17319 W MAGNOLIA BLVD 91316
Certificate Information: 17319 W MAGNOLIA BLVD 91316
- Application / Permit
- 19010-20000-04573
- Plan Check / Job No.
- B19VN17623
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Patio Cover
- Work Description
- NEW 13' X 18' DETACHED PATIO COVER , ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | RARES BODEA |
| Corrections Issued | 10/26/2019 | RARES BODEA |
| Quality Review Completed | 10/29/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/29/2019 | APPLICANT |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Plan Check Approved | 2/6/2020 | RARES BODEA |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 2/24/2021 | STEVEN BACK |
| Permit Finaled | 3/3/2021 | MICHAEL SMITH |
| CofO Issued | 3/3/2021 | MICHAEL SMITH |
| Permit Finaled | 3/3/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | MARKOS PEREZ-BRAN |
| Low Impact Development | Cleared | 11/14/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 11/14/2019 | MARKOS PEREZ-BRAN |
| ZA Case | Cleared | 1/9/2020 | HERMINIGILDO AGUSTIN |
| ZA Case | Cleared | 1/9/2020 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2020 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 4/1/2020 | Partial Approval | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 4/21/2020 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 4/21/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 6/29/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 6/29/2020 | Approved | STEVEN BACK |
| Verify Sprinkler Sign Off | 6/29/2020 | Approved | STEVEN BACK |
| Insulation | 7/1/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 1/20/2021 | No Access for Inspection | PAUL CHOPP |
| Final | 1/20/2021 | No Access for Inspection | PAUL CHOPP |
| SGSOV-Seismic Gas S/O Valve | 1/20/2021 | SGSOV Not Ready | PAUL CHOPP |
| Service/Power Release | 1/20/2021 | No Access for Inspection | PAUL CHOPP |
| Smoke Detectors | 1/20/2021 | No Access for Inspection | PAUL CHOPP |
| Drywall Nailing | 2/2/2021 | Approved | STEVEN BACK |
| Final | 2/2/2021 | Not Ready for Inspection | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 2/2/2021 | SGSOV Approved | STEVEN BACK |
| Service/Power Release | 2/2/2021 | Not Required | STEVEN BACK |
| Smoke Detectors | 2/2/2021 | Approved | STEVEN BACK |
| Final | 2/5/2021 | Not Ready for Inspection | STEVEN BACK |
| Final | 2/24/2021 | OK to Issue CofO | STEVEN BACK |