19148 N LEMAY ST 91335
Certificate Information: 19148 N LEMAY ST 91335
- Application / Permit
- 19010-20000-04554
- Plan Check / Job No.
- B19VN17557
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 40' 0" X 20'0" ACCESSORY DWELLING UNIT PER AB 494 AND SB 220 ALL WORK PER WFPP
- Permit Issued
- Issued on 1/27/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/12/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 11/4/2019 | SEWADA ZADOORIAN MILAGARDI |
| Green Plans Picked Up | 11/6/2019 | APPLICANT |
| Quality Review Completed | 11/15/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 11/20/2019 | APPLICANT |
| Applicant returned to address corrections | 1/13/2020 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 1/27/2020 | SEWADA ZADOORAN MILAGARDI |
| Issued | 1/27/2020 | LADBS |
| CofO in Progress | 3/10/2021 | VINCENT HANLEY |
| CofO Issued | 3/12/2021 | RONALD MYRICK |
| Permit Finaled | 3/12/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 12/4/2019 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2019 | THOMAS LANG |
| Sewer availability | Cleared | 12/4/2019 | THOMAS LANG |
| Green Code | Cleared | 1/13/2020 | AARON COSTA |
| Low Impact Development | Cleared | 1/13/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 1/13/2020 | CELINA MORENO |
| ZI | Cleared | 1/15/2020 | TERRI OSBORNE |
| Construction near power lines | Cleared | 1/16/2020 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 1/27/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | N E Construction; Lic. No.: 696948-B | 22817 VENTURA BLVD #930 WOODLAND HILLS, CA 91364 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/21/2020 | Order to Comply Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/28/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 3/25/2020 | Approved | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/25/2020 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 3/25/2020 | Approved | VINCENT HANLEY |
| HVAC-Rough | 4/20/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Insulation | 4/20/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| Interior/Exterior Lathing | 4/20/2020 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Rough | 4/22/2020 | Approved | VINCENT HANLEY |
| Insulation | 4/22/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 4/22/2020 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 4/22/2020 | Approved | VINCENT HANLEY |
| Drywall Nailing | 5/1/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/1/2020 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 5/1/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/1/2020 | Approved | VINCENT HANLEY |
| Sewer | 9/1/2020 | Approved | VINCENT HANLEY |
| Underground Mechanical | 9/1/2020 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/22/2020 | Not Ready for Inspection | STEVEN BACK |
| Final | 10/22/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 10/22/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 10/22/2020 | SGSOV Not Ready | STEVEN BACK |
| Service/Power Release | 10/22/2020 | Corrections Issued | STEVEN BACK |
| Smoke Detectors | 10/22/2020 | Not Ready for Inspection | STEVEN BACK |
| Verify Sprinkler Sign Off | 10/22/2020 | Not Ready for Inspection | STEVEN BACK |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | VINCENT HANLEY |
| Final | 12/8/2020 | Corrections Issued | VINCENT HANLEY |
| Green Building Final | 12/8/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 12/8/2020 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 12/8/2020 | Not Required | VINCENT HANLEY |
| Smoke Detectors | 12/8/2020 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 12/8/2020 | Not Ready for Inspection | VINCENT HANLEY |
| ELECTRICAL-Final | 3/10/2021 | Approved | VINCENT HANLEY |
| Final | 3/10/2021 | OK to Issue CofO | VINCENT HANLEY |
| HVAC-Final | 3/10/2021 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 3/10/2021 | Approved | VINCENT HANLEY |