946 N EMBURY ST 90272
Certificate Information: 946 N EMBURY ST 90272
- Application / Permit
- 19010-20000-04585
- Plan Check / Job No.
- B19VN17694
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 79'-7-3/8" X 30' 2 STORY SFD WITH 19'11" X 19' 7-1/4" ATTACHED TWO CAR GARAGE AND NEW 14' X 12'6" ATTACHED OPEN TRELLIS , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 2/14/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/6/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Green Plans Picked Up | 10/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | RARES BODEA |
| Corrections Issued | 10/27/2019 | RARES BODEA |
| Quality Review Completed | 10/29/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/31/2019 | APPLICANT |
| Applicant returned to address corrections | 12/5/2019 | RARES BODEA |
| Plan Check Approved | 1/22/2020 | RARES BODEA |
| Issued | 2/14/2020 | LADBS |
| CofO in Progress | 6/16/2021 | JOHN KIDWELL |
| CofO Issued | 7/6/2021 | VINCENT COTTON |
| Permit Finaled | 7/6/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 11/14/2019 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | GUILLERMO PETRA |
| Permit | Cleared | 11/14/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/14/2019 | GUILLERMO PETRA |
| Low Impact Development | Cleared | 12/3/2019 | MITESH PATEL |
| GPI Written Notices | Cleared | 12/5/2019 | RARES BODEA |
| Grading Pre-Inspection | Cleared | 12/5/2019 | RARES BODEA |
| Green Code | Cleared | 12/5/2019 | AARON COSTA |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | JOHN LIN |
| Trees in Parkway | Cleared | 12/9/2019 | JOHN KIM |
| Hydrant and Access approval | Cleared | 12/10/2019 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno S; Lic. No.: S3454 | 25531 PRADO DELAS BELLOTAS CALABASAS, CA 91302 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/1/2020 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 4/3/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/3/2020 | Partial Approval | DANNY TOLENTINO |
| Underground Mechanical | 4/3/2020 | Partial Approval | DANNY TOLENTINO |
| Footing/Foundation/Slab | 4/16/2020 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2020 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Not Ready for Inspection | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | JOHN KIDWELL |
| HVAC-Rough | 6/9/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 6/9/2020 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 6/19/2020 | Partial Approval | TIM CHRISTENSEN |
| Shower Pan | 6/19/2020 | Partial Approval | TIM CHRISTENSEN |
| Interior/Exterior Lathing | 6/23/2020 | Partial Approval | JOHN KIDWELL |
| ELECTRICAL-Rough | 6/25/2020 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 6/30/2020 | Partial Approval | JOHN KIDWELL |
| Drywall Nailing | 7/8/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/8/2020 | Approved | JOHN KIDWELL |
| Insulation | 7/8/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Final | 1/14/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 1/14/2021 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 1/14/2021 | Approved | JOHN KIDWELL |
| Service/Power Release | 3/5/2021 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 6/15/2021 | Approved | JOHN KIDWELL |
| Final | 6/15/2021 | OK to Issue CofO | JOHN KIDWELL |
| Footing/Foundation/Slab | 6/15/2021 | Approved | JOHN KIDWELL |
| Green Building Final | 6/15/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 6/15/2021 | Approved | JOHN KIDWELL |
| Smoke Detectors | 6/15/2021 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 6/15/2021 | Approved | JOHN KIDWELL |