1413 W OAK GROVE DR 90041
Certificate Information: 1413 W OAK GROVE DR 90041
- Application / Permit
- 19010-20000-04648
- Plan Check / Job No.
- B19VN18012
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSE 30'X40'ONE STORY ADU PER AB 494 AND SB 229
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/16/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Green Plans Picked Up | 10/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | DAWN MC NULTY |
| Corrections Issued | 11/6/2019 | DAWN MC NULTY |
| Quality Review Completed | 11/6/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Applicant returned to address corrections | 1/2/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 1/17/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/5/2020 | DAWN MC NULTY |
| Applicant returned to address corrections | 2/14/2020 | DAWN MC NULTY |
| Plan Check Approved | 2/28/2020 | DAWN MC NULTY |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 3/11/2022 | CRAIG VAUGHAN |
| Permit Finaled | 3/16/2022 | DEROLD HAUFF |
| Permit Finaled | 3/16/2022 | DEROLD HAUFF |
| CofO Issued | 3/16/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 11/6/2019 | AARON COSTA |
| Address approval | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 11/7/2019 | GEORGE SUCHAND |
| Permit | Cleared | 11/7/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/7/2019 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 1/2/2020 | DAWN MC NULTY |
| Grading Pre-Inspection | Cleared | 1/2/2020 | DAWN MC NULTY |
| Low Impact Development | Cleared | 2/10/2020 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 2/11/2020 | APEKSHYA BAJRACHARYA |
| Trees in Parkway | Cleared | 2/27/2020 | JOHN KIM |
Contact Information
| Contractor | Moraga Builders And Design; Lic. No.: 567115-B | 8436 BARDWELL AVENUE PANORAMA, CA 91402 |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 839 S MUIRFIELD RD LOS ANGELES, CA 90005 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2021 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/13/2021 | Approved | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/27/2021 | Partial Approval | COREY HUPP |
| BUILDING-Rough-Frame | 7/12/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/12/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Rough | 7/12/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/12/2021 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/12/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/12/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 7/12/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/10/2021 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 8/10/2021 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 8/10/2021 | Approved | CRAIG VAUGHAN |
| Wood Frame | 8/10/2021 | Corrections Issued | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/27/2021 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 8/27/2021 | Approved | CRAIG VAUGHAN |
| Insulation | 8/27/2021 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 9/9/2021 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/9/2021 | Partial Approval | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 9/30/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 9/30/2021 | Conditional Approval | HAMIK HARTOUNIAN |
| Final | 12/6/2021 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 12/6/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/6/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 12/6/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 12/6/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 12/22/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Gas Test | 1/25/2022 | Partial Approval | CRAIG VAUGHAN |
| Final | 1/31/2022 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/31/2022 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 1/31/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Smoke Detectors | 1/31/2022 | Approved | CRAIG VAUGHAN |
| Final | 2/7/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 2/7/2022 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 2/7/2022 | Corrections Issued | CRAIG VAUGHAN |
| Final | 2/14/2022 | Corrections Issued | CRAIG VAUGHAN |
| Service/Power Release | 2/14/2022 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Final | 3/10/2022 | Approved | CRAIG VAUGHAN |
| Final | 3/10/2022 | OK to Issue CofO | CRAIG VAUGHAN |
| HVAC-Final | 3/10/2022 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 3/10/2022 | Approved | CRAIG VAUGHAN |