18619 W VICTORY BLVD 91335

Certificate Information: 18619 W VICTORY BLVD 91335

Application / Permit
19010-20000-04636
Plan Check / Job No.
B19VN17963
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 40'0"X26'0" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT WITH 4'0"X6'0" ATTACHED PATIO PER AB 494 AND SB 229. ALL WORK PER WFPP
Permit Issued
Issued on 2/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 MARVEL DELACRUZ
Corrections Issued 11/8/2019 MARVEL DELACRUZ
Quality Review Completed 11/12/2019 GUANG MIN TUNG
Building Plans Picked Up 11/15/2019 APPLICANT
Green Plans Picked Up 11/15/2019 APPLICANT
Applicant returned to address corrections 2/3/2020 MARVEL DELACRUZ
Plan Check Approved 2/4/2020 MARVEL DELACRUZ
Issued 2/4/2020 LADBS
CofO in Progress 3/11/2021 STEVEN BACK
CofO Issued 3/12/2021 RONALD MYRICK
Permit Finaled 3/12/2021 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/12/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 12/12/2019 GUILLERMO PETRA
Permit Cleared 12/12/2019 GUILLERMO PETRA
Sewer availability Cleared 12/12/2019 GUILLERMO PETRA
ZI Cleared 12/27/2019 STEVEN WECHSLER
Green Code Cleared 1/23/2020 MARVEL DELACRUZ
Hydrant and Access approval Cleared 1/28/2020 GEORGE SUCHAND
Low Impact Development Cleared 2/3/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/3/2020 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/2/2020 Partial Approval STEVEN BACK
Sewer 4/2/2020 Approved STEVEN BACK
Footing/Foundation/Slab 4/10/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 4/14/2020 Partial Approval STEVEN BACK
Excavation/Setback/Form/Re-Bar 4/21/2020 Approved STEVEN BACK
Underground Mechanical 4/24/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 5/18/2020 Not Ready for Inspection STEVEN BACK
ELECTRICAL-Rough 5/18/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/18/2020 Approved STEVEN BACK
Green Building Rough 5/18/2020 Not Ready for Inspection STEVEN BACK
HVAC-Rough 5/18/2020 Approved STEVEN BACK
PLUMBING-Rough 5/18/2020 Approved STEVEN BACK
Verify Sprinkler Sign Off 5/18/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 5/28/2020 Approved STEVEN BACK
ELECTRICAL-Rough 5/28/2020 Approved STEVEN BACK
Green Building Rough 5/28/2020 Approved STEVEN BACK
Interior/Exterior Lathing 5/28/2020 Partial Approval STEVEN BACK
Insulation 6/9/2020 Approved STEVEN BACK
Interior/Exterior Lathing 6/9/2020 Partial Approval STEVEN BACK
Drywall Nailing 6/15/2020 Approved STEVEN BACK
Final 12/9/2020 Corrections Issued STEVEN BACK
Footing/Foundation/Slab 12/9/2020 Approved STEVEN BACK
Green Building Final 12/9/2020 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 12/9/2020 SGSOV Approved STEVEN BACK
Service/Power Release 12/9/2020 Not Ready for Inspection STEVEN BACK
Smoke Detectors 12/9/2020 Approved STEVEN BACK
Final 3/11/2021 OK to Issue CofO STEVEN BACK
Service/Power Release 3/11/2021 Approved STEVEN BACK