18619 W VICTORY BLVD 91335
Certificate Information: 18619 W VICTORY BLVD 91335
- Application / Permit
- 19010-20000-04636
- Plan Check / Job No.
- B19VN17963
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 40'0"X26'0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT WITH 4'0"X6'0" ATTACHED PATIO PER AB 494 AND SB 229. ALL WORK PER WFPP
- Permit Issued
- Issued on 2/4/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 11/7/2019 | MARVEL DELACRUZ |
| Corrections Issued | 11/8/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 11/12/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/15/2019 | APPLICANT |
| Green Plans Picked Up | 11/15/2019 | APPLICANT |
| Applicant returned to address corrections | 2/3/2020 | MARVEL DELACRUZ |
| Plan Check Approved | 2/4/2020 | MARVEL DELACRUZ |
| Issued | 2/4/2020 | LADBS |
| CofO in Progress | 3/11/2021 | STEVEN BACK |
| CofO Issued | 3/12/2021 | RONALD MYRICK |
| Permit Finaled | 3/12/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2019 | GUILLERMO PETRA |
| Permit | Cleared | 12/12/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 12/12/2019 | GUILLERMO PETRA |
| ZI | Cleared | 12/27/2019 | STEVEN WECHSLER |
| Green Code | Cleared | 1/23/2020 | MARVEL DELACRUZ |
| Hydrant and Access approval | Cleared | 1/28/2020 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/3/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 2/3/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/2/2020 | Partial Approval | STEVEN BACK |
| Sewer | 4/2/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 4/10/2020 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 4/14/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Approved | STEVEN BACK |
| Underground Mechanical | 4/24/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/18/2020 | Not Ready for Inspection | STEVEN BACK |
| ELECTRICAL-Rough | 5/18/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2020 | Approved | STEVEN BACK |
| Green Building Rough | 5/18/2020 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 5/18/2020 | Approved | STEVEN BACK |
| PLUMBING-Rough | 5/18/2020 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 5/18/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 5/28/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 5/28/2020 | Approved | STEVEN BACK |
| Green Building Rough | 5/28/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 5/28/2020 | Partial Approval | STEVEN BACK |
| Insulation | 6/9/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/9/2020 | Partial Approval | STEVEN BACK |
| Drywall Nailing | 6/15/2020 | Approved | STEVEN BACK |
| Final | 12/9/2020 | Corrections Issued | STEVEN BACK |
| Footing/Foundation/Slab | 12/9/2020 | Approved | STEVEN BACK |
| Green Building Final | 12/9/2020 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 12/9/2020 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 12/9/2020 | Approved | STEVEN BACK |
| Final | 3/11/2021 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 3/11/2021 | Approved | STEVEN BACK |