13443 W GALEWOOD ST 91423
Certificate Information: 13443 W GALEWOOD ST 91423
- Application / Permit
- 19010-20000-04576
- Plan Check / Job No.
- B19VN17631
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- NEW 19'-6" X 13' L-SHAPED DETACHED RECREATION ROOM WITH EXTERIOR ACCESS FULL BATHROOM. WORK PER ENGINEER.
- Permit Issued
- Issued on 8/26/2020
- Issuing Office
- Current Status
- CofO Issued on 6/30/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/16/2019 | ROSENDO MEDINA |
| Corrections Issued | 10/21/2019 | ROSENDO MEDINA |
| Building Plans Picked Up | 10/24/2019 | APPLICANT |
| Applicant returned to address corrections | 8/21/2020 | ROSENDO MEDINA |
| Plan Check Approved | 8/25/2020 | ROSENDO MEDINA |
| Issued | 8/26/2020 | APPLICANT |
| CofO in Progress | 6/14/2021 | DANIEL ORRANTE |
| Permit Finaled | 6/30/2021 | MICHAEL SMITH |
| CofO Issued | 6/30/2021 | MICHAEL SMITH |
| Permit Finaled | 6/30/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 10/24/2019 | RIDWAN HARDY |
| Construction within easement | Cleared | 10/24/2019 | RIDWAN HARDY |
| Roof/Waste drainage to street | Cleared | 7/9/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 7/9/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 8/4/2020 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 8/25/2020 | ROSENDO MEDINA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/21/2020 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 10/8/2020 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 10/21/2020 | Partial Approval | CHARLES POWELL |
| ELECTRICAL-Rough | 10/21/2020 | Partial Approval | CHARLES POWELL |
| Green Building Rough | 10/21/2020 | Not Ready for Inspection | CHARLES POWELL |
| PLUMBING-Rough | 10/21/2020 | Approved | CHARLES POWELL |
| Verify Sprinkler Sign Off | 10/21/2020 | Not Ready for Inspection | CHARLES POWELL |
| Insulation | 10/26/2020 | Approved | CHARLES POWELL |
| Interior/Exterior Lathing | 10/26/2020 | Approved | CHARLES POWELL |
| Verify Sprinkler Sign Off | 10/26/2020 | Approved | CHARLES POWELL |
| Drywall Nailing | 11/4/2020 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/4/2020 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/4/2020 | Partial Approval | ARAM AVEDISIAN |
| Shower Pan | 11/4/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 2/1/2021 | Partial Approval | CHARLES POWELL |
| PLUMBING-Final | 2/1/2021 | Approved | CHARLES POWELL |
| BUILDING-Rough-Frame | 3/12/2021 | Approved | CHARLES POWELL |
| Final | 3/12/2021 | Corrections Issued | CHARLES POWELL |
| Green Building Final | 3/12/2021 | Approved | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Approved | CHARLES POWELL |
| Service/Power Release | 3/12/2021 | Approved | CHARLES POWELL |
| Smoke Detectors | 3/12/2021 | Approved | CHARLES POWELL |
| Final | 6/14/2021 | OK to Issue CofO | DANIEL ORRANTE |