16706 W BLACKHAWK ST 91344

Certificate Information: 16706 W BLACKHAWK ST 91344

Application / Permit
19010-20000-04599
Plan Check / Job No.
B19VN17766
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER AB494 & SB229 W/ ATTACHED GARAGE (NPFA-13D FIRE SPRINKLERS THROUGHOUT) PER WFPP
Permit Issued
Issued on 1/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 11/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 11/7/2019 NILOOFAR MEHRAIN
Green Plans Picked Up 11/13/2019 APPLICANT
Corrections Issued 11/20/2019 NILOOFAR MEHRAIN
Quality Review Completed 11/20/2019 GUANG MIN TUNG
Building Plans Picked Up 12/11/2019 APPLICANT
Applicant returned to address corrections 1/15/2020 NILOOFAR MEHRAIN
Plan Check Approved 1/16/2020 NILOOFAR MEHRAIN
Issued 1/21/2020 LADBS
CofO in Progress 11/9/2020 MARK JOHNSON
CofO Issued 11/23/2020 MICHAEL SMITH
Permit Finaled 11/23/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 1/14/2020 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 1/14/2020 LEE GUILBEAUX
Low Impact Development Cleared 1/14/2020 ORVAL HERNANDEZ-MARCI
Permit Cleared 1/14/2020 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 1/14/2020 JOHN TRIANTAFYLLOS
Sewer availability Cleared 1/14/2020 LEE GUILBEAUX
Hydrant and Access approval Cleared 1/15/2020 GEORGE SUCHAND
Green Code Cleared 1/16/2020 MICHAEL AYERS
Trees in Parkway Cleared 1/17/2020 ADRIAN SANCHEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/27/2020 Partial Approval MARK JOHNSON
Sewer 1/27/2020 Approved MARK JOHNSON
Underground Mechanical 1/27/2020 Approved MARK JOHNSON
Footing/Foundation/Slab 2/5/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 4/3/2020 Partial Approval MARK JOHNSON
BUILDING-Rough-Frame 4/22/2020 Not Ready for Inspection MARK JOHNSON
ELECTRICAL-Rough 4/22/2020 Corrections Issued MARK JOHNSON
Green Building Rough 4/22/2020 Approved MARK JOHNSON
HVAC-Rough 4/22/2020 Partial Approval MARK JOHNSON
Interior/Exterior Lathing 4/22/2020 Not Ready for Inspection MARK JOHNSON
PLUMBING-Rough 4/22/2020 Corrections Issued MARK JOHNSON
Verify Sprinkler Sign Off 4/22/2020 Approved MARK JOHNSON
Wood Frame 4/22/2020 Not Ready for Inspection MARK JOHNSON
BUILDING-Rough-Frame 4/27/2020 Approved MARK JOHNSON
Rough-Elec/Plmb/HVAC 4/27/2020 Approved MARK JOHNSON
Insulation 4/28/2020 Corrections Issued DANIEL ORRANTE
Drywall Nailing 4/30/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 5/12/2020 Approved GREGG CUMMINGS
Shower Pan 5/12/2020 Approved GREGG CUMMINGS
Final 10/19/2020 Corrections Issued MARK JOHNSON
Green Building Final 10/19/2020 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved MARK JOHNSON
Service/Power Release 10/19/2020 Not Ready for Inspection MARK JOHNSON
Smoke Detectors 10/19/2020 Approved MARK JOHNSON
Final 10/26/2020 Not Ready for Inspection MARK JOHNSON
Special/Order Compliance 10/29/2020 Not Ready for Inspection MARK JOHNSON
Final 11/9/2020 OK to Issue CofO MARK JOHNSON
Service/Power Release 11/9/2020 Approved MARK JOHNSON