5401 N ENCINO AVE 91316
Certificate Information: 5401 N ENCINO AVE 91316
- Application / Permit
- 19010-20000-04620
- Plan Check / Job No.
- B19VN17884
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD WITH ATTACHED GARAGE/PATIO & PATIO TRELLIS <Sprinklers Req'd Throughout>
- Permit Issued
- Issued on 2/7/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/20/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | ABDUL CHEGENI |
| Corrections Issued | 10/28/2019 | ABDUL CHEGENI |
| Quality Review Completed | 10/30/2019 | STEVEN KIM |
| Building Plans Picked Up | 11/1/2019 | APPLICANT |
| Green Plans Picked Up | 11/27/2019 | APPLICANT |
| Applicant returned to address corrections | 1/6/2020 | ABDUL CHEGENI |
| Applicant returned to address corrections | 1/17/2020 | ABDUL CHEGENI |
| Plan Check Approved | 1/28/2020 | ABDUL CHEGENI |
| Issued | 2/7/2020 | LADBS |
| CofO in Progress | 7/15/2021 | STEVEN BACK |
| Permit Finaled | 7/20/2021 | JOHN JANSON |
| CofO Issued | 7/20/2021 | JOHN JANSON |
| Permit Finaled | 7/20/2021 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Highway dedication | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Permit | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/27/2019 | ADRIAN CASTRO |
| Green Code | Cleared | 1/3/2020 | MICHAEL AYERS |
| Low Impact Development | Cleared | 1/6/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 1/6/2020 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 1/16/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/17/2020 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 5/6/2020 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 5/22/2020 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 6/16/2020 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 6/24/2020 | Approved | STEVEN BACK |
| ELECTRICAL-Rough | 7/10/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 7/21/2020 | Approved | STEVEN BACK |
| Shower Pan | 7/21/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 7/22/2020 | Corrections Issued | STEVEN BACK |
| Green Building Rough | 7/22/2020 | Not Ready for Inspection | STEVEN BACK |
| MERV13>=Rough | 7/22/2020 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 7/22/2020 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 9/30/2020 | Approved | STEVEN BACK |
| Green Building Rough | 9/30/2020 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 9/30/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 10/15/2020 | Approved | STEVEN BACK |
| Insulation | 10/15/2020 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 10/20/2020 | Partial Approval | STEVEN BACK |
| Interior/Exterior Lathing | 10/22/2020 | Approved | STEVEN BACK |
| Sewer | 10/22/2020 | Approved | STEVEN BACK |
| Grounding or Bonding | 3/15/2021 | Approved | STEVEN BACK |
| ELECTRICAL-Final | 6/16/2021 | Approved | PETER FOLLING |
| HVAC-Final | 6/16/2021 | Approved | PETER FOLLING |
| PLUMBING-Final | 6/16/2021 | Approved | PETER FOLLING |
| Final | 6/22/2021 | Corrections Issued | STEVEN BACK |
| Green Building Final | 6/22/2021 | Approved | STEVEN BACK |
| MERV13>=Final | 6/22/2021 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 6/22/2021 | Not Ready for Inspection | STEVEN BACK |
| Smoke Detectors | 6/22/2021 | Approved | STEVEN BACK |
| Final | 7/15/2021 | OK to Issue CofO | STEVEN BACK |
| Service/Power Release | 7/15/2021 | Approved | STEVEN BACK |