHEL ABAJAN
Final 7/23/2020 Corrections Issued MICHEL ABAJAN
Final 8/18/2020 Not Ready for Inspection MICHEL ABAJAN
Final 8/31/2020 OK to Issue CofO MICHEL ABAJAN
Final 9/3/2020 Corrections Issued MICHEL ABAJAN
Final 10/5/2020 OK to Issue CofO MICHEL ABAJAN