5401 N ENCINO AVE 91316

Certificate Information: 5401 N ENCINO AVE 91316

Application / Permit
19010-20000-04620
Plan Check / Job No.
B19VN17884
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 2-STORY SFD WITH ATTACHED GARAGE/PATIO & PATIO TRELLIS <Sprinklers Req'd Throughout>
Permit Issued
Issued on 2/7/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/20/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 ABDUL CHEGENI
Corrections Issued 10/28/2019 ABDUL CHEGENI
Quality Review Completed 10/30/2019 STEVEN KIM
Building Plans Picked Up 11/1/2019 APPLICANT
Green Plans Picked Up 11/27/2019 APPLICANT
Applicant returned to address corrections 1/6/2020 ABDUL CHEGENI
Applicant returned to address corrections 1/17/2020 ABDUL CHEGENI
Plan Check Approved 1/28/2020 ABDUL CHEGENI
Issued 2/7/2020 LADBS
CofO in Progress 7/15/2021 STEVEN BACK
Permit Finaled 7/20/2021 JOHN JANSON
CofO Issued 7/20/2021 JOHN JANSON
Permit Finaled 7/20/2021 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 11/27/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/27/2019 ADRIAN CASTRO
Highway dedication Cleared 11/27/2019 ADRIAN CASTRO
Permit Cleared 11/27/2019 ADRIAN CASTRO
Sewer availability Cleared 11/27/2019 ADRIAN CASTRO
Green Code Cleared 1/3/2020 MICHAEL AYERS
Low Impact Development Cleared 1/6/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 1/6/2020 THOMAS LANG
Hydrant and Access approval Cleared 1/16/2020 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/17/2020 Partial Approval STEVEN BACK
Footing/Foundation/Slab 5/6/2020 Approved STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 5/22/2020 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval STEVEN BACK
PLUMBING-Rough 6/24/2020 Approved STEVEN BACK
ELECTRICAL-Rough 7/10/2020 Approved STEVEN BACK
HVAC-Rough 7/21/2020 Approved STEVEN BACK
Shower Pan 7/21/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 7/22/2020 Corrections Issued STEVEN BACK
Green Building Rough 7/22/2020 Not Ready for Inspection STEVEN BACK
MERV13>=Rough 7/22/2020 Approved STEVEN BACK
Verify Sprinkler Sign Off 7/22/2020 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Approved STEVEN BACK
BUILDING-Rough-Frame 9/30/2020 Approved STEVEN BACK
Green Building Rough 9/30/2020 Approved STEVEN BACK
Verify Sprinkler Sign Off 9/30/2020 Approved STEVEN BACK
Drywall Nailing 10/15/2020 Approved STEVEN BACK
Insulation 10/15/2020 Partial Approval STEVEN BACK
Interior/Exterior Lathing 10/20/2020 Partial Approval STEVEN BACK
Interior/Exterior Lathing 10/22/2020 Approved STEVEN BACK
Sewer 10/22/2020 Approved STEVEN BACK
Grounding or Bonding 3/15/2021 Approved STEVEN BACK
ELECTRICAL-Final 6/16/2021 Approved PETER FOLLING
HVAC-Final 6/16/2021 Approved PETER FOLLING
PLUMBING-Final 6/16/2021 Approved PETER FOLLING
Final 6/22/2021 Corrections Issued STEVEN BACK
Green Building Final 6/22/2021 Approved STEVEN BACK
MERV13>=Final 6/22/2021 Approved STEVEN BACK
SGSOV-Seismic Gas S/O Valve 6/22/2021 SGSOV Approved STEVEN BACK
Service/Power Release 6/22/2021 Not Ready for Inspection STEVEN BACK
Smoke Detectors 6/22/2021 Approved STEVEN BACK
Final 7/15/2021 OK to Issue CofO STEVEN BACK
Service/Power Release 7/15/2021 Approved STEVEN BACK