5351 N DONNA AVE 91356

Certificate Information: 5351 N DONNA AVE 91356

Application / Permit
19010-20000-04725
Plan Check / Job No.
B19VN18272
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Recreation Room
Work Description
NEW 12'-6" X 18' REC ROOM WITH HALF BATHROOM
Permit Issued
Issued on 1/31/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/21/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 SELLA BENYAMIN
Green Plans Picked Up 11/6/2019 APPLICANT
Corrections Issued 11/15/2019 SELLA BENYAMIN
Quality Review Completed 11/15/2019 STEVEN KIM
Building Plans Picked Up 11/18/2019 APPLICANT
Plan Check Approved 1/30/2020 SELLA BENYAMIN
Issued 1/31/2020 LADBS
CofO in Progress 11/20/2020 DAVID SANDOVAL
Permit Finaled 11/21/2020 MICHAEL SMITH
CofO Issued 11/21/2020 MICHAEL SMITH
Permit Finaled 11/21/2020 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/14/2020 GABRIEL ROBLES
Low Impact Development Cleared 1/14/2020 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 1/14/2020 GABRIEL ROBLES
Miscellaneous Cleared 1/15/2020 STEVEN WECHSLER
Green Code Cleared 1/17/2020 MICHAEL AYERS

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/6/2020 Partial Approval DAVID SANDOVAL
Underground Mechanical 3/6/2020 Partial Approval DAVID SANDOVAL
Deputy Reinf. Concrete 3/9/2020 Approved DAVID SANDOVAL
Footing/Foundation/Slab 4/3/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Not Ready for Inspection DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval DAVID SANDOVAL
Gas Test 6/12/2020 Approved DAVID SANDOVAL
HVAC-Rough 6/12/2020 Approved DAVID SANDOVAL
PLUMBING-Rough 6/12/2020 Approved DAVID SANDOVAL
ELECTRICAL-Rough 6/15/2020 Approved DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Approved DAVID SANDOVAL
BUILDING-Rough-Frame 6/23/2020 Approved DAVID SANDOVAL
Green Building Rough 6/23/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 6/23/2020 Partial Approval DAVID SANDOVAL
Verify Sprinkler Sign Off 6/23/2020 Approved DAVID SANDOVAL
Interior/Exterior Lathing 6/30/2020 Not Ready for Inspection HENRY KIM
Drywall Nailing 7/8/2020 Approved DAVID SANDOVAL
Insulation 7/8/2020 Approved DAVID SANDOVAL
ELECTRICAL-Final 10/7/2020 Approved DAVID SANDOVAL
HVAC-Final 10/7/2020 Approved DAVID SANDOVAL
PLUMBING-Final 10/7/2020 Approved DAVID SANDOVAL
Final 10/30/2020 Corrections Issued DAVID SANDOVAL
Green Building Final 10/30/2020 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 10/30/2020 SGSOV Approved DAVID SANDOVAL
Service/Power Release 10/30/2020 Approved DAVID SANDOVAL
Smoke Detectors 10/30/2020 Approved DAVID SANDOVAL
Final 11/20/2020 OK to Issue CofO DAVID SANDOVAL