867 N HARTZELL ST 90272
Certificate Information: 867 N HARTZELL ST 90272
- Application / Permit
- 19010-20000-04626
- Plan Check / Job No.
- B19VN17910
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 77'0"X30'0" 2-STORY SFD WITH ATTACHED 2-CAR GARAGE. NFPA 13 D FIRE SPRINKLERS REQ'D THROUGHOUT
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | MARVEL DELACRUZ |
| Green Plans Picked Up | 11/1/2019 | APPLICANT |
| Corrections Issued | 11/2/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/6/2019 | APPLICANT |
| Applicant returned to address corrections | 12/26/2019 | MARVEL DELACRUZ |
| Plan Check Approved | 1/15/2020 | MARVEL DELACRUZ |
| Issued | 1/23/2020 | LADBS |
| CofO in Progress | 12/18/2020 | CHRIS CHRISTENSEN |
| CofO Issued | 3/17/2021 | VINCENT COTTON |
| Permit Finaled | 3/17/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 12/16/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/16/2019 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 12/16/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 12/16/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 12/17/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 12/17/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/17/2019 | GUILLERMO PETRA |
| GPI Written Notices | Cleared | 12/26/2019 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 12/26/2019 | MARVEL DELACRUZ |
Contact Information
| Contractor | Sun Developers Inc; Lic. No.: 865631-B | 23371 MULHOLLAND DRIVE #295 WOODLAND HILLS, CA 91364 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/7/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 2/18/2020 | Approved | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2020 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2020 | Partial Approval | DANNY TOLENTINO |
| Green Building Rough | 4/13/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| ELECTRICAL-Rough | 4/28/2020 | Not Ready for Inspection | DANNY TOLENTINO |
| HVAC-Rough | 4/28/2020 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 4/28/2020 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2020 | Partial Approval | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 5/14/2020 | Corrections Issued | DANNY TOLENTINO |
| ELECTRICAL-Rough | 5/14/2020 | Partial Approval | DANNY TOLENTINO |
| HVAC-Rough | 5/14/2020 | Approved | DANNY TOLENTINO |
| Interior/Exterior Lathing | 5/14/2020 | Partial Approval | DANNY TOLENTINO |
| PLUMBING-Rough | 5/14/2020 | Approved | DANNY TOLENTINO |
| Shower Pan | 5/14/2020 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 5/19/2020 | Approved | DANNY TOLENTINO |
| ELECTRICAL-Rough | 5/19/2020 | Approved | DANNY TOLENTINO |
| Green Building Rough | 5/19/2020 | Approved | DANNY TOLENTINO |
| Verify Sprinkler Sign Off | 5/19/2020 | Approved | DANNY TOLENTINO |
| Insulation | 5/21/2020 | Approved | DANNY TOLENTINO |
| Drywall Nailing | 5/29/2020 | Approved | DANNY TOLENTINO |
| Interior/Exterior Lathing | 6/9/2020 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 7/10/2020 | Partial Approval | ROBERT SHELLY |
| Sewer | 9/8/2020 | Approved | JOHN KIDWELL |
| Underground Mechanical | 9/10/2020 | Partial Approval | JOHN KIDWELL |
| HVAC-Final | 11/12/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 11/13/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Final | 11/13/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Final | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| Final | 12/17/2020 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 12/17/2020 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 12/17/2020 | Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 12/17/2020 | Approved | CHRIS CHRISTENSEN |