62 N BEVERLY PARK 90210
Certificate Information: 62 N BEVERLY PARK 90210
- Application / Permit
- 19010-20000-04640
- Plan Check / Job No.
- B19VN17969
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- (N) 2-STORY ACCESSORY LIVING QUARTERS OVER BASEMENT STORAGE & EQUIPMENT ROOM (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 3/25/2021
- Issuing Office
- Current Status
- CofO Issued on 7/7/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/4/2019 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 11/4/2019 | APPLICANT |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Applicant returned to address corrections | 11/19/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 12/10/2019 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/8/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/23/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/19/2020 | NILOOFAR MEHRAIN |
| Issued | 3/25/2021 | APPLICANT |
| CofO in Progress | 6/26/2025 | SEAN HAUPT |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
| CofO Issued | 7/7/2025 | RICHARD STEINBACH |
| Permit Finaled | 7/7/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/14/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/14/2019 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 11/14/2019 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | DINAH GARIN |
| Hydrant and Access approval | Cleared | 11/14/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | DINAH GARIN |
| Sewer availability | Cleared | 11/14/2019 | DINAH GARIN |
| Miscellaneous | Cleared | 12/18/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/18/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/18/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/18/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 12/18/2019 | SARAH GOLDMAN |
| Specific Plan | Cleared | 12/18/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 12/18/2019 | SARAH GOLDMAN |
| ZI | Cleared | 12/18/2019 | SARAH GOLDMAN |
| Excavation more than 5-ft deep | Cleared | 1/8/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/8/2020 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 1/8/2020 | NILOOFAR MEHRAIN |
| Green Code | Cleared | 1/15/2020 | DAVID MATSON |
| Low Impact Development | Cleared | 2/21/2020 | SARAH YOUSSEF |
Contact Information
| Contractor | James Roman Design Build Inc; Lic. No.: 953964-B | 8383 WILSHIRE BLVD 8TH FLOOR BEVERLY HILLS, CA 90211 |
| Engineer | Fischer, Kurt Mark; Lic. No.: S5432 | PO BOX 809 POWAY, CA 92074 |
| Engineer | Salehipour, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Salehipour, Sassan Abolghasem; Lic. No.: C44172 | 1290 NORTH LAKE AVENUE STE 204 PASADENA, CA 91104 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2021 | Partial Approval | ANTHONY MCDOWALL |
| Pre-Inspection | 5/3/2021 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/6/2021 | Partial Approval | ANTHONY MCDOWALL |
| Pre-Inspection | 5/6/2021 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Other (see comments) | 5/10/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 5/11/2021 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/12/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/12/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Deputy Grading | 5/13/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Other (see comments) | 5/13/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/13/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/14/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/14/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/17/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/17/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/18/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/19/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/19/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/21/2021 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 5/21/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Grading | 5/24/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/24/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/25/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/25/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/26/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/27/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Grading | 5/28/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 5/28/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Grading | 6/1/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Grading | 6/8/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Other (see comments) | 6/8/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Grading | 6/9/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 6/9/2021 | Partial Approval | ANTHONY MCDOWALL |
| FLOOD-Elevation Certificate | 6/15/2021 | Approved | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 6/15/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 7/8/2021 | Partial Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 7/14/2021 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Other (see comments) | 7/27/2021 | Conditional Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 7/28/2021 | Partial Approval | ANTHONY MCDOWALL |
| Piling/Pier/Caisson | 7/29/2021 | Partial Approval | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 8/6/2021 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 8/6/2021 | Partial Approval | JOHNNY MIRANDA |
| Deputy Other (see comments) | 8/20/2021 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 8/23/2021 | Partial Approval | MATT KELLERMAN |
| Grading Pre-Inspection | 9/17/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 9/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 9/29/2021 | Partial Approval | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 11/8/2021 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 12/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 12/6/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Masonry Wall/Backfill | 12/7/2021 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Piling/Pier/Caisson | 2/9/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 3/2/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/6/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 4/6/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 4/8/2022 | Partial Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/12/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Excavation/Setback/Form/Re-Bar | 5/4/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 5/4/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Deputy Reinf. Concrete | 5/10/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Grading Pre-Inspection | 5/17/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/8/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 6/15/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 6/17/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 6/29/2022 | Partial Approval | BRENDAN LOONEY |
| Footing/Foundation/Slab | 7/18/2022 | Partial Approval | BRENDAN LOONEY |
| Deputy Steel/Welding | 7/26/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| Deputy Steel/Welding | 7/27/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| FLOOD-Proofing Certificate | 8/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Structural Steel Frame | 8/12/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 9/29/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Underground Mechanical | 10/4/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 12/5/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Pre-Inspection | 12/14/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2022 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Wood Frame | 2/7/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 5/2/2023 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Rough | 5/19/2023 | Partial Approval | BRENDAN LOONEY |
| PLUMBING-Rough | 5/26/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 5/30/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 6/21/2023 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 7/24/2023 | Partial Approval | BRENDAN LOONEY |
| Interior/Exterior Lathing | 8/9/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 8/15/2023 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 8/21/2023 | Partial Approval | BRENDAN LOONEY |
| Drywall Nailing | 9/6/2023 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 9/6/2023 | Partial Approval | BRENDAN LOONEY |
| Verify Sprinkler Sign Off | 9/11/2023 | Approved | BRENDAN LOONEY |
| Pre-Inspection | 3/11/2024 | Approved | SEAN HAUPT |
| Special/Order Compliance | 3/11/2024 | Approved | SEAN HAUPT |
| Interior/Exterior Lathing | 4/8/2024 | Approved | SEAN HAUPT |
| Insulation | 6/20/2024 | Approved | SEAN HAUPT |
| ELECTRICAL-Final | 8/21/2024 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Final | 9/11/2024 | Not Ready for Inspection | SEAN HAUPT |
| ELECTRICAL-Final | 9/12/2024 | Approved | SEAN HAUPT |
| HVAC-Final | 3/28/2025 | Corrections Issued | SEAN HAUPT |
| PLUMBING-Final | 3/28/2025 | Corrections Issued | SEAN HAUPT |
| ELECTRICAL-Final | 4/22/2025 | Approved | SEAN HAUPT |
| PLUMBING-Final | 4/22/2025 | Approved | SEAN HAUPT |
| HVAC-Final | 5/21/2025 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 6/16/2025 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 6/16/2025 | Approved | SEAN HAUPT |
| Green Building Final | 6/16/2025 | Approved | SEAN HAUPT |
| Green Building Rough | 6/16/2025 | Approved | SEAN HAUPT |
| SGSOV-Seismic Gas S/O Valve | 6/16/2025 | SGSOV Approved | SEAN HAUPT |
| Service/Power Release | 6/16/2025 | Approved | SEAN HAUPT |
| Smoke Detectors | 6/16/2025 | Approved | SEAN HAUPT |
| Structural Steel Frame | 6/16/2025 | Approved | SEAN HAUPT |
| Final | 6/25/2025 | OK to Issue CofO | SEAN HAUPT |