946 N EMBURY ST 90272

Certificate Information: 946 N EMBURY ST 90272

Application / Permit
19010-20000-04585
Plan Check / Job No.
B19VN17694
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 79'-7-3/8" X 30' 2 STORY SFD WITH 19'11" X 19' 7-1/4" ATTACHED TWO CAR GARAGE AND NEW 14' X 12'6" ATTACHED OPEN TRELLIS , NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 2/14/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/6/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2019 APPLICANT
Green Plans Picked Up 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 RARES BODEA
Corrections Issued 10/27/2019 RARES BODEA
Quality Review Completed 10/29/2019 GUANG MIN TUNG
Building Plans Picked Up 10/31/2019 APPLICANT
Applicant returned to address corrections 12/5/2019 RARES BODEA
Plan Check Approved 1/22/2020 RARES BODEA
Issued 2/14/2020 LADBS
CofO in Progress 6/16/2021 JOHN KIDWELL
CofO Issued 7/6/2021 VINCENT COTTON
Permit Finaled 7/6/2021 VINCENT COTTON

Permit Application Clearance Information

Address approval Cleared 11/14/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/14/2019 GUILLERMO PETRA
Permit Cleared 11/14/2019 GUILLERMO PETRA
Sewer availability Cleared 11/14/2019 GUILLERMO PETRA
Low Impact Development Cleared 12/3/2019 MITESH PATEL
GPI Written Notices Cleared 12/5/2019 RARES BODEA
Grading Pre-Inspection Cleared 12/5/2019 RARES BODEA
Green Code Cleared 12/5/2019 AARON COSTA
Roof/Waste drainage to street Cleared 12/5/2019 JOHN LIN
Trees in Parkway Cleared 12/9/2019 JOHN KIM
Hydrant and Access approval Cleared 12/10/2019 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

TEMISTOCLES CAAL, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI
JESUS PINEDA, (213) 653-1908 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/1/2020 Partial Approval DANNY TOLENTINO
Excavation/Setback/Form/Re-Bar 4/3/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/3/2020 Partial Approval DANNY TOLENTINO
Underground Mechanical 4/3/2020 Partial Approval DANNY TOLENTINO
Footing/Foundation/Slab 4/16/2020 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 5/1/2020 Partial Approval DANNY TOLENTINO
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Not Ready for Inspection KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval JOHN KIDWELL
HVAC-Rough 6/9/2020 Not Ready for Inspection JOHN KIDWELL
PLUMBING-Rough 6/9/2020 Approved JOHN KIDWELL
Floor/Roof Diaphrgm/Shear Wall 6/19/2020 Partial Approval TIM CHRISTENSEN
Shower Pan 6/19/2020 Partial Approval TIM CHRISTENSEN
Interior/Exterior Lathing 6/23/2020 Partial Approval JOHN KIDWELL
ELECTRICAL-Rough 6/25/2020 Approved JOHN KIDWELL
Interior/Exterior Lathing 6/30/2020 Partial Approval JOHN KIDWELL
Drywall Nailing 7/8/2020 Approved JOHN KIDWELL
Green Building Rough 7/8/2020 Approved JOHN KIDWELL
Insulation 7/8/2020 Approved JOHN KIDWELL
ELECTRICAL-Final 1/14/2021 Approved JOHN KIDWELL
HVAC-Final 1/14/2021 Approved JOHN KIDWELL
PLUMBING-Final 1/14/2021 Approved JOHN KIDWELL
Service/Power Release 3/5/2021 Not Ready for Inspection JOHN KIDWELL
BUILDING-Rough-Frame 6/15/2021 Approved JOHN KIDWELL
Final 6/15/2021 OK to Issue CofO JOHN KIDWELL
Footing/Foundation/Slab 6/15/2021 Approved JOHN KIDWELL
Green Building Final 6/15/2021 Approved JOHN KIDWELL
SGSOV-Seismic Gas S/O Valve 6/15/2021 SGSOV Approved JOHN KIDWELL
Service/Power Release 6/15/2021 Approved JOHN KIDWELL
Smoke Detectors 6/15/2021 Approved JOHN KIDWELL
Verify Sprinkler Sign Off 6/15/2021 Approved JOHN KIDWELL